Home / Browse projects / Palghar, Maharashtra / WOLLYWOOD PHASE IV

Registered No litigation declared Residential / Group Housing project

WOLLYWOOD PHASE IV

By NIRVANA LIFESTYLE VENTURES

RG-MH-65845 · RERA P99000016676 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
0 of 836Construction stages doneacross 76 buildings; furthest along: Excavation, 0%
1Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

WOLLYWOOD PHASE IV is a Residential / Group Housing project by NIRVANA LIFESTYLE VENTURES in Palghar, Maharashtra, registered with MahaRERA as P99000016676 on 5 Jun 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameWOLLYWOOD PHASE IV
  • TypeResidential / Group Housing
  • Location
    • BHIWANDI WADA ROAD
    • GATES BUDRUK
    • Gates Bk.
    • Vada
    • Palghar
    • 421303
  • Pincode421303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000016676
  • ReraGenie IDRG-MH-65845

Builder

  • NameNIRVANA LIFESTYLE VENTURES
  • Entity typePartnership
  • PartnersSARKAR SHIVAJIRAO NIMBALKAR, PRAVIN KUMAR JUGAL KISHORE AGARWAL, PRAVIN KUMAR JUGAL KISHORE AGARWAL, PUNIT PRAVIN KUMAR AGARWAL, BHARAT BALU KOR
  • Other registrations4 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2018First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Jun 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
  • Buildings76 building records
  • Documents filed86 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VILLA 3ANA20000
VILLA 3BNA20000
VILLA 4ANA20000
VILLA 4BNA20000
VILLA 5ANA20000
VILLA 5BNA20000
VILLA 6NA20000
VILLA 7ANA20000
VILLA 7BNA20000
VILLA 8ANA20000
VILLA 8BNA20000
VILLA 9ANA20000
VILLA 9BNA20000
VILLA 10ANA20000
VILLA 10BNA20000
VILLA 11ANA20000
VILLA 11BNA20000
VILLA 12ANA20000
VILLA 12BNA20000
VILLA 13ANA20000
VILLA 13BNA20000
VILLA 14ANA20000
VILLA 14BNA20000
VILLA 15ANA20000
VILLA 15BNA20000
VILLA 16ANA20000
VILLA 16BNA20000
VILLA 23ANA20000
VILLA 23BNA20000
VILLA 27BNA20000
VILLA 27ANA20000
VILLA 29ANA20000
VILLA 29BNA20000
VILLA 30ANA20000
VILLA 30BNA20000
VILLA 38ANA20000
VILLA 38BNA20000
VILLA 39ANA20000
VILLA 39BNA20000
VILLA 41ANA20000
VILLA 41BNA20000
VILLA 42ANA20000
VILLA 42BNA20000
VILLA 43ANA20000
VILLA 43BNA20000
VILLA 44ANA20000
VILLA 44BNA20000
VILLA 90NA20000
VILLA 91ANA20000
VILLA 91BNA20000
VILLA 93ANA20000
VILLA 93BNA20000
VILLA 94ANA20000
VILLA 94BNA20000
VILLA 95ANA20000
VILLA 95BNA20000
VILLA 96ANA20000
VILLA 96BNA20000
VILLA 98ANA20000
VILLA 98BNA20000
VILLA 99NA20000
VILLA 100NA20000
VILLA 101ANA20000
VILLA 101BNA20000
VILLA 102ANA20000
VILLA 102BNA20000
VILLA 103ANA20000
VILLA 103BNA20000
VILLA 104ANA20000
VILLA 104BNA20000
VILLA 105ANA20000
VILLA 105BNA20000
VILLA 106ANA20000
VILLA 106BNA20000
VILLA 107ANA20000
VILLA 107BNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 76 buildings; the table lists the first 20.

0 of 836 construction stages are filed complete across 76 buildings. The stage furthest along is Excavation, at 0%.

