This is a sample karnataka buyer report, generated from the real RERA Karnataka filing for Prestige Elm Park, Bengaluru East. About this sample · What the reports cover
or press Ctrl+P / Cmd+P
ReraGenie Buyer Report · Karnataka · Sample
Report date: 12 November 2026
RERA Karnataka filing as updated on 12 November 2026
Bengaluru East · Bengaluru Urban district · PIN 560049

Prestige Elm Park

by Prestige Estates Projects Ltd  ·  RERA Karnataka PRM/KA/RERA/1251/446/PR/250123/005667  ·  ReraGenie RG-KA-38014
Registration
Registration approved
since 25 Jan 2023
Completion date filed
14 Aug 2026
unmoved since registration
Units booked
143 of 192
latest quarterly update
Latest quarterly update
14 Oct 2026
Q2 2026-27

01At a glance

  • Prestige Elm Park is a 192 unit apartment project in 3 towers in Bengaluru East, Bengaluru Urban, registered with RERA Karnataka on 25 January 2023 by Prestige Estates Projects Ltd.
  • 143 of 192 units are booked (74%) in the latest quarterly update, Q2 2026-27, filed 14 Oct 2026.
  • The promoter files its own completion figure at 90%, up from 54% in Q3 2025-26.
  • The filed completion date, 14 August 2026, passed 3 months ago, and the register shows no application for completion.
  • The promoter has 45 other registrations on RERA Karnataka, with 77 complaints across all its projects.
  • No complaint against this project is listed on the register.
Source: RERA Karnataka filing PRM/KA/RERA/1251/446/PR/250123/005667 and 45 other filings of the same promoter, as updated on 12 November 2026.

02Red flags and clear checks

On the record

The filed completion date, 14 Aug 2026, has passed and the register shows no application for completion. see 07
10 construction items not finished past their planned finish date. see 08

Clear

Every applicable clearance (6) reads Approved in the latest quarterly update.
Every flat in the flat table carries a parking lot (192).
A khata is filed for every survey number (1).
A conversion order is filed for every survey number.
No complaint against this project is listed on the register.
The latest quarterly update is less than six months old.
Red means the condition has happened. Amber is a caution on record. These are filed facts, not opinions.

03The units: types, sizes and how they compare

The register lists every unit of this project: 192 in 3 towers. The commonest type is 3 BHK, 108 of them.

TypeUnitsCarpet area range, sq mMedian carpet, sq mExclusive common, sq mParking per unitBalconies, all, sq m
3 BHK
filed as 3 BHK + MAID’S
108104.1 to 124.1115.0
1,238 sq ft
39.11.01,760.0
4 BHK
filed as 4 BHK + MAID’S
84145.0 to 149.2147.1
1,583 sq ft
49.11.01,849.0
How the sizes compare
  • 3 BHK: a median of 115.0 sq m here, against 100.0 sq m for the middle of 750 projects in Bengaluru East taluk; 606 of them are smaller.
  • 4 BHK: a median of 147.1 sq m here, against 159.8 sq m for the middle of 178 projects in Bengaluru East taluk; 59 of them are smaller.

Carpet area by type, against the district

Square metres. Blue bar: this project's range. Gold diamond: its median. Grey band: the middle half of the comparison projects' medians, with their median as the dark line.
3 BHK4 BHK100120140160180200
How to read it: a diamond right of the dark line is a project whose typical unit of that type is larger than the typical project's.
RERA Karnataka unit tables; comparison projects exclude any whose areas read like square feet.

04Your share of the land

The undivided share is the part of the land each unit carries with it. Your sale deed should state it, and it is what a flat owner holds if the building is ever redeveloped, so the figure in your agreement should match the one filed here.

TypeUnits filing a shareMedian shareRange
3 BHK
filed as 3 BHK + MAID’S
10876.3 sq m68.2 to 81.7 sq m
4 BHK
filed as 4 BHK + MAID’S
8495.7 sq m94.8 to 98.1 sq m
  • The shares filed for 192 units add up to 16,015 sq m, against a filed land area of 16,120 sq m.
  • Per square metre of carpet area, a unit here carries a median 0.66 sq m of land. Across 675 projects in Bengaluru East taluk, the middle figure is 0.54, and 521 have a lower figure.

