Home / Browse projects / Pune, Maharashtra / World One Solitaire World

Registered No litigation declared Residential / Group Housing project

World One Solitaire World

By Classic Promoters and Builders Private Limited

RG-MH-23997 · RERA P52100004877 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 36 months
  • 3 extensions taken
  • Rs 160.00 crore secured on the land, in favour of CAPRI GLOBAL CAPITAL LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
18 of 26Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
54 of 185Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 411 documents Report an error

World One Solitaire World is a Residential / Group Housing project by Classic Promoters and Builders Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100004877 on 9 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 131 of the 185 units on this registration are recorded sold or booked, and 18 of 26 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameWorld One Solitaire World
  • TypeResidential / Group Housing
  • Location
    • Pune
    • Bibwewadi
    • Pune (M Corp.)
    • Pune City
    • 411037
  • Pincode411037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004877
  • ReraGenie IDRG-MH-23997

Builder

  • NameClassic Promoters and Builders Private Limited
  • Entity typeCompany
  • CINU70101MH1988PTC047131
  • GSTIN27AABCC1200C1ZN
  • Managing DirectorAshok Dhanraj Chordia
  • Other registrations14 more →
  • Completed4 of 15
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed411 files

Current status

71%131 of 185 units booked
93.4%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building -1 World One Up to 16th FloorNA19171010101
Building -2 World One -17th to 30th FLNA141484084
Building 3NA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 26 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Building -1 World One Up to 16th Floor100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building -2 World One -17th to 30th FL100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes70%
Street LightingYes5%
Community BuildingsYesNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed824

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots824
Closed/Covered824

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,076 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofCAPRI GLOBAL CAPITAL LIMITED
Secured amountRs 160.00 crore
CERSAI search filedYes
Declared on13 Aug 2025
LandownerVillageDistrict
M/s Shah Promoters and DevelopersPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI32176.0
Proposed, not sanctioned32,176 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShirole Bhavan Pmt Building Jangli Maharaj Road, Pune, Dist -Pune, Maharashtra
Estimated costRs 134.06 cr
Cost incurredRs 125.18 cr
Work done93.38%
BuildingWingEstimatedIncurred
Building -1 World One Up to 16th FloorNARs 65.97 crRs 61.85 cr
Building -2 World One -17th to 30th FLNARs 54.11 crRs 50.73 cr
-NARs 13.98 crRs 12.61 cr

Certifying professionals and partners12

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVenkataramanan Associates
ArchitectFourth Dimension Architects PVT LTD
ArchitectANA Consortium Pvt Ltd
EngineerJW CONSULTANTS LLP
EngineerShivprasad Kale
EngineerIshwar Ghodke
EngineerSwapnil Sonawane
EngineerSushil Bhoi
Chartered AccountantBogati & Co.
Chartered AccountantGMKS & Co.
Chartered AccountantRSVA & Co
Chartered AccountantSPAK & Co
PartnerRole in project
Classic Promoters and Builders Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017516Dec 2023 → Dec 2024

Reason as filed by the promoterdue to the COVID-19 pandemic, we faced several challenges that adversely affected the construction activities and the sales of the project. Some of these challenges were: • Lack of availability of labour contractors as many of them migrated back to their native places during the lockdown. • Disruption of supply chain of essential construction materials such as cement, steel, sand, etc. • Poor market condition reduced the demand and sales of residential properties and affected our cash flow and liquidity. These factors were beyond our control and caused a significant delay in the completion of

EXT52100025345Dec 2023 → Dec 2025

Reason as filed by the promoter1. We Classic Promoters and Builders Private Limited are developing the said Project which is part of a larger layout. 2. We state that the construction and development of the said Project got delayed due to the fact that after commencement of construction of the same, we faced numerous challenges as the Project layout was unforeseeably surrounded with the illegal huts and slum encroachments which were causing obstruction and unwarranted delays in carrying out smooth construction activities. We state that to deal with the same, we faced a lot of inconvenience and removing the illegal encroachm

EA13012619432Dec 2023 → Dec 2026

Reason as filed by the promoterAs per order of the Hon'ble Chairman (MahaRERA) Dated 09/03/2026 we request you kindly to grant us extension till 31/12/2026.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000033462Atul Rasiklal MehtaClassic Promoters and Builders Pvt. Ltd.23/09/2019
CC005000000167446UMESH RAMESH JAINCLASSIC PROMOTERS AND BUILDERS PVT. LTD.20/08/2022
CC005000000177735UMESH RAMESH JAINCLASSIC PROMOTERS AND BUILDERS PVT.LTD01/11/2022
CC12503527Nutan Atish SonigaraClassic Promoters and Builders Private Limited03/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed411

