Home / Browse projects / Dakshina Kannada, Karnataka / WALK IN NIRVANA
WALK IN NIRVANA
By WALK IN BUILDERS AND DEVELOPERS
RG-KA-54465 · RERA PRM/KA/RERA/1257/334/PR/200224/006643 · Last updated on RERA Karnataka portal: 15 Jul 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
WALK IN NIRVANA is a Residential/Group Housing project by WALK IN BUILDERS AND DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200224/006643 on 20 Feb 2024. Possession is promised by 28 Feb 2027. 15 of the 30 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.
At a glance
Project
- NameWALK IN NIRVANA
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- 575002
- Pincode575002
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/200224/006643
- ReraGenie IDRG-KA-54465
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on20 Feb 2024
- Promised completion28 Feb 2027
- Revised completionNone
- Buildings1 building record
- Documents filed120 files
Current status
Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WALK IN NIRVANA | - | - | - | 30 | 0 | 30 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 16 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities40
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | 100% |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Piped Gas | Yes | 100% |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | No | Not applicable |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VINCENT NAZARETH | - | - |
| NIRMALA IRENE SYLVIA NAZARETH | - | - |
| MONTHU LIGORY D'SILVA | - | - |
| JACINTHA MONTHU D'SILVA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 8.00 cr | Rs 26.17 lakh |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | - | Rs 3.85 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | BABA ALANKAR |
| Engineer | DESIGN ASSOCIATES ANAND BHAT |
| Chartered Accountant | NITHIN J SHETTY |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed120
As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200224/006643 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1-Nirvana- with UDIN.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5 nirvana.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form6 nirvana.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q4-Nirvana with UDIN.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 nirvana Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 nirvana Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Walk-In Form 4 Q3 Nirvana.pdf | 20 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 nirvana Q3.pdf | 20 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 nirvana Q3.pdf | 20 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 20 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 20 Feb 2026 |
| MRFile: MR.pdf | 15 Feb 2024 |
| MutationFile: Mutation.pdf | 9 Feb 2024 |
| ClarificationFile: clarification.pdf | 9 Feb 2024 |
| ECFile: EC.pdf | 9 Feb 2024 |
| The bank account name should be as per the bank account directionFile: BANK NIRVANA.pdf | 2 Feb 2024 |
| MRFile: MR Nirvana.pdf | 2 Feb 2024 |
| CORRECT EC UPDATEDFile: EC.pdf | 2 Feb 2024 |
| profit and loss account and balance sheet 2020-21, 2021-22 & 2022-23 with CA UDIN along with schedulFile: BS PL 21 with UDIN with schdules.pdf | 20 Jan 2024 |
| 2022File: BS and PL 22 with Udin and schdule.pdf | 20 Jan 2024 |
| 2023File: BS and PL 23 with Udin and schedule.pdf | 20 Jan 2024 |
| PRM/KA/RERA/1257/334/PR/201222/005544 update quarterly reportFile: Quarter details.pdf | 20 Jan 2024 |
| connected MR in PDF formatFile: Mutation.pdf | 20 Jan 2024 |
| ECFile: EC new.pdf | 20 Jan 2024 |
| JDAFile: JDA-NIRVANA.pdf | 20 Jan 2024 |
| JD AFFIDAVIT CUM DECLARATIONFile: Joint Declaration.pdf | 20 Jan 2024 |
| self-attested copy of the Engineer license certificateFile: Engineer certificate self attested.pdf | 20 Jan 2024 |
| self-attested copy of the Engineer license certificateFile: Engr license self attested.pdf | 20 Jan 2024 |