05Parking

  • The unit table allots at least one parking lot to 192 of 192 units.
  • The approved plan files 192 covered, 40 open parking spaces.
  • The latest quarterly update (Q2 2026-27) lists 143 of 192 parking spaces booked and 49 available.
  • That is 1.00 lots per unit. Across 1,049 projects in Bengaluru East taluk filing lots per unit, the middle figure is 1.00, and 65 have fewer.
The filing does not say whether parking meets the planning authority's norm; this report compares filings and states no adequacy.

06Towers and the approved plan

All 3 towers are filed as residential.

TowerFloorsBasementsHeightUnitsUnits a floorParking
Tower 117255.4 m72472
Tower 211237.0 m48448
Tower 317255.4 m72472
Approved plan numberBBMP/Addl.Dir/JDNorth/0050/22
Plan approved on14 December 2022
Approving authorityBBMP - Bruhat Bengaluru Mahanagara Palike
Land area16,120 sq m
Built-up area, as filed54,529 sq m
Carpet area, plan total24,338 sq m
Plinth area3,203 sq m
FAR sanctioned2.23
399 of 935 projects in Bengaluru East taluk file a lower FAR; middle figure 2.25
TDR usedNo
Same plan registered beforeNo
Source of water, as filedBoreWell, BWSSB
560 of 979 projects in Bengaluru Urban district that file a water source name a borewell
Built-up area includes areas FAR does not count, such as basements and parking, so the two are printed side by side and not divided into a claim about FAR used.

07The possession story

No extension, date passed 3 months ago

Registration to the completion date now on file.
Registered Jan 2023Promised Aug 2026
RERA Karnataka project details and extension tab.
Standing on the registerRegistration approved
Registered25 January 2023
Construction start, as filed15 April 2023
First completion date14 August 2026
Completion date now on file14 August 2026
RERA Karnataka files Approved whatever the date, so it says the registration was approved, not that it is current.
Against the area
  • The completion date has not moved since registration. Of 1,227 projects in Bengaluru East taluk, 753 have not moved theirs either.

08Construction against its own schedule

  • The latest quarterly update (Q2 2026-27) files 18 construction items with planned and actual dates; 8 are finished.
  • 10 unfinished items are past the planned finish date, the oldest by 10 months.
  • Of 8 finished items with both dates, 7 finished more than a month late; the middle item finished 7 months after its planned date.

Construction schedule, planned against actual

Every work item in the Q2 2026-27 update. The dashed line is the report date.
planneddoneunder way, past its planned finishEarth work and other leveling prepar...Foundation footing workUpto Plinth LevelSub-structure flooring (Parking Floo...Retaining wall (All types)RCC or MS Framed structureMasonry ConstructionPlastering inside , outside & CeilingJoinery: Doors, Windows, Ventilators...90%Basic work of Water supply, Sanitary...80%Dadoing, Skirting, Flooring, Tiles w...90%Railing and Grill fixing95%Electrification, Water supply and Sa...80%Painting70%Fire prevention and fire fighting fi...75%Weather Proof work(tile,concrete)80%Elevation work70%Internal and External work including...70%202420252026
How to read it: the outline is the promoter's own plan; the filled bar below it is what the same promoter filed as happening.
RERA Karnataka quarterly update, as filed by the promoter.
Item past its planned finishPlanned finishDone, as filed
Weather Proof work(tile,concrete)31 Jan 202680%
Railing and Grill fixing1 Mar 202695%
Basic work of Water supply, Sanitary and Electrification1 Apr 202680%
Dadoing, Skirting, Flooring, Tiles work (All types)1 May 202690%
Joinery: Doors, Windows, Ventilators etc10 May 202690%
Fire prevention and fire fighting fitting and fixture with network30 Jun 202675%
Electrification, Water supply and Sanitary Finishing31 Jul 202680%
Painting10 Aug 202670%
Elevation work10 Aug 202670%
Internal and External work including landscapes as per sanctioned drawings10 Aug 202670%

The promoter's own completion figure: 54% in Q3 2025-26, 60% in Q4 2025-26, 88% in Q1 2026-27, 90% in Q2 2026-27. From Q3 2025-26 that is +36 points over 3 quarters.

This figure is the promoter's own; RERA Karnataka does not inspect it.
Floor by floor, latest update
  • Tower 1: floors 0 to 17 at 70% to 95%; the tower figure is 81%.
  • Tower 2: floors 0 to 11 at 95% to 100%; the tower figure is 98%.
  • Tower 3: floors 0 to 17 at 50% to 85%; the tower figure is 76%.
Floor percentages are the promoter's frame for the tower, not a measure of any one unit.

