Home / Browse projects / Mumbai Suburban, Maharashtra / WHISPERING TOWERS EFG WINGS

Registration lapsed No litigation declared Residential / Group Housing project

WHISPERING TOWERS EFG WINGS

By HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD

RG-MH-24008 · RERA P51800007809 · Last updated on MahaRERA portal: 11 Apr 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 71 months past the filed date
  • 47 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2020Possession promised71 months past this date
0 of 66Construction stages doneacross 6 buildings; furthest along: Excavation, 82%
47Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

WHISPERING TOWERS EFG WINGS is a Residential / Group Housing project by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007809 on 18 Aug 2017. Possession was promised by 30 Nov 2020 and is now 71 months past that date. 47 complaints are on record with the regulator.

At a glance

Project

  • NameWHISPERING TOWERS EFG WINGS
  • TypeResidential / Group Housing
  • Location
    • LBS Marg
    • Mulund West
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007809
  • ReraGenie IDRG-MH-24008

Builder

  • NameHOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
  • Entity typeCompany
  • Managing DirectorSARANG WADHAWAN
  • Other registrations13 more →
  • No longer live14 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

71 months past promisethis monthRegisteredAug 2017PromisedNov 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Nov 2020
  • Revised completionNone
  • Buildings6 building records
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING - ENA370000
WING - FNA370000
WING - GNA370000
WING E - PHASE 2-29th to 40th floorNA120000
WING F - PHASE 2-29th to 40th floorNA120000
WING G - PHASE 2-29th to 40th floorNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 11 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Excavation, at 82%.

WING - E45%
ActivityProgress
Excavation82%
Basement (if any)82%
Podiums (if any)82%
Plinth82%
Stilt Floor82%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises21%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING - F45%
ActivityProgress
Excavation82%
Basement (if any)82%
Podiums (if any)82%
Plinth82%
Stilt Floor82%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises19%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING - G45%
ActivityProgress
Excavation82%
Basement (if any)82%
Podiums (if any)82%
Plinth82%
Stilt Floor82%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING E - PHASE 2-29th to 40th floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING F - PHASE 2-29th to 40th floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING G - PHASE 2-29th to 40th floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed578

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots578
Closed/Covered572
Open Space6
BuildingClosed/CoveredOpen SpaceTotal
WING - E2062208
WING - F022
WING - G1272129
WING E - PHASE 2-29th to 40th floor93093
WING F - PHASE 2-29th to 40th floor91091
WING G - PHASE 2-29th to 40th floor55055

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,965 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI60894.73
Proposed, not sanctioned41,837 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANDRA WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIndrajeet S. Deshmukh
EngineerStruct Bombay Consultants
PartnerRole in project
HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD-

Litigation declared2

CaseCourtStatus
2410/2008BOMBAY HIGH COURTPENDING
24/2017BOMBAY HIGH COURTPENDING

