ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / White Pearl

Registered No litigation declared Residential / Group Housing project

White Pearl

By Imtiaz Saigara and Ahmedi Delawala

RG-MH-26077 · RERA P51900007731 · Last updated on MahaRERA portal: 16 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 48 months from the original
3 of 11Construction stages donefurthest along: Internal walls, 92%
60 of 117Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

White Pearl is a Residential / Group Housing project by Imtiaz Saigara and Ahmedi Delawala in Mumbai City, Maharashtra, registered with MahaRERA as P51900007731 on 17 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing. 57 of the 117 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameWhite Pearl
  • TypeResidential / Group Housing
  • Location
    • stable street
    • two tank
    • Mumbai City
    • 400008
  • Pincode400008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007731
  • ReraGenie IDRG-MH-26077

Builder

  • NameImtiaz Saigara and Ahmedi Delawala
  • Entity typeOthers
  • AopsAHMEDI DELAWALA -, IMTIAZ SAIGARA -

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed84 files

Current status

49%57 of 117 units booked
87.8%Work done, per cost certificate

Figures as on 16 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
White PearlNA312010710117

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

White Pearl: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed59

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots59
Closed/Covered59

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,044 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Feb 2026

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI4399.98
Proposed, not sanctioned4,079 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKRISHNA KUNJ DUNCAN ROAD NULL BAAZAR
Estimated costRs 13.55 cr
Cost incurredRs 11.89 cr
Work done87.77%
BuildingWingEstimatedIncurred
White PearlNARs 13.55 crRs 11.89 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNARENDRA B P CHITRODA
EngineerJUZER A TINWALA
EngineerAhemadi K Delawala
Chartered AccountantRashmee Shah
Chartered AccountantVijay H Shah
PartnerRole in project
Imtiaz Saigara and Ahmedi Delawala-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900025153Dec 2023 → Dec 2027

Reason as filed by the promotera) A major hindrance faced in the early stages of the project was the non-cooperation of some of the existing tenants occupying the premises. Multiple rounds of communication and negotiation were required to initiate vacating procedures, which delayed the commencement of actual on-site construction work. Legal and procedural constraints in dealing with tenant-related issues further slowed the progress. b) The process of obtaining building plan sanctions and approvals from the Municipal Corporation was considerably prolonged due to administrative delays. Repeated clarifications, document resubm

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000054603Samnan Shahid MirImtiaz Saigara22/05/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: AR imtiaz .pdf16 Jun 2026
Withdrawal Update Form 2File: ER - Imtiaz.pdf16 Jun 2026
Withdrawal Update Form 3File: CA Certificate Q1 25-26.pdf16 Jun 2026
Form 1File: Architect Certificate Joint 2023-24 Q4.pdf5 Mar 2026
Form 2File: Engineer Certificate-New MH-Ver Joint 2023-24 Q4.pdf5 Mar 2026
Form 3File: CA Certificate Joint 2023-24 Q4-min.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory - 2023-24.pdf5 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A March 25 (2).pdf5 Mar 2026
Declaration in FORM BFile: Form B Joint - Devloper.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q1.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q2.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q2.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q3.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q4.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q1.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q2.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q3.pdf29 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Joint 2023-24 Q4.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2023-24 Q2-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2024-25 Q4-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2024-25 Q3-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2024-25 Q2-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2024-25 Q1-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2023-24 Q4-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2023-24 Q3-min.pdf29 May 2025
Certificates of CA (Form 3)File: CA Certificate Joint 2023-24 Q1-min.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-New MH-Ver Joint 2023-24 Q2.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 2024-25 Q4.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- 2024-25 Q3.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- 2024-25 Q2.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-2024-25 Q1.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-New MH-Ver Joint 2023-24 Q4.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-New MH-Ver 11 Joint 2023-24 Q3.pdf29 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-New MH-Ver Joint 2023-24 Q1.pdf29 May 2025
Commencement Certificates / NA Order for plotted developmentFile: 6 CC Revalidation Approval Letter Joint.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2017-18.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2018-19.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2019-20.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2020-21.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2021-22.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2022-23.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2023-24.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2024-25.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - 2024-25.pdf29 May 2025
Other - TechnicalFile: Form 2A.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit Report-Joint 2023-24.pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2a 2019-20.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a 2020-21.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a 2021-22.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a 2022-23.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a 2023-24.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: IMTIAZ AHMEDI JV 2017-18.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: IMTIAZ AHMEDI JV 2018-19.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: IMTIAZ AHMEDI JV 2019-20.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: IMTIAZ AHMEDI JV 2020-21.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: IMTIAZ AHMEDI JV 2021-22.pdf23 Dec 2024
CERSAI detailsFile: CERSAI 241219.pdf19 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: 1 b Details of encumbrances concerned to Legal 241207.pdf19 Dec 2024
Details of encumbrances concerned to FinanceFile: 1 b Details of encumbrances concerned to Legal 241207.pdf18 Dec 2024
Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal 241207.pdf18 Dec 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate 241207.pdf16 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 signed RERA Joint 240410.pdf15 Apr 2024
Certificates of CA (Form 5)File: CA certificate for RERA 2023.pdf30 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 RERA signed Joint.pdf6 Apr 2023
Certificates of CA (Form 5)File: CA certificate for RERA 2019.pdf11 Feb 2023
Certificates of CA (Form 5)File: CA certificate for RERA 2020.pdf11 Feb 2023
Certificates of CA (Form 5)File: CA certificate for RERA 2021.pdf11 Feb 2023
Certificates of CA (Form 5)File: CA certificate for RERA 2022.pdf11 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC upto 20th floor.pdf10 Jul 2021
Certificates of CA (Form 5)File: form 5 .pdf5 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf22 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf31 Jul 2017
Layout approvalFile: Declaration that Layout Approval is not Applicable.pdf29 Jul 2017
Building plan approvalFile: IOD.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Declaration that Layout Approval is not Applicable.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf29 Jul 2017
Declaration in FORM BFile: Form B.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale MM.pdf29 Jul 2017

How this compares with Mumbai City

49%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 48 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep White Pearl on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near two tank780+ in Mumbai City

2 kmWhite PearlCompleted 26Lapsed / revoked 33Other 97Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: Imtiaz Saigara and Ahmedi Delawala

Imtiaz Saigara and Ahmedi Delawala has 1 registration on MahaRERA, including White Pearl. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if White Pearl is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of White Pearl?

The registered promoter entity is Imtiaz Saigara and Ahmedi Delawala, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in White Pearl?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against White Pearl?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for White Pearl?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at White Pearl?

The professionals named in the filing: Architect: NARENDRA B P CHITRODA; Engineer: JUZER A TINWALA; Engineer: Ahemadi K Delawala; Chartered Accountant: Rashmee Shah; Chartered Accountant: Vijay H Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in White Pearl?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About White Pearl. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save White Pearl to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.