09What is still available, by type

Booked and available units by type, from the quarterly update filed 14 October 2026.

TypeUnitsBookedAvailableBookings, earliest update shown
3 BHK1088028up from 74 in Q3 2025-26
4 BHK846321up from 58 in Q3 2025-26
Booked is the register's word; RERA Karnataka files no separate sold figure, and its project page shows only the last four quarterly updates.

10Approvals and clearances

Each clearance this project files, with its status as the promoter reports it in the quarterly update of 14 October 2026, the fee filed against it and whether a document under that name is on the register.

ClearanceStatus, as reportedApplied onDocuments
Commencement certificatenot in the update1 on file
Fire and safetyApproved29 Aug 20225 on file
Pollution control board (KSPCB)Approved18 Oct 20229 on file
Environment clearance (SEIAA or MoEF)Approved19 Sep 20221 on file
Airport Authority height clearanceApproved24 Feb 20225 on file
Power supply (BESCOM, KPTCL)Approved5 Aug 20227 on file
Water and sewage boardApproved6 Mar 20236 on file

Approval costs filed in total: Rs 6.3 crore.

A document on the register shows something was uploaded under that title. This report does not read it and does not say a clearance was granted.

11Amenities and outside works

41 amenities and internal works are filed as applicable, with progress from the latest quarterly update.

  • Internal Infrastructure (7): 50% to 70% done, as filed
    Water Supply 70%, Sewage and Drainage System 70%, Water conservation/rain water harvesting/recharge of ground water 70%, Energy management 50%, Fire protection and fire safety requirements 70%, Solid waste management and disposal 70%, Emergency Evacuation services 70%
  • External Infrastructure (13): 50% to 85% done, as filed
    Water Supply 70%, Internal Roads & Footpaths 70%, Sewage and Drainage System 80%, Solid waste management and disposal 70%, Emergency Evacuation services 70%, Storm water drains 85%, Use of renewable energy 50%, Water conservation/rain water harvesting/recharge of ground water 70%, Fire protection and fire safety requirements 70%, Sewage Treatment Plant (STP) 80%, Parks & Tree planting 50%, Street Lighting 50%, Electricity supply transformer 75%
  • Amenities (11): 50% to 90% done, as filed
    Electricity 50%, CCTV Surveillance 70%, Club House 85%, Community Hall 90%, Outdoor Sports facility 85%, Indoor Sports facility 85%, Swimming Pool 90%, Gym 90%, Parks 50%, Power Backup 50%, Water and Sanitation 75%
  • Common Areas (10): 65% to 99% done, as filed
    Staircases 80%, Lifts 75%, Corridor/Lobbies 75%, Fire escapes 80%, Common entrance and exit for the building/common portico/foyer/verandah 70%, Basement 75%, Terrace 85%, Outer Wall 99%, Open parking areas 65%, Water conservation and renewable energy 75%

12Money: collected, withdrawn and spent

Rs 257.8 cr
project cost, as filed
Rs 90.2 cr
land cost, as filed
Rs 167.6 cr
development cost, as filed
Rs 161.3 cr
construction estimate certified by the engineer
Land as a share of cost35% of the project cost
762 of 1,021 projects in Bengaluru East taluk file a lower share; middle figure 22%
Money borrowed for the projectNo, as declared
Land mortgagedNo, as declared
Money lines in each quarterly update
QuarterFiledAdvance from buyersWithdrawnConstruction spend
Q3 2025-2615 Jan 2026Rs 10.6 croreRs 12.4 croreRs 117.0 crore
Q4 2025-2615 Apr 2026Rs 10.4 croreRs 15.4 croreRs 124.7 crore
Q1 2026-2715 Jul 2026Rs 4.0 croreRs 6.3 croreRs 124.7 crore
Q2 2026-2714 Oct 2026Rs 4.1 croreRs 11.4 croreRs 127.1 crore
These are printed exactly as each quarterly update files them. Promoters file them both as running totals and as figures for the quarter alone (the advance falls from one quarter to the next on a third of all consecutive updates), so this report adds no quarters together and draws no ratio across them.

The designated project account is filed with KOTAK MAHINDRA BANK, Lavelle Road, Bangalore (IFSC KKBK0000422). Pay into the account your agreement names, and check it is this one.

The RERA Act requires 70% of the money collected from buyers to be kept in a separate account and used for the land and construction of this project.