Complaints filed with MahaRERA47

Case no.ComplainantRespondentFiled
CC006000000000192Atul Vasant GhotageHousing Development and Infrastructure Ltd.03/08/2018
CC006000000000483K RANJAN KUMAR SUBUDHIHOUSING DEVELOPMENT AND INFRASTRUCTURE LTD12/09/2017
CC006000000023586PRAKASH KISANRAO BHAVSARHOUSING DEVELOPMENT AND INFRASTRUCTURE LTD06/03/2018
CC006000000023843AJAY KULKARNIHDIL01/08/2018
CC006000000044555Prakash AhujaHousing Development and Infrastructure Limited17/05/2018
CC006000000110644Santosh Babaji SarangHousing Development and Infrastructure Limited22/08/2019
CC006000000055794Milind DhandeHousing Developement and Infra. LTD14/08/2018
CC006000000055915Pandurang Baban BadheHousing Development And Infrastructure Limited23/08/2018
CC006000000056269ATUL ARUN CHAVANHOUSING DEVELOPMENT AND INFRASTRUCTURE LIMITED21/09/2018
CC006000000056289Yogesh Dilip ShivalkarHousing Development and Infrastructure Ltd (HDIL)15/10/2018
CC006000000056693S.KarthikeyanHOUSING DEVELOPMENT AND INFRASTRUCTURE LTD23/10/2018
CC006000000057294Anil Baburao GaikwadHousing Development and Infrastructure Limited13/12/2018
CC006000000057417Aprameya Narasimhamurthy RaoSarang Wadhawan24/12/2018
CC006000000057865Mr. Nitin R RathodHousing Development and Infrastructure Limited31/01/2019
CC006000000057936Mr. Saiprasad M. Modi & Mrs. Vaidehi ModiHousing Development and Infrastructure Limited07/02/2019
CC006000000057919Mrs. Kalindi SinghHousing Development and Infrastructure Limited04/02/2019
CC006000000057962Mr. Sandeep Yashwant Indulkar & Mrs. Vaidehi Sandeep IndulkarHousing Development and Infrastructure Limited07/02/2019
CC006000000057952Mr. Parth Anil Sejpal (HUF)M/s Housing Development and Infrastructure Limited04/02/2019
CC006000000057955Sanjay BherwaniHousing Development and infrastructure Limited07/02/2019
CC006000000057999Shekhar BherwaniHousing Development And Infrastructure Limited07/02/2019
CC006000000058000Satish AmbwaniHousing Development and Infrastructure Limited07/02/2019
CC006000000058001Umesh BajajHousing Development & Infrastructure Limited07/02/2019
CC006000000057973Mr. Kanwar Pal Singh & Mrs. Charanjit KaurHousing Development and Infrastructure Limited07/02/2019
CC006000000058012Dr. Liladhar Ramji ChandanHousing Development and Infrastructure Limited09/02/2019
CC006000000058008Mr. Ladru D'souzaM/s. Housing Development and Infrastructure Limited09/02/2019
CC006000000058009Dr. Anish Paul Gregory and Mr. Paul GregoryHousing Development and Infrastructure Limited09/02/2019
CC006000000058037Rajesh DondeHousing Development and Infrastructure Ltd.07/05/2019
CC006000000058058Mr. Nitin S. PalanHousing Development and Infrastructure Limited14/02/2019
CC006000000058104Mrs Khushi Prashant KhanchandaniM/s Housing Development And Infrastructure Limited18/02/2019
CC006000000058130Mrs Sibrina ShafiqueM/s Housing Development and21/02/2019
CC006000000058138Mr Suhail S SaquibM/s Housing Development And Infrastructure Limited21/02/2019
CC006000000068147Mr Sridhar V CharyM/s Housing Development And Infrastructure Limited21/02/2019
CC006000000068146Brinda SubramanianM/s. Housing Development And Infrastructure Ltd.22/02/2019
CC006000000078190Mrs Shagufta Mudar DargahwalaM/s. Housing Development And Infrastructure Limited22/02/2019
CC006000000078231Mr Virendra Ramesh PandirkarMs Housing Development And Infrastructure Limited26/02/2019
CC006000000078267Mrs Sonal Aniruddha SawantM/s Housing Development And Infrastructure Limited01/03/2019
CC006000000078305Mr Prakash P PatilM/s Housing Development And Infrastructure Limited04/03/2019
CC006000000078335Mr Sanket Jayawant JadhavM/s Housing Development And Infrastructure Limited06/03/2019
CC006000000141128Uttam M AmarnaniHousing Development and Infrastructure Limited02/10/2019
CC006000000078816Mrs. Smita Sanjay Kajale & Sanjay Maganrao KajaleHDIL Towers15/04/2019
CC006000000078843Mr. Sanjay Maganrao Kajale & Mrs. Smita Sanjay KajaleHousing Development and Infrastructure Limited15/04/2019
CC006000000078831Mr. Sachin Bansi Parkhe & Mrs. Kshitija Subhash ShindeHousing Development and Infrastructure Limited15/04/2019
CC006000000078857Mr. Vikram Shambhubhai Davda & Mr. Hemal Vikram DavdaHousing Development and Infrastructure Limited18/04/2019
CC006000000078858Mr. Laxmandas R. Kungwani, Mrs. Meena Kungwani & Mr. Roshan L. KungwaniHousing Development and Infrastructure Limited18/04/2019
CC006000000079051Mrs. Neeta GadaHousing Development and Infrastructure Limited03/05/2019
CC006000000079093Mrs. Sangita S. Pandit and Mr. Sunil B. PanditHousing Development and Infrastructure Limited03/05/2019
CC006000000100391shailesh singhHDIL02/08/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Whispering Tower,EFG Wings - Form 5.pdf11 Apr 2019
Proforma of Allotment letterFile: AFS Whispering Towers rera F.pdf12 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ArchCert EtG.pdf30 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Sale Building CC.pdf15 Nov 2017
Layout approvalFile: 08 REFUGE F G 28TH FLOOR.pdf29 Jul 2017
Layout approvalFile: 09 TERRACE SECTION.pdf29 Jul 2017
Layout approvalFile: 06 5TH POD 6TH POD.pdf29 Jul 2017
Layout approvalFile: 07 6TH POD TYP REF.pdf29 Jul 2017
Layout approvalFile: 01 LAYOUT LB.pdf29 Jul 2017
Layout approvalFile: 02 LB UB.pdf29 Jul 2017
Layout approvalFile: 03 AREA DIA UB GR FL.pdf29 Jul 2017
Layout approvalFile: 04 GR FL 1ST POD.pdf29 Jul 2017
Layout approvalFile: 05 2ND TO 5TH POD.pdf29 Jul 2017
Building plan approvalFile: 00 IOD.pdf29 Jul 2017
PAN CardFile: PANCARD.pdf29 Jul 2017
Copy of the legal title reportFile: TC - Whispering Towers-Part-1.pdf29 Jul 2017
Copy of the legal title reportFile: TC - Whispering Towers-Part-2.pdf29 Jul 2017
Details of encumbrancesFile: Charge on Project WT EFG.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 01 LAYOUT LB.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 02 LB UB.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 03 AREA DIA UB GR FL.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 04 GR FL 1ST POD.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 05 2ND TO 5TH POD.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 06 5TH POD 6TH POD.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 07 6TH POD TYP REF.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 08 REFUGE F G 28TH FLOOR.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 09 TERRACE SECTION.pdf29 Jul 2017
Building Plan Approval (IOD)File: 00 IOD.pdf29 Jul 2017
Declaration in FORM BFile: Form B - Whispering Towers EFG 28072017.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certi Whispering EFG.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate Whispering EFG.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Whispering EFG.pdf29 Jul 2017
Proforma of Allotment letterFile: AL_AFS Whispering Towers.pdf29 Jul 2017

