Home / Browse projects / Mumbai Suburban, Maharashtra / Vrindavan

Registration lapsed No litigation declared Others project

Vrindavan

By JE AND VEE INFRASTRUCTURE

RG-MH-53997 · RERA P51800017298 · Last updated on MahaRERA portal: 18 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
4 of 11Construction stages donefurthest along: Staircases, 80%
2Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Vrindavan is a Others project by JE AND VEE INFRASTRUCTURE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017298 on 31 Jul 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVrindavan
  • TypeOthers
  • Location
    • BUILDING NO 15 SHIVDHAM COMPLEX DINDOSHI MALAD EAST
    • OPP OBEROI MALL
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • RERA no.P51800017298
  • ReraGenie IDRG-MH-53997

Builder

  • NameJE AND VEE INFRASTRUCTURE
  • Entity typePartnership
  • PartnerDIPESH SURENDRAPRASAD SINGH
  • Other registrations8 more →
  • Completed1 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

22 months past promisethis monthRegisteredJul 2018PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2018
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VrindavanNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

Vrindavan: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure23%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 18 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed61

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots61
Closed/Covered61

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area674 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Dindoshi Vrindavan CHS LtdBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI2021.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOREGAON WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThree Dimensional Consultants LLP
EngineerHIREN M TANNA
PartnerRole in project
JE AND VEE INFRASTRUCTURE-

Litigation declared2

CaseCourtStatus
10281/2019BOMBAY HIGH COURTDisposed
12996/2019Supreme Court Of IndiaDisposed

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000396321Mr. Vinay SinghNeha Patil19/06/2023
CC006000000396322Mr. Vinay SinghNilesh Patil19/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jan 2022

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: CA FORM.pdf18 Oct 2023
Details of encumbrancesFile: Vrindavan Encumbrance Letter .pdf12 Dec 2022
Building plan approvalFile: Basement IOD.pdf30 Aug 2022
Building plan approvalFile: Basement IOD PLAN.pdf30 Aug 2022
Building plan approvalFile: CFO-REMARK.pdf30 Aug 2022
Building plan approvalFile: CFO PLANS.pdf30 Aug 2022
Building Plan Approval (IOD)File: Basement IOD.pdf30 Aug 2022
Building Plan Approval (IOD)File: Basement IOD PLAN.pdf30 Aug 2022
Building Plan Approval (IOD)File: CFO-REMARK.pdf30 Aug 2022
Building Plan Approval (IOD)File: CFO PLANS.pdf30 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Basement - CC.pdf30 Aug 2022
OtherFile: OC Plans.pdf7 May 2022
OtherFile: VRINDAVAN - OC.pdf1 May 2022
Building plan approvalFile: IOD -22nd Floor.pdf19 Jan 2022
Building plan approvalFile: 1_0001.pdf19 Jan 2022
Building plan approvalFile: 2_0001.pdf19 Jan 2022
Building plan approvalFile: 3_0001.pdf19 Jan 2022
Building plan approvalFile: 4_0001.pdf19 Jan 2022
Building plan approvalFile: 5_0001.pdf19 Jan 2022
Building plan approvalFile: 6_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: IOD -22nd Floor.pdf19 Jan 2022
Building Plan Approval (IOD)File: 1_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: 2_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: 3_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: 4_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: 5_0001.pdf19 Jan 2022
Building Plan Approval (IOD)File: 6_0001.pdf19 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VRINDAVAN PART OC.pdf19 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: further c c upto 22 floor- Vrindavan.pdf24 Aug 2021
Details of encumbrancesFile: NO ENCUM.pdf9 Feb 2021
Proforma of Allotment letterFile: Draft Agreement.pdf29 Aug 2019
Copy of the legal title reportFile: TITLE CERTIFICATE 1.pdf27 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: Vrindavan Plinth CC.pdf26 Jun 2019
Certificates of CA (Form 3)File: CA certificate for RERA.pdf26 Jul 2018
Layout approvalFile: Vrindavan Layout.pdf20 Jul 2018
Copy of Layout Approval (in case of layout)File: Vrindavan Layout.pdf20 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Vrindavan IOD COPY - 1.pdf20 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: VRINDAVAN IOD COPY - 2-min.pdf20 Jul 2018
Proforma of Allotment letterFile: Vrindavan Allotment Letter.pdf20 Jul 2018
OtherFile: Offer Letter 1-5.pdf20 Jul 2018
OtherFile: Offer Letter 6-9.pdf20 Jul 2018
Declaration in FORM BFile: Affidavite cum declaration - Vrindavan - RERA.pdf18 Jul 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Vrindavan Society formation certificate.pdf18 Jul 2018
Status of ConveyanceFile: Sale Deed - Vrindavan - MHADA.pdf18 Jul 2018
Status of ConveyanceFile: Lease Deed - Vrindavan - MHADA.pdf18 Jul 2018
Building plan approvalFile: VRINDAVAN IOD PLAN-Compressed.pdf17 Jul 2018
PAN CardFile: JE AND VEE INFRASTRUCTURE - Paartnership PAN Card.pdf17 Jul 2018
Copy of the legal title reportFile: Title Certificate - Vrindavan.pdf17 Jul 2018
Details of encumbrancesFile: DECLARATION FOR NO ENCUMBRANCE - Vrindavan.pdf17 Jul 2018
Building Plan Approval (IOD)File: VRINDAVAN IOD PLAN-Compressed.pdf17 Jul 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
PRAYAG HEIGHTSBUILDING NO 13 SHIVDHAM COMPLEX DINDOSHI MALAD - EAST MUMBAI - 400097157CompletedDec 2022Dec 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vrindavan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP OBEROI MALL6,700+ in Mumbai Suburban

Builder: JE AND VEE INFRASTRUCTURE

JE AND VEE INFRASTRUCTURE has 9 registrations on MahaRERA, including Vrindavan and MADHUBAN. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Vrindavan shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vrindavan is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vrindavan?

The registered promoter entity is JE AND VEE INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vrindavan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vrindavan?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vrindavan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vrindavan?

The professionals named in the filing: Architect: Three Dimensional Consultants LLP; Engineer: HIREN M TANNA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vrindavan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vrindavan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vrindavan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.