13The promoter's financial statements on file

The promoter's financial statements on the register, by year. This report lists which are filed; it does not read them.

Statement2019-202020-212021-22
Auditor's Reporton fileon fileon file
Balance Sheeton fileon fileon file
Cash Flow Statementnot on fileon fileon file
Director's Reporton fileon fileon file
Profit and losson fileon fileon file
Tax returnon fileon fileon file
Marked not applicable: the slot holds a file the promoter labelled not applicable rather than a statement.

14Land and title, survey by survey

What the promoter filed about the land, survey number by survey number. The register holds the promoter's filing, not a title search, and nothing here is a title opinion.

Survey number 142

Extent4 Acres 10 Guntas/17199 Sq. Mts.
Held asJDA Land
How the promoter acquired it, as filedPurchased Land
Owners on record1
Conversion to non-agricultural useOrder ALN(EBK)SR/95/2014-15, 8 February 2016, Office of the Deputy Commissioner, Bengaluru, for residential use
Sale or title deedBNS-1-16649-2015-16, registered 12 February 2016 at Sub-Registrar,Shivajinagara, Bengaluru
from Kamalamma & others to Gaffar Baig & others
Joint development agreementRegistered, 31 December 2021 at Sub-registrar, Banaswadi, Bengaluru
KhataA Khatha, number 2057/142/ 284, 12 November 2020, BBMP
Guidance value, as filed3,160
the register does not state the unit
In date orderFeb 2016 converted; Feb 2016 deed registered; Nov 2020 khata; Dec 2021 joint development registered; Dec 2022 plan approved; Jan 2023 registered with RERA
Land documents on the registerRTC, Mutation, Encumbrance certificate, Khata, Conversion order, Sale or title deed, JDA
Landowners as filed
NameSurvey numberShare
Gaffar Baig14235%

Total land area filed: 16,120 sq m, of which 3,203 sq m is covered by building.

15Who you are dealing with

Promoter, as filedPRESTIGE ESTATES PROJECTS LTD
Entity typeCompany
Company or firm registration numberU07010KA1997PLC022322
GSTIN29AABCP8096K1ZP
Websitewww.prestigeconstrucitons.com
Office address, as filedPrestige Falcon Towers, No. 19, Brunton, Road, Bengaluru East, Bengaluru, Bengaluru East, Bengaluru Urban-560025
People named in the filing
NameDesignation, as filed
Swaroop AnishAuthorized Signatory
Irfan RazackCMD
Rezwan RazackDirector
Noaman RazackDirector
Raghavendra NProject Head
Professionals and contractors named
RoleNameRegistration or licence
ArchitectZachariah ConsultantsCA/2010/47015
EngineerPrasad ConsultantsBCC/BL-3.6/S.E :276:18-19
Chartered AccountantM Padmanabha Bhat025305
ContractorK2K Infrastructure (I) Pvt Ltd

16The promoter's record

RERA Karnataka registers each project alone. Joining every registration of Prestige Estates Projects Ltd gives the record a buyer needs: 45 other registrations, all from the register's own list for this promoter.

45
other registrations on RERA Karnataka
14
with an occupancy certificate filed as received
13
applied for completion, no OC filed yet
6
past the filed completion date, no completion filed

How far each registration's completion date has moved

One dot per registration by this promoter; the gold dot is this project.
05101621 months26 projects at zerothis project · 0
How to read it: each dot is one of this promoter's registrations, placed by how many months its filed completion date has moved; further right is a longer move. It is a spread, not a ranking.
RERA Karnataka project details.
This promoter's registrationsDistrictUnitsBookedCompletion dateComplaints
Prestige Gardenia Estate Phase 2Bengaluru RurallayoutOct 2027
Evergreen @ Prestige Raintree ParkBengaluru Urban2,0001,559 of 2,000Jun 2030
Prestige Crystal LawnsBengaluru RurallayoutMar 2027
Prestige GreenbrookBengaluru RurallayoutMar 2027
Prestige Autumn LeavesBengaluru RurallayoutMar 20271
Prestige Gardenia EstateBengaluru RurallayoutApr 2027
Prestige SuncrestBengaluru Urban437437 of 437Sep 2028
Prestige White Meadows - Clover LeafBengaluru Urban104Aug 20241
Prestige Pine ForestBengaluru Urban316210 of 316Dec 2028
Prestige Raintree ParkBengaluru Urban1,5201,455 of 1,520Dec 20281
Prestige Camden GardensBengaluru Urban117117 of 117Dec 2027
Prestige SomervilleBengaluru Urban306306 of 306Dec 2027
Prestige Elm Park · this reportBengaluru Urban192143 of 192Aug 2026
Showing the newest 12 of 45. Every one is on the promoter's page on reragenie.com and on the register.