| original copy of the section 3(1) notarized affidavit.File: original notorized.pdf | 20 Jan 2024 |
| Proforma of the agreement for sale.File: Profoma for agreement of sale.pdf | 20 Jan 2024 |
| self attested copy of the Power supply NOCFile: Mescom noc with receipts self attested.pdf | 20 Jan 2024 |
| self attested copy of the Water NOCFile: Water NOC self attested.pdf | 20 Jan 2024 |
| statbility certificateFile: Stability certificate.pdf | 20 Jan 2024 |
| STP design drawing certified by the EngineerFile: STP drawing Nirvana.pdf | 20 Jan 2024 |
| stp layout drawingFile: STP.pdf | 20 Jan 2024 |
| GPAFile: GPA.pdf | 20 Jan 2024 |
| ClarificationFile: clarification.pdf | 20 Jan 2024 |
| source of fundsFile: Source of fund.pdf | 20 Jan 2024 |
| bank 100File: BANK 100.jpeg | 20 Jan 2024 |
| bank 70File: BANK 70.jpeg | 20 Jan 2024 |
| bank 30File: BANK 30.jpeg | 20 Jan 2024 |
| KSPCBFile: Pollution NOC.pdf | 20 Jan 2024 |
| RTC, survey 95/2A1P | - |
| Mutation, survey 95/2A1P | - |
| Encumbrance Certificate, survey 95/2A1P | - |
| Conversion/Alienation Order, survey 95/2A1P | - |
| Sale/Title/Gift Deed, survey 95/2A1P | - |
| JDA, survey 95/2A1P | - |
| Khatha, survey 95/2A1P | - |
| Registration CertificateFile: Trade license Nirvana.pdf | - |
| Certificate issued by CA Form 1File: Walk in Nirvana RERA Form 1.pdf | - |
| Certificate issued by Architect Form 2File: Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non litigation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: Walk in Nirvana RERA Form 1.pdf | - |
| Balance Sheet 2022 - 2023File: BS and PL 23.pdf | - |
| Balance Sheet 2021 - 2022File: BS and PL 22.pdf | - |
| Balance Sheet 2020 - 2021File: BS PL 21.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: BS and PL 23.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: BS and PL 22.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: BS PL 21.pdf | - |
| Auditor's Report 2022 - 2023File: Audit report 23.pdf | - |
| Auditor's Report 2021 - 2022File: audit report 22.pdf | - |
| Auditor's Report 2020 - 2021File: audit report 21.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR 23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR 22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR 21.pdf | - |
| NIRVANA LICENCE | - |
| MESCOM NOC WITH RECEIPT | - |
| WATER NOC | - |
| Approved Plan | - |
| Approved Plan | - |
| Approved Plan | - |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| WALK IN AIKYA | PADAVU MANGALORE | Ongoing | Dec 2025 | Not delivered |
| WALK IN LOUANN PLAZA | PANDESHWAR, MANGALORE | Ongoing | Feb 2024 | Not delivered |
| WALK IN MAGNIFICA | KULSHEKAR, MANGALORE | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep WALK IN NIRVANA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 99 registered projects within 2 km.
Shivabagh
Land Trades Builders and Developers
SMRITHI HEIGHTS
Nidhi Land Infrastructure Developers India
BLOOM NEXUS
PARADISE CITADEL PROJECTS
INLAND BUENOS AIRES
M/S IN-LAND BUILDERS
Altitude
LAND TRADES BUILDERS & DEVELOPERS
ROHAN GARDEN
PROPERTY REAL ESTATE & DEVELOPERS
See every Dakshina Kannada project, with the district possession charts
Builder: WALK IN BUILDERS AND DEVELOPERS
WALK IN BUILDERS AND DEVELOPERS has 3 registrations on RERA Karnataka, including WALK IN AEKTA and WALK IN NIRVANA. Its filings declare 6 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if WALK IN NIRVANA is delayed beyond 28 Feb 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of WALK IN NIRVANA?
The registered promoter entity is WALK IN BUILDERS AND DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29AILPD3408LIZ3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in WALK IN NIRVANA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at WALK IN NIRVANA?
The professionals named in the filing: Architect: BABA ALANKAR; Engineer: DESIGN ASSOCIATES ANAND BHAT; Chartered Accountant: NITHIN J SHETTY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in WALK IN NIRVANA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback