Red flags
- Litigation declared, 30 cases
- 9 complaints at MahaRERA
- Completion date moved by 60 months
- 1 extension taken
- Rs 700.00 crore secured on the land, in favour of The Federal Bank Limited
- The declared charge does not appear in the CERSAI report on the filing
Clear
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Godrej Avenue Eleven - Tower A is a Residential / Group Housing project by GODREJ RESIDENCY PRIVATE LIMITED in Mahalaxmi, 400008, registered with MahaRERA as P51900005216 on 10 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 60 months from the original filing. 170 of the 227 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 9 complaints are on record with the regulator.
At a glance
Project
- NameGodrej Avenue Eleven - Tower A
- TypeResidential / Group Housing
- Location
- Dr E Moses Road
- Mahalaxmi
- 400008
- Pincode400008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900005216
- ReraGenie IDRG-MH-26515
Builder
- NameGODREJ RESIDENCY PRIVATE LIMITED
- Entity typeCompany
- CINU70109MH2017PTC292515
- GSTIN27AAGCG7455G1ZD
- Godrej Leadership Forum - Region Head Mumbai CityAmitesh Shah
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Aug 2017
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed251 files
Current status
Figures as on 13 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | NA | 78 | 59 | 227 | 0 | 227 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 87%.
Tower A: 58% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 87% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 47% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed656
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Indo Global Solutions and Technologies Pvt Ltd | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower A | NA | Rs 852.87 cr | Rs 280.05 cr |
| - | NA | Rs 10.02 cr | Rs 7.66 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUPALI D MANDE |
| Engineer | Rajendra Joshi |
| Engineer | Vinyasa Consultants |
| Chartered Accountant | BSR and Co. LLP ( 101248W/W-100022) |
| Chartered Accountant | BSR and Co. LLP |
| Chartered Accountant | AKPJ & Associates |
| Partner | Role in project |
|---|---|
| GODREJ RESIDENCY PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Project approved by the Hon'ble Authority u/s. 15 via email dated 27th March 2023. (order attached in others tab below) 2) We have updated details in correction Application and for date we have applied under extension. 3) The new project completion date post takeover is 31st Dec 2028. 4) We have taken 51% consent (attached) as per latest books and updated inventory and the same is updated in the website. 5) Sr. No.1 and 2 are covering letter and Annexure as per format and Sr. No. 3 to 53 are 51 consents. 6) All the information as requested is updated.
Litigation declared30
| Case | Court | Status |
|---|---|---|
| RAD Suit No 2064 of 2007/2007 | Small Causes Court Trial Mumbai | Ongoing |
| RAD Suit No 323 of 2008/2008 | Small Causes Court Trial Mumbai | Ongoing |
| RAD Suit No 324 of 2008/2008 | Small Causes Court Trial Mumbai | Ongoing |
| RAE Suit No 130/163 of 2011/2011 | Small Causes Court Trial Mumbai | Ongoing |
| LC Suit No 2501 of 2009/2009 | City Civil Court Mumbai | Ongoing |
| FA No 972 of 2010/2010 | Bombay High Court | Ongoing |
| LC Suit No 1362 of 2011/2011 | City Civil Court Mumbai | Ongoing |
| LC Suit No 1363 of 2011/2011 | City Civil Court Mumbai | Ongoing |
| LC Suit No 1035 of 2012/2012 | City Civil Court Mumbai | Ongoing |
| RAD Suit No 98 of 2011/2011 | Small Causes Court Mumbai | Ongoing |
| RAD Suit No 100 of 2011/2011 | Small Causes Court Trial Mumbai | Ongoing |
| RAD Suit No 104 of 2011/2011 | Small Causes Court Trial Mumbai | Ongoing |
| WP L No 661 of 2015/2015 | Bombay High Court | Ongoing |
| Suit No 2323 of 2015/2015 | City Civil Court Mumbai | Ongoing |
| CHS No 807 of 2007 in LC Suit 4562 of 2006/2006 | City Civil Court Mumbai | Ongoing |
| CHS No 805 of 2007 in LC Suit 479 of 2006/2006 | City Civil Court Mumbai | Ongoing |
| NM 3659 of 2015 in SC No 6888 of 2014/2014 | City Civil Court Mumbai | Ongoing |
| Appeal 53 of 2017/2017 | High Power Committee MHADA | Ongoing |
| Appeal 52 of 2017/2017 | High Power Committee MHADA | Ongoing |
| Suit No 996 of 2017/2017 | City Civil Court Mumbai | Ongoing |
| CWP No 779/2014 | High Court Bombay | Ongoing |
| CWP No 4458/2014 | High Court Bombay | Ongoing |
| Appeal No 54/2017 | High Power Committee MHADA | Ongoing |
| WP No 760 of 2018/2018 | High Court Bombay | Ongoing |
| Comm Suit No 1177 of 2018/2018 | High Court Bombay | Ongoing |
| Appeal No 7 of 2018/2018 | High Power Committee MHADA | Ongoing |
| 2018 | High Court Bombay | Ongoing |