77 complaints against this promoter across all its RERA Karnataka projects (73 disposed, 3 under enquiry, 1 posted for orders).

Registrations the promoter declares in other states
RegistrationStateProject on ReraGenieStatus thereCompletion date filed
P51900031285MaharashtraPrestige Jasdan ClassicCompleted31 Dec 2025
Maharashtra registrations are matched to ReraGenie's MahaRERA data by their registration number.
Earlier projects the promoter declares
ProjectDistrictStatus, as declaredCompletion date declared
Prestige WaterfordBengaluru RuralOngoingDec 2023
A declaration by the promoter; RERA Karnataka files no finish date for these.

17Within 2 km of the project

45 RERA Karnataka registrations sit within 2 km of this project's filed location; the nearest 12 are below. Booking and unit sizes appear only where a project files them.

ProjectDistanceTypeUnitsBookedMedian 2 BHKCompletion date
Urban Forest0.1 kmResidential63680.1 sq mDec 2018
Gopalan Aqua0.2 kmResidential32086.3 sq mDec 2024
Ankuraa Lotus0.4 kmResidential8475.8 sq mDec 2022
Desai Radiant0.4 kmResidential130Jan 2018
S.V.Prime0.5 kmMixed260178 of 26070.3 sq mNov 2025
Sbr One Residence0.5 kmMixed931261 of 931Dec 2030
The Loft0.5 kmResidential14435 of 14490.8 sq mDec 2029
Balaji Aavaas0.7 kmResidential12574.9 sq mDec 2019
Sree Samruddhi0.7 kmResidential60Sep 2024
Ark Oak Tree0.7 kmResidential176101 of 17675.7 sq mFeb 2028
Disha Courtyard0.7 kmResidential26471.8 sq mSep 2022
Cloud Forest0.7 kmResidential798470 of 79878.2 sq mOct 2029
Straight-line distance between filed map locations.

18This project against its district

This project against the other building projects of its taluk, or its district where the taluk has fewer than 20 filing a figure. Each row compares only projects that file that figure.

MeasureThis projectMiddle projectCompared withPosition
Median carpet area, 3 BHK115.0 sq m100.0 sq m750, Bengaluru East taluk606 smaller
Median carpet area, 4 BHK147.1 sq m159.8 sq m178, Bengaluru East taluk59 smaller
Land share per sq m of carpet0.660.54675, Bengaluru East taluk521 lower
Parking lots per unit1.001.001,049, Bengaluru East taluk65 fewer
FAR sanctioned2.232.25935, Bengaluru East taluk399 lower
Land as a share of project cost35%22%1,021, Bengaluru East taluk762 lower
Months the completion date has moved001,227, Bengaluru East taluk753 also unmoved

19Filing discipline

The quarterly updates the register shows for this project. Its project page shows the last four at most.

QuarterFiled on
Q3 2025-2615 Jan 2026
Q4 2025-2615 Apr 2026
Q1 2026-2715 Jul 2026
Q2 2026-2714 Oct 2026

18 documents were uploaded in answer to the authority's enquiries during registration: No litigation Affidavit; Opinion; Joint Affidavit; Guidelines value; Sanction level floor plan; Village map; CDP map; Specifications; Engineer Structural safety certificate; Allotment letter; Sec 3 (1)Affidavit; BESCOM NOC along with fee receipt; KSFES NOC along with fee receipt; BWSSB Demand note with Affidavit and more.

120 documents in all: 36 quarterly updates, 22 project documents, 18 answers to enquiries, 17 financial statements, 10 extension, 8 land, 7 certificates, 2 promoter.

20What to verify before you book

  1. Ask the promoter for the revised completion date and the reason, and check the register's extension tab before you pay further instalments.
  2. Ask for the current schedule of the items past their planned finish, and compare the quarterly update with what you see on site.
  3. Match the carpet area and undivided share in your agreement against your unit's row in the appendix.
  4. Check that the parking lot allotted to your unit is named in the agreement.
  5. Ask for the khata and the conversion order for your survey number and match them against the land section.
  6. Check that the approved plan number in your agreement is BBMP/Addl.Dir/JDNorth/0050/22.
  7. Pay only into the designated project account named in the money section.
  8. Compare your agreement for sale with the proforma agreement the promoter filed with RERA Karnataka.
Drawn from this filing. Not legal advice.