VILLA 3A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 3B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 4A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 4B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 5A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 5B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 7A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 7B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 8A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 8B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 9A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 9B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 10A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 10B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 11A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 11B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 12A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 12B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA 13A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes60%
Street LightingYes25%
Community BuildingsYes85%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes20%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Open Space76
BuildingOpen SpaceTotal
VILLA 3A11
VILLA 3B11
VILLA 4A11
VILLA 4B11
VILLA 5A11
VILLA 5B11
VILLA 611
VILLA 7A11
VILLA 7B11
VILLA 8A11
VILLA 8B11
VILLA 9A11
VILLA 9B11
VILLA 10A11
VILLA 10B11
VILLA 11A11
VILLA 11B11
VILLA 12A11
VILLA 12B11
VILLA 13A11
VILLA 13B11
VILLA 14A11
VILLA 14B11
VILLA 15A11
VILLA 15B11
VILLA 16A11
VILLA 16B11
VILLA 23A11
VILLA 23B11
VILLA 27B11
VILLA 27A11
VILLA 29A11
VILLA 29B11
VILLA 30A11
VILLA 30B11
VILLA 38A11
VILLA 38B11
VILLA 39A11
VILLA 39B11
VILLA 41A11
VILLA 41B11
VILLA 42A11
VILLA 42B11
VILLA 43A11
VILLA 43B11
VILLA 44A11
VILLA 44B11
VILLA 9011
VILLA 91A11
VILLA 91B11
VILLA 93A11
VILLA 93B11
VILLA 94A11
VILLA 94B11
VILLA 95A11
VILLA 95B11
VILLA 96A11
VILLA 96B11
VILLA 98A11
VILLA 98B11
VILLA 9911
VILLA 10011
VILLA 101A11
VILLA 101B11
VILLA 102A11
VILLA 102B11
VILLA 103A11
VILLA 103B11
VILLA 104A11
VILLA 104B11
VILLA 105A11
VILLA 105B11
VILLA 106A11
VILLA 106B11
VILLA 107A11
VILLA 107B11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,671 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jun 2026

Approvals and building plan

Sanctioning authorityTOWN PLANNING
Permissible FSI7723.13
Proposed, not sanctioned7,723 sq m
Buildings approved76
Buildings sanctioned76

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 TO 5 NEW GITANJALI SOCIETY RAHEJA TOWNSHIP UPPER GOVIND NAGAR MUMBAI 400097

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEEPAK HIREMATH ASSOCIATES
EngineerNaik Associates
Chartered AccountantSanjay R Soni & Associate
PartnerRole in project
NIRVANA LIFESTYLE VENTURES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000027105Dec 2024 → Dec 2026

Reason as filed by the promoterThere has been a severe loss of materials and labour due to the flood in the project land resulting in delay. Due to lock down the construction work came to a halt for months apart from the labour migrancy to the native state resulting in shortage of labour. Apart from it due to lock resulting in loss in business and jobs