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered late
ProjectLocationFlatsStatusPromisedDelivered
HDIL INDUSTRIAL PARKBESIDES LAXMI MARBLES CHANDANSAR ROAD VILLAGE CHANDANSAR VIRAR EAST627CompletedApr 2017Late, Jul 2017
PREMIER EXOTICA IIPREMIER AUTO KIROL ROAD KURLA WEST MUMBAI 40007083CompletedJun 2013Late, Jun 2017
HARMONYNEW LINK ROAD GOREGAON WEST MUMBAI 400104221CompletedJun 2013Late, Jul 2017
PREMIER RESIDENCESPREMIER AUTO KURLA WEST MUMBAI - 4000701,087CompletedDec 2012Late, Mar 2017
GALAXY APARTMENTS WING ABEBHANDARY ESTATE KURLA EAST MUMBAI 400024314CompletedDec 2011Late, Jun 2017
HDIL RESIDENCY PARKOPP YAZOO PARK NARANGI BYPASS ROAD VILLAGE DONGRE VIRAR WEST1,199CompletedAug 2011Late, Oct 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WHISPERING TOWERS EFG WINGS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West6,700+ in Mumbai Suburban

2 kmWHISPERING TOWERS EFG WICompleted 96Lapsed / revoked 66Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 297 registered projects within 2 km.

Builder: HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD

HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD has 14 registrations on MahaRERA, including THE NEST and PREMIER EXOTICA I. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that WHISPERING TOWERS EFG WINGS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if WHISPERING TOWERS EFG WINGS is delayed beyond 30 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WHISPERING TOWERS EFG WINGS?

The registered promoter entity is HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WHISPERING TOWERS EFG WINGS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against WHISPERING TOWERS EFG WINGS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for WHISPERING TOWERS EFG WINGS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WHISPERING TOWERS EFG WINGS?

The professionals named in the filing: Architect: Indrajeet S. Deshmukh; Engineer: Struct Bombay Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WHISPERING TOWERS EFG WINGS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WHISPERING TOWERS EFG WINGS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WHISPERING TOWERS EFG WINGS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.