21Your rights under the RERA Act

  • Delay. Under section 18 of the RERA Act, if possession is not given by the date in your agreement you may withdraw and get your money back with interest, or stay and be paid interest for every month of delay. The rate is the one the Karnataka RERA rules prescribe; confirm the current figure with the authority or a lawyer before relying on an amount.
  • Advance. Under section 13 the promoter may not take more than 10% of the cost as an advance before a registered agreement for sale.
  • Changes to your unit. Under section 14 the promoter may not change the sanctioned plan or specifications of your unit without your consent, and needs two thirds of allottees for other changes.
  • Structural defects. Under section 14(3) the promoter must fix structural defects reported within five years of possession.
  • Information. Under section 19 you are entitled to the stage-wise completion schedule and the sanctioned plans.
  • Complaints. A complaint can be filed online with RERA Karnataka at rera.karnataka.gov.in.

22What this filing does not contain

  • No sale price: RERA Karnataka files no price for any unit.
  • Booked, not sold: the register files units booked and has no separate sold figure; its project page shows only the last four quarterly updates.
  • No title search: the land section restates the promoter's filing and is not a title opinion.
  • The guidance value is filed without a unit.
  • No lender or loan amount: the filing says only whether the land is mortgaged and whether money was borrowed.
  • Nothing read from the documents: this report lists the filed documents and does not read them.
  • The promoter's completion figure, floor percentages and money lines are the promoter's own filings; RERA Karnataka does not inspect them.

23Appendix: every unit as filed

Every unit as the register lists it. Find yours by its number and check the agreement against this row.