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400877GAURAV BHANWARLAL GHATAWATNIRVANA LIFESTYLE VENTURES23/11/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1(architect certificate) Dec 25 Ready.pdf22 Jun 2026
Form 2File: Form 2 Naik associates Dec 25 Ready.pdf22 Jun 2026
Form 3File: Form 3 (CA)Certificate NLV Dec 25 phase IV.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked inventory - Wollywood phase IV Sept 25.pdf22 Jun 2026
Form 1File: Form 1(architect certificate) Mar 26 Ready.pdf22 Jun 2026
Form 2File: Form 2 Naik associates Mar 26 Ready.pdf22 Jun 2026
Form 3File: Form 3 (CA)Certificate NLV Mar 26 phase IV.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked inventory - Wollywood phase IV Sept 25.pdf22 Jun 2026
Form 1File: Form 1 WW ph IV Sept 25 Compress.pdf6 Feb 2026
Form 2File: Form 2 WW IV Sept 25.pdf6 Feb 2026
Form 3File: Form 3 nirvana lifestyle phase 4 Signed.pdf6 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked inventory - Wollywood phase IV Sept 25.pdf6 Feb 2026
Form 1File: Form 1(architect certificate) Mar 25 Ready.pdf5 Feb 2026
Form 2File: Form 2 Naik associates Mar 25 Ready.pdf5 Feb 2026
Form 3File: Form 3 WW phs IV Mar 25.pdf5 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold WW phs IV.pdf5 Feb 2026
Form 1File: Form 1(architect certificate).pdf5 Feb 2026
Form 2File: Form 2 Naik associates.pdf5 Feb 2026
Form 3File: Form 3 WW phs IV.pdf5 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold WW phs IV.pdf5 Feb 2026
Certificates of CA (Form 3)File: Rera June 2023.pdf5 Jun 2025
Certificates of CA (Form 3)File: September 2023.pdf5 Jun 2025
Certificates of CA (Form 3)File: December 2023.pdf5 Jun 2025
Certificates of CA (Form 3)File: WW Phs IV Jun 24.pdf5 Jun 2025
Certificates of CA (Form 3)File: WW phs IV Mar 25.pdf5 Jun 2025
Certificates of CA (Form 3)File: WW phs IV Sept 24.pdf5 Jun 2025
Certificates of CA (Form 3)File: WW Phs IV Dec 24.pdf5 Jun 2025
Certificates of CA (Form 3)File: WW phs IV Mar 25.pdf5 Jun 2025
Certificates of CA (Form 3)File: March 2024.pdf5 Jun 2025
Details of encumbrances concerned to FinanceFile: legal Encumbrance Certificate.pdf4 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Dec 24.pdf4 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Mar 25 Ready.pdf4 Jun 2025
Certificates of CA (Form 3)File: Form 3 Dec 24.pdf4 Jun 2025
Certificates of CA (Form 3)File: Form 3 Mar 25.pdf4 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Sept 24 Ready.pdf4 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Mar 25 Ready.pdf4 Jun 2025
Declaration about Commencement CertificateFile: Commencement Certificate.pdf4 Jun 2025
CERSAI detailsFile: Cesai Report Wollywood Phase III.pdf4 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration abt Separate bank account.pdf4 Jun 2025
Deviation Report with respect to Allotment letterFile: Deviation for Agreement for Sale.pdf4 Jun 2025
Details of encumbrances concerned to LegalFile: legal Encumbrance Certificate.pdf4 Jun 2025
Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for Sale.pdf4 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-Engineers certificate for quality assurance 2022.pdf4 Jun 2025
Proforma of Agreement for saleFile: Proforma Agreement for Sale.pdf4 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations Sarkar.pdf4 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of Interest in Other Real Estate Organizations Bharat Kor.pdf4 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Disclosure of Interest in Other Real Estate Organizations Pravinkumar.pdf4 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 4 Disclosure of Interest in Other Real Estate Organizations Punit Agrwal.pdf4 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Engineers certificate for quality assurance 2023.pdf4 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-Engineers certificate for quality assurance 2024.pdf4 Jun 2025
Certificates of CA (Form 3)File: Form 3 Mar 25.pdf9 May 2025
Certificates of CA (Form 3)File: Form 3 Dec 24.pdf9 May 2025
Certificates of CA (Form 3)File: Form 3 Sept 24.pdf9 May 2025
Certificates of CA (Form 3)File: Form 3 Jun 24.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3 Mar 24.pdf9 May 2025
Certificates of CA (Form 3)File: Form 3 Jun 23.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 Sept 23.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 Dec 23.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 Mar 24.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 Dec 24.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 5 Mar 25.pdf26 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Mar 25.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Dec 23 Ready.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Mar 24 Ready.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Jun 24 Ready.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Sept 24 Ready.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Jun 23 Ready.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Sept 23 Ready.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Dec 23 Ready.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Mar 24 Ready.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Jun 24 Ready.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Sept 24 Ready.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Jun 23 Ready.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Sept 23 Ready.pdf11 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 3 Phase IV WW.pdf6 Mar 2024
Certificates of CA (Form 3)File: CA CERTIFICATE (1)-ilovepdf-compressed.pdf26 May 2018
Proforma of Allotment letterFile: Proforma of Allotment.pdf25 May 2018
Building plan approvalFile: IOD.pdf24 May 2018
Layout approvalFile: MAIN LAYOUT PLAN.pdf24 May 2018
PAN CardFile: PAN CARD.pdf24 May 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
WOLLYWOOD PHASE 1GATES BUDRUK SHISHIR PADA BHIWANDI WADA ROAD WADA PALGHAR312CompletedApr 2017Apr 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WOLLYWOOD PHASE IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GATES BUDRUK3,200+ in Palghar

2 kmWOLLYWOOD PHASE IVLapsed / revoked 1Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: NIRVANA LIFESTYLE VENTURES

NIRVANA LIFESTYLE VENTURES has 5 registrations on MahaRERA, including WOLLYWOOD PHASE II and WOLLYWOOD PHASE III. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if WOLLYWOOD PHASE IV is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WOLLYWOOD PHASE IV?

The registered promoter entity is NIRVANA LIFESTYLE VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WOLLYWOOD PHASE IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against WOLLYWOOD PHASE IV?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for WOLLYWOOD PHASE IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WOLLYWOOD PHASE IV?

The professionals named in the filing: Architect: DEEPAK HIREMATH ASSOCIATES; Engineer: Naik Associates; Chartered Accountant: Sanjay R Soni & Associate. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WOLLYWOOD PHASE IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WOLLYWOOD PHASE IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WOLLYWOOD PHASE IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.