| Company Petition No /2018 | NCLT Mumbai | Ongoing |
| WP L No 2575 of 2018/2018 | High Court Bombay | Ongoing |
| Review Petition No 2 of 2019 in WP No 1531 of 2017/2015 | High Court Bombay | Ongoing |
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001255 | PAHLAJ BAJAJ | NEELKAMAL REALTORS TOWERS PVT. LTD. | 13/10/2017 |
| CC006000000001256 | PAHLAJ BAJAJ | NEELKAMAL REALTORS TOWER PVT LTD | 13/10/2017 |
| CC006000000012348 | NSB Infrastructure and Projects Private Limited | Neelkamal Realtors Tower Pvt. Ltd | 08/12/2017 |
| CC006000000012535 | Antony Jacob | Neelkamal Realtors Tower Pvt Ltd | 21/12/2017 |
| CC006000000044089 | GUNWANTI RAMNIKLAL PATEL | NEELKAMAL REALTORS TOWER PRIVATE LIMITED | 16/04/2018 |
| CC006000000057603 | Advocate Ganesh Iyer | Neelkamal Realtors Tower Private Limited | 09/01/2019 |
| CC006000000078702 | Mr. Antony Jacob & Mrs. Celine Rose | Neelkamal Realtors Tower Pvt. Ltd. | 29/03/2019 |
| CC006000000194351 | MR. VINU PATEL AND MRS. DAKSHABEN PATEL | M/s. Neelkamal Realtors Tower Pvt. Ltd. | 09/10/2020 |
| CC006000000194571 | RAVI RAMESH ROHIRA | NEELKAMAL REALTORS TOWER PRIVATE LIMITED | 19/10/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jan 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed251
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 251 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A_Tower A.pdf | 13 Jun 2026 |
| Commencement certificateFile: Avenue Eleven CC 2 Apr 2026.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: Godrej Avenue_Tower A_Signed.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: Godrej Avenue_Tower A_Signed.pdf | 16 Apr 2026 |
| Withdrawal Update Form 2File: RERA-Withdrawal Application Form2 TA_Signed.pdf | 16 Apr 2026 |
| Withdrawal Update Form 2File: RERA-Withdrawal Application Form2 TA_Signed.pdf | 16 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_Tower A_Signed.pdf | 16 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_Tower A_Signed.pdf | 16 Apr 2026 |
| Form 1File: Tower A _Dec 2025_Signed.pdf | 16 Jan 2026 |
| Form 2File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE DEC25-Final_Signed.pdf | 16 Jan 2026 |
| Form 3File: CA certificate Dec 25 - One M- Tower A_Final_Signed.pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory Details - Circular 29 (Dec25) Tower A_Signed.pdf | 16 Jan 2026 |
| Form 1File: Tower A _Sep 2025_Signed.pdf | 11 Oct 2025 |
| Form 2File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE SEPT'25-Final_Signed.pdf | 11 Oct 2025 |
| Form 3File: CA certificate sep'25 - One M- Tower A_Final.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory Details - Circular 29 (Sep'25) Tower A.pdf | 11 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5_OneM Tower A_Mar'25_compressed.pdf | 28 Aug 2025 |
| Form 1File: Tower A June 2025_Signed.pdf | 20 Jul 2025 |
| Form 2File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE JUN'25-Final_Signed.pdf | 20 Jul 2025 |
| Form 3File: CA certificate Jun 25 - One M- Tower A_Final.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory Details - Circular 29 (Mar'25) Tower A.pdf | 20 Jul 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_Tower A_Signed.pdf | 16 May 2025 |
| Certificates of CA (Form 3)File: CA Certificate_Tower A_Comp.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Details - Circular 29 (Mar'25) Tower A_Comp.pdf | 17 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A _March 2025_Signed.pdf | 15 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE 31ST MAR'25-Final_Signed.pdf | 15 Apr 2025 |
| Building plan approvalFile: Approval letter_signed.pdf | 11 Mar 2025 |
| Building plan approvalFile: Drawing 1.pdf | 11 Mar 2025 |
| Building Plan Approval (IOD)File: Approval letter_signed.pdf | 11 Mar 2025 |
| Building Plan Approval (IOD)File: Drawing 1.pdf | 11 Mar 2025 |
| Building plan approvalFile: Certificate.pdf | 21 Jan 2025 |
| Building plan approvalFile: Certificate.pdf | 21 Jan 2025 |
| Building plan approvalFile: Certificate.pdf | 21 Jan 2025 |
| Building Plan Approval (IOD)File: Certificate.pdf | 21 Jan 2025 |
| Other - LegalFile: Litigation Declaration.pdf | 21 Jan 2025 |
| Building Plan Approval (IOD)File: Certificate.pdf | 21 Jan 2025 |
| Other - LegalFile: Litigation Declaration.pdf | 21 Jan 2025 |
| Building Plan Approval (IOD)File: Certificate.pdf | 21 Jan 2025 |
| Other - LegalFile: Litigation Declaration.pdf | 21 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A _Dec 2024_Signed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE DEC'24-Signed.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Tower A_Inventory.pdf | 20 Jan 2025 |