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 411 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - World One - SW- Jun 26.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 World One - Jun 26.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 - World One -Jun 26.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A World One - Mar 26.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 - World One - Mar 26.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - World One - Mar 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 - World One - Mar 26.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 - World One - Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - World One - Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - World One - Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 - World One - Sept 2025.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 - World One - Sept 2025.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3 - World One - Sept 2025.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: World One -Form 5-FY 24-25.pdf1 Sep 2025
Withdrawal Update Form 1File: Form 1 SW-One- Jun-25.pdf21 Jul 2025
Withdrawal Update Form 2File: Form 2 SW-One- Jun-25.pdf21 Jul 2025
Withdrawal Update Form 3File: Form 3 SW One Jun-25.pdf21 Jul 2025
Withdrawal Update Form 1File: Form 1 SW-One- Jun-25.pdf19 Jul 2025
Withdrawal Update Form 1File: Form 1 SW-One- Jun-25.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2 SW-One- Jun-25.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2 SW-One- Jun-25.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 SW One Jun-25.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 SW One Jun-25.pdf19 Jul 2025
Withdrawal Update Form 1File: Form 1 - World One - Mar 25.pdf11 Jul 2025
Withdrawal Update Form 2File: Form 2 - World One - Mar 25.pdf11 Jul 2025
Withdrawal Update Form 3File: Form 3_March 2025.pdf11 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - World One - Mar 25.pdf24 Apr 2025
Certificates of CA (Form 3)File: Form 3- World One - Mar 25_compressed.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- World One - Mar 25.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Disclosure - World One - Mar 25.pdf24 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - World One - Mar 25.pdf24 Apr 2025
Certificates of CA (Form 3)File: Form 3 - World One - Dec 24.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - World One - Dec 24.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Disclosure - World Onw - Dec 24.pdf20 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - World One - Dec 24.pdf18 Jan 2025
Details of encumbrancesFile: World One-SW - Encumbrance - 7-01-2025.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: World One - SW - FY 23-24 - Form 5.pdf20 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: World One - FY 23-24 - Form 5.pdf17 Dec 2024
Certificates of CA (Form 3)File: Form -3- World One - Sept 2023.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3_World 1_Dec-23.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 -World One-SW-Mar 24.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 - World One - Jun 24.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 -World One-SW-Sept 24.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2- World One - Sept 2023.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 -World One-SW-Sept 24.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 -World One-SW-Jun 24.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 -World One-SW-Mar 24.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_World 1_Dec-23.pdf12 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Disclosure World 1- SEP 24.pdf12 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- World One - Sept 24.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: World 1 June 24 Sold Disclosure.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Disclosure - W1- Bldg -1-2.pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- World One - Jun 2024.pdf21 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Disclosure - World One - Mar 24.pdf5 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1- Mar 24 - World One.pdf18 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A - Mar 24 - World One.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: World One -Dec 23 Sold Disclosure.pdf20 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- World One - Dec 23.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - World One - Dec 23.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: World One - Sept 23 Sold Disclosure.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - World One FY 22-23.pdf13 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1- World One - Sept 2023.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - SW World One - Sept 2023.pdf6 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 SW W1.pdf14 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Feb-18.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: May-18.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aug-18.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nov-18.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Feb-19.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: May-19.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: July-19.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nov-19.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Feb-20.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: May-20.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aug-20.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nov-20.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Feb-21.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June-21.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep-21.pdf4 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec-21.pdf4 Sep 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Avalon C-3Pimpri Chinchwad Pune 41101247CompletedDec 2019Late, Feb 2020

How this compares with Pune

71%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep World One Solitaire World on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bibwewadi13,700+ in Pune

2 kmWorld One Solitaire WorlCompleted 39Lapsed / revoked 26Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 128 registered projects within 2 km.

Builder: Classic Promoters and Builders Private Limited

Classic Promoters and Builders Private Limited has 15 registrations on MahaRERA, including AVALON CITY C-3 and MUDRA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if World One Solitaire World is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of World One Solitaire World?

The registered promoter entity is Classic Promoters and Builders Private Limited, a company as per the filing. Its CIN U70101MH1988PTC047131 and GSTIN 27AABCC1200C1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in World One Solitaire World?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against World One Solitaire World?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for World One Solitaire World?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at World One Solitaire World?

The professionals named in the filing: Architect: Venkataramanan Associates; Architect: Fourth Dimension Architects PVT LTD; Architect: ANA Consortium Pvt Ltd; Engineer: JW CONSULTANTS LLP; Engineer: Shivprasad Kale; Engineer: Ishwar Ghodke. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in World One Solitaire World?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About World One Solitaire World. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save World One Solitaire World to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.