TowerFloorUnitTypeCarpet area (sq m)Exclusive common area (sq m)Undivided shareParking lots
Tower 1010013 BHK + MAID’S115.039.176.31
Tower 1010023 BHK + MAID’S120.240.579.01
Tower 1010033 BHK + MAID’S124.141.981.71
Tower 1010043 BHK104.135.769.61
Tower 1110113 BHK + MAID’S115.039.176.31
Tower 1110123 BHK + MAID’S120.240.579.01
Tower 1110133 BHK + MAID’S124.141.981.71
Tower 1110143 BHK104.135.769.61
Tower 1210213 BHK + MAID’S115.039.176.31
Tower 1210224 BHK + MAID’S145.048.694.81
Tower 1210234 BHK + MAID’S149.250.398.11
Tower 1210243 BHK104.135.769.61
Tower 1310313 BHK + MAID’S115.039.176.31
Tower 1310324 BHK + MAID’S145.048.694.81
Tower 1310334 BHK + MAID’S149.250.398.11
Tower 1310343 BHK104.135.769.61
Tower 1410413 BHK + MAID’S115.039.176.31
Tower 1410424 BHK + MAID’S145.048.694.81
Tower 1410434 BHK + MAID’S149.250.398.11
Tower 1410443 BHK104.135.769.61
Tower 1510513 BHK + MAID’S115.039.176.31
Tower 1510524 BHK + MAID’S145.048.694.81
Tower 1510534 BHK + MAID’S149.250.398.11
Tower 1510543 BHK104.135.769.61
Tower 1610613 BHK + MAID’S115.039.176.31
Tower 1610624 BHK + MAID’S145.048.694.81
Tower 1610634 BHK + MAID’S149.250.398.11
Tower 1610643 BHK104.135.769.61
Tower 1710713 BHK + MAID’S115.039.176.31
Tower 1710724 BHK + MAID’S145.048.694.81
Tower 1710734 BHK + MAID’S149.250.398.11
Tower 1710743 BHK104.135.769.61
Tower 1810813 BHK + MAID’S115.039.176.31
Tower 1810824 BHK + MAID’S145.048.694.81
Tower 1810834 BHK + MAID’S149.250.398.11
Tower 1810843 BHK104.135.769.61
Tower 1910913 BHK + MAID’S115.039.176.31
Tower 1910924 BHK + MAID’S145.048.694.81
Tower 1910934 BHK + MAID’S149.250.398.11
Tower 1910943 BHK104.135.769.61
Tower 11011013 BHK + MAID’S115.039.176.31
Tower 11011024 BHK + MAID’S145.048.694.81
Tower 11011034 BHK + MAID’S149.250.398.11
Tower 11011043 BHK104.135.769.61
Tower 11111113 BHK + MAID’S115.039.176.31
Tower 11111124 BHK + MAID’S145.048.694.81
Tower 11111134 BHK + MAID’S149.250.398.11
Tower 11111143 BHK104.135.769.61
Tower 11211213 BHK + MAID’S115.039.176.31
Tower 11211224 BHK + MAID’S145.048.694.81
Tower 11211234 BHK + MAID’S149.250.398.11
Tower 11211243 BHK104.135.769.61
Tower 11311313 BHK + MAID’S115.039.176.31
Tower 11311324 BHK + MAID’S145.048.694.81
Tower 11311334 BHK + MAID’S149.250.398.11
Tower 11311343 BHK104.135.769.61
Tower 11411413 BHK + MAID’S115.039.176.31
Tower 11411424 BHK + MAID’S145.048.694.81
Tower 11411434 BHK + MAID’S149.250.398.11
Tower 11411443 BHK104.135.769.61
Tower 11511513 BHK + MAID’S115.039.176.31
Tower 11511524 BHK + MAID’S145.048.694.81
Tower 11511534 BHK + MAID’S149.250.398.11
Tower 11511543 BHK104.135.769.61
Tower 11611613 BHK + MAID’S115.039.176.31
Tower 11611624 BHK + MAID’S145.048.694.81
Tower 11611634 BHK + MAID’S149.250.398.11
Tower 11611643 BHK104.135.769.61
Tower 11711713 BHK + MAID’S115.039.176.31
Tower 11711724 BHK + MAID’S145.048.694.81
Tower 11711734 BHK + MAID’S149.250.398.11
Tower 11711743 BHK104.135.769.61
Tower 2020013 BHK + MAID’S115.039.176.31
Tower 2020023 BHK + MAID’S120.240.579.01
Tower 2020033 BHK + MAID’S124.140.979.91
Tower 2020043 BHK104.134.968.21
Tower 2120113 BHK + MAID’S115.039.176.31
Tower 2120123 BHK + MAID’S120.240.579.01
Tower 2120133 BHK + MAID’S124.140.979.91
Tower 2120143 BHK104.134.968.21
Tower 2220213 BHK + MAID’S115.039.176.31
Tower 2220224 BHK + MAID’S145.048.694.81
Tower 2220234 BHK + MAID’S149.249.195.71
Tower 2220243 BHK104.134.968.21
Tower 2320313 BHK + MAID’S115.039.176.31
Tower 2320324 BHK + MAID’S145.048.694.81
Tower 2320334 BHK + MAID’S149.249.195.71
Tower 2320343 BHK104.134.968.21
Tower 2420413 BHK + MAID’S115.039.176.31
Tower 2420424 BHK + MAID’S145.048.694.81
Tower 2420434 BHK + MAID’S149.249.195.71
Tower 2420443 BHK104.134.968.21
Tower 2520513 BHK + MAID’S115.039.176.31
Tower 2520524 BHK + MAID’S145.048.694.81
Tower 2520534 BHK + MAID’S149.249.195.71