| CERSAI detailsFile: CERSAI_Search_Report_200335726623_For_Asset_Based_Search_17_01_2025_12_54_17_965.pdf | 20 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Tower A_Dec'24_Signed.pdf | 20 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A _Dec 2024_Signed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE DEC'24-Signed.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Tower A_Inventory.pdf | 20 Jan 2025 |
| CERSAI detailsFile: CERSAI_Search_Report_200335726623_For_Asset_Based_Search_17_01_2025_12_54_17_965.pdf | 20 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Tower A_Dec'24_Signed.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A _Dec 2024_Signed.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Tower A_Dec'24_Signed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE DEC'24-Signed.pdf | 20 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Other - LegalFile: BR_Godrej Residency_Documents.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Tower A_Inventory.pdf | 20 Jan 2025 |
| CERSAI detailsFile: CERSAI_Search_Report_200335726623_For_Asset_Based_Search_17_01_2025_12_54_17_965.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Godrej Tower A Nov 24 Signed_compressed.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Godrej Tower A Nov 24 Signed_compressed.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Godrej Tower A Nov 24 Signed_compressed.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Godrej Tower A Nov 24 Signed_compressed.pdf | 21 Nov 2024 |
| Declaration about Commencement CertificateFile: CC Declaration_TA_Signed.pdf | 18 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mahalaxmi Tower A _Sep 2024_Signed.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE SEPT'24_Signed.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Details - Circular 29 (Sep'24) Tower A_Signed.pdf | 18 Oct 2024 |
| CERSAI detailsFile: Non Encumbrance Certificate Legal and Finance_Godrej Avenue Eleven_Signed.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_Tower A_Sep'24_Signed.pdf | 18 Oct 2024 |
| Declaration about Commencement CertificateFile: CC Declaration_TA_Signed.pdf | 18 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mahalaxmi Tower A _Sep 2024_Signed.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE SEPT'24_Signed.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Details - Circular 29 (Sep'24) Tower A_Signed.pdf | 18 Oct 2024 |
| CERSAI detailsFile: Non Encumbrance Certificate Legal and Finance_Godrej Avenue Eleven_Signed.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_Tower A_Sep'24_Signed.pdf | 18 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mahalaxmi Tower A _Sep 2024_Signed.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_Tower A_Sep'24_Signed.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ AVENUE11- TOWER A-MAHALAKSHMI_CERTIFICATE SEPT'24_Signed.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Details - Circular 29 (Sep'24) Tower A_Signed.pdf | 18 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 251 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Godrej Avenue Eleven - Tower A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahalaxmi
Filed coordinates, straight-line distance. 59 registered projects within 2 km.
FATIMA HEIGHTS
M K ENTERPRISES
Nexsa Sky Vista
D.K. REALTORS & DEVELOPERS LIMITED
Lakadawala Garden
M/s. Lakadawala Developers Pvt. Ltd.
La Mer Residences
EXCELLENT REALTOR DEVELOPERS
FUEGO
HILTON INFRASTRUCTURE
AJMAL-235
AWFI REAL ESTATE PRIVATE LIMITED
Builder: GODREJ RESIDENCY PRIVATE LIMITED
GODREJ RESIDENCY PRIVATE LIMITED has 2 registrations on MahaRERA, including Godrej Avenue Eleven - Tower A and Godrej Avenue Eleven - Tower B. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record.
Frequently asked questions
What are my rights if Godrej Avenue Eleven - Tower A is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Godrej Avenue Eleven - Tower A?
The registered promoter entity is GODREJ RESIDENCY PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH2017PTC292515 and GSTIN 27AAGCG7455G1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Godrej Avenue Eleven - Tower A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Avenue Eleven - Tower A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Godrej Avenue Eleven - Tower A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Godrej Avenue Eleven - Tower A?
The professionals named in the filing: Architect: RUPALI D MANDE; Engineer: Rajendra Joshi; Engineer: Vinyasa Consultants; Chartered Accountant: BSR and Co. LLP ( 101248W/W-100022); Chartered Accountant: BSR and Co. LLP; Chartered Accountant: AKPJ & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Avenue Eleven - Tower A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback