ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Western Woods

Registration lapsed No litigation declared Residential / Group Housing project

Western Woods

By Karmvir Mumbai Housing Private Limited

RG-MH-12426 · RERA P51800007330 · Last updated on MahaRERA portal: 13 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
7Complaints at MahaRERAon this registration
Jump to the 31 documents Report an error

Western Woods is a Residential / Group Housing project by Karmvir Mumbai Housing Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007330 on 17 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. The completion date has moved by 12 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameWestern Woods
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007330
  • ReraGenie IDRG-MH-12426

Builder

  • NameKarmvir Mumbai Housing Private Limited
  • Entity typeCompany

Key dates

82 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed31 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Western WoodsNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Western Woods: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed69

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots69
Closed/Covered69

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,358 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s Soni & BrothersBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI3483.27
Proposed, not sanctioned3,314 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch4, Laxmi Towers, Bandra Kurla Complex Road, B Wing, Bandra Kurla Complex, Bandra East, Mumbai, Mahar

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJIGAR NAGDA
EngineerGokani Consultants Pvt. Ltd.
PartnerRole in project
Karmvir Mumbai Housing Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800002054Dec 2018 → Dec 2019

Reason as filed by the promoter1. The development control and promotions regulations 2034 for Greater Mumbai was sanctioned on 8th May, 2018. However, a major part of the same was under Excluded Part. Hence, the implementation of the same was not possible. 2. The earlier DCR 1991, stopped being in existence from 31st August, 2018. 3. The Government sanctioned the Excluded Part on 21st September, 2018 and stated that implementation of DCPR 2034 would commence form 24th October, 2018. 4. However, the Government notified on 23rd October, 2018 that there were lots of typographical errors in the notification dated 21st September

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000198297VEENA DSOUZAKarmvir Mumbai Housing Pvt Ltd08/09/2021
CC006000000198317Mathew ThomasKarmvir Mumbai Housing Pvt Ltd10/09/2021
CC006000000198722Hiralal JaiswalKarmvir Mumbai Housing Pvt Ltd14/11/2021
CC006000000198972Subhas MajumderKarmvir Mumbai Housing Pvt. Ltd.10/11/2021
CC006000000220829Narinder Pal SinghKarmvir Mumbai Housing Pvt Ltd15/04/2022
CC12602858Surojit SahaKarmvir Mumbai Housing Private Limited15/05/2026
CC12603255Rahul DudhadeKarmvir Mumbai Housing Private Limited30/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Oct 2023

Documents filed31

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Architect’s Certificate on Completion of Project (Form 4).pdf13 Oct 2023
Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report_KMHPL-19-20.pdf19 Apr 2021
Certificates of CA (Form 3)File: 8-Certificate of CA (Form 3)_Western Woods_KMHPL-3Qtr-2019.pdf21 Nov 2020
Certificates of CA (Form 3)File: 9-Certificate of CA (Form 3)_Western Woods_KMHPL-4Qtr-2019.pdf21 Nov 2020
Certificates of CA (Form 3)File: 10-Certificate of CA (Form 3)_Western Woods_KMHPL-1Qtr-2020.pdf21 Nov 2020
Certificates of CA (Form 3)File: 11-Certificate of CA (Form 3)_Western Woods_KMHPL-2Qtr-2020.pdf21 Nov 2020
Certificates of CA (Form 3)File: Form 3_KMHPL_Q1_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_KMHPL_Q2_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_KMHPL_Q3_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_KMHPL_Q4_18-19.pdf23 May 2020
Certificates of CA (Form 5)File: D:\SAMEER PANCHAL - CS\Company Secretary\03_MahaRERA\00_PROJECTS\00_ PROJECTS\01_Western W3 Feb 2020
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Western Woods_KMHPL-1Qtr.pdf5 Nov 2019
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Western Woods_KMHPL-2Qtr.pdf5 Nov 2019
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Western Woods_KMHPL-3Qtr.pdf5 Nov 2019
OtherFile: KMHPL _BR-Change in Regd office_01-02-2019.pdf17 Apr 2019
Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report.pdf7 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1).pdf26 Jul 2017
Certificates of CA (Form 3)File: Certificate of CA (Form 3).pdf26 Jul 2017
Layout approvalFile: Building plan apporval (IOD)_3.pdf21 Jul 2017
Building plan approvalFile: Building plan apporval (IOD).pdf21 Jul 2017
Building plan approvalFile: Building plan apporval (IOD)_2.pdf21 Jul 2017
PAN CardFile: Pan Card-KMHPL.pdf21 Jul 2017
Copy of the legal title reportFile: Copy of the Legal Title Report.pdf21 Jul 2017
Details of encumbrancesFile: Self Declaration for encumbrances.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Building plan apporval (IOD)_3.pdf21 Jul 2017
Building Plan Approval (IOD)File: Building plan apporval (IOD).pdf21 Jul 2017
Building Plan Approval (IOD)File: Building plan apporval (IOD)_2.pdf21 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf21 Jul 2017
Declaration in FORM BFile: Declaration in Form B.pdf21 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate _WW.pdf21 Jul 2017
Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf21 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Western Woods on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmWestern WoodsCompleted 112Lapsed / revoked 70Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 324 registered projects within 2 km.

Builder: Karmvir Mumbai Housing Private Limited

Karmvir Mumbai Housing Private Limited has 1 registration on MahaRERA, including Western Woods. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Western Woods shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Western Woods is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Western Woods?

The registered promoter entity is Karmvir Mumbai Housing Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Western Woods?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Western Woods?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Western Woods?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Western Woods?

The professionals named in the filing: Architect: JIGAR NAGDA; Engineer: Gokani Consultants Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Western Woods?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Western Woods. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Western Woods to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.