Tower 2520543 BHK104.134.968.21
Tower 2620613 BHK + MAID’S115.039.176.31
Tower 2620624 BHK + MAID’S145.048.694.81
Tower 2620634 BHK + MAID’S149.249.195.71
Tower 2620643 BHK104.134.968.21
Tower 2720713 BHK + MAID’S115.039.176.31
Tower 2720724 BHK + MAID’S145.048.694.81
Tower 2720734 BHK + MAID’S149.249.195.71
Tower 2720743 BHK104.134.968.21
Tower 2820813 BHK + MAID’S115.039.176.31
Tower 2820824 BHK + MAID’S145.048.694.81
Tower 2820834 BHK + MAID’S149.249.195.71
Tower 2820843 BHK104.134.968.21
Tower 2920913 BHK + MAID’S115.039.176.31
Tower 2920924 BHK + MAID’S145.048.694.81
Tower 2920934 BHK + MAID’S149.249.195.71
Tower 2920943 BHK104.134.968.21
Tower 21021013 BHK + MAID’S115.039.176.31
Tower 21021024 BHK + MAID’S145.048.694.81
Tower 21021034 BHK + MAID’S149.249.195.71
Tower 21021043 BHK104.134.968.21
Tower 21121113 BHK + MAID’S115.039.176.31
Tower 21121124 BHK + MAID’S145.048.694.81
Tower 21121134 BHK + MAID’S149.249.195.71
Tower 21121143 BHK104.134.968.21
Tower 3030013 BHK + MAID’S115.039.176.31
Tower 3030023 BHK + MAID’S120.241.480.81
Tower 3030033 BHK + MAID’S124.140.979.91
Tower 3030043 BHK104.134.968.21
Tower 3130113 BHK + MAID’S115.039.977.81
Tower 3130123 BHK + MAID’S120.241.480.81
Tower 3130133 BHK + MAID’S124.140.979.91
Tower 3130143 BHK104.134.968.21
Tower 3230213 BHK + MAID’S115.039.977.81
Tower 3230224 BHK + MAID’S145.049.596.61
Tower 3230234 BHK + MAID’S149.249.195.71
Tower 3230243 BHK104.134.968.21
Tower 3330313 BHK + MAID’S115.039.977.81
Tower 3330324 BHK + MAID’S145.049.596.61
Tower 3330334 BHK + MAID’S149.249.195.71
Tower 3330343 BHK104.134.968.21
Tower 3430413 BHK + MAID’S115.039.977.81
Tower 3430424 BHK + MAID’S145.049.596.61
Tower 3430434 BHK + MAID’S149.249.195.71
Tower 3430443 BHK104.134.968.21
Tower 3530513 BHK + MAID’S115.039.977.81
Tower 3530524 BHK + MAID’S145.049.596.61
Tower 3530534 BHK + MAID’S149.249.195.71
Tower 3530543 BHK104.134.968.21
Tower 3630613 BHK + MAID’S115.039.977.81
Tower 3630624 BHK + MAID’S145.049.596.61
Tower 3630634 BHK + MAID’S149.249.195.71
Tower 3630643 BHK104.134.968.21
Tower 3730713 BHK + MAID’S115.039.977.81
Tower 3730724 BHK + MAID’S145.049.596.61
Tower 3730734 BHK + MAID’S149.249.195.71
Tower 3730743 BHK104.134.968.21
Tower 3830813 BHK + MAID’S115.039.977.81
Tower 3830824 BHK + MAID’S145.049.596.61
Tower 3830834 BHK + MAID’S149.249.195.71
Tower 3830843 BHK104.134.968.21
Tower 3930913 BHK + MAID’S115.039.977.81
Tower 3930924 BHK + MAID’S145.049.596.61
Tower 3930934 BHK + MAID’S149.249.195.71
Tower 3930943 BHK104.134.968.21
Tower 31031013 BHK + MAID’S115.039.977.81
Tower 31031024 BHK + MAID’S145.049.596.61
Tower 31031034 BHK + MAID’S149.249.195.71
Tower 31031043 BHK104.134.968.21
Tower 31131113 BHK + MAID’S115.039.977.81
Tower 31131124 BHK + MAID’S145.049.596.61
Tower 31131134 BHK + MAID’S149.249.195.71
Tower 31131143 BHK104.134.968.21
Tower 31231213 BHK + MAID’S115.039.977.81
Tower 31231224 BHK + MAID’S145.049.596.61
Tower 31231234 BHK + MAID’S149.249.195.71
Tower 31231243 BHK104.134.968.21
Tower 31331313 BHK + MAID’S115.039.977.81
Tower 31331324 BHK + MAID’S145.049.596.61
Tower 31331334 BHK + MAID’S149.249.195.71
Tower 31331343 BHK104.134.968.21
Tower 31431413 BHK + MAID’S115.039.977.81
Tower 31431424 BHK + MAID’S145.049.596.61
Tower 31431434 BHK + MAID’S149.249.195.71
Tower 31431443 BHK104.134.968.21
Tower 31531513 BHK + MAID’S115.039.977.81
Tower 31531524 BHK + MAID’S145.049.596.61
Tower 31531534 BHK + MAID’S149.249.195.71
Tower 31531543 BHK104.134.968.21
Tower 31631613 BHK + MAID’S115.039.977.81
Tower 31631624 BHK + MAID’S145.049.596.61
Tower 31631634 BHK + MAID’S149.249.195.71
Tower 31631643 BHK104.134.968.21
Tower 31731713 BHK + MAID’S115.039.977.81
Tower 31731724 BHK + MAID’S145.049.596.61
Tower 31731734 BHK + MAID’S149.249.195.71
Tower 31731743 BHK104.134.968.21