Home / Browse projects / Mumbai City, Maharashtra / VRAJ TIARA

Completed No litigation declared Residential / Group Housing project

VRAJ TIARA

By VRAJ REALTORS

RG-MH-09664 · RERA P51900002902 · Last updated on MahaRERA portal: 10 Jan 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

VRAJ TIARA is a Residential / Group Housing project by VRAJ REALTORS in Mumbai City, Maharashtra, registered with MahaRERA as P51900002902 on 4 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVRAJ TIARA
  • TypeResidential / Group Housing
  • Location
    • Veer Nariman Road
    • Worli
    • Mumbai City
    • 400025
  • Pincode400025
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900002902
  • ReraGenie IDRG-MH-09664

Builder

  • NameVRAJ REALTORS
  • Entity typePartnership
  • PartnersHIRAL MITESH BABARIA, MITESH KIRIT BABARIA, DEVANSH SHARAD BABARIA
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed118 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TIARANA420000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

TIARA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed67

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots67
Closed/Covered67

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,134 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5828.3
Proposed, not sanctioned1,445 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch105, 10th Floor, Maker Chambers III,Nariman Point, Mumbai-400021

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR AMEET PAWAR
EngineerJ W CONSULTANTS LLP
PartnerRole in project
VRAJ REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900013545Dec 2022 → Dec 2023

Reason as filed by the promoterI/We the Promoters of the Project name Vraj Tiara registered under project registration no P51900002902. This is to bring to your notice that our project completion is 30th December 2022. We would like to bring to your notice that our project is 100% completed, we have applied for Occupation Certificate but we have not received yet, there are some inventories which are unsold and we are not able to sell those inventories. Hence we are applying for extension. request you grant us extension till 30th December 2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jan 2024

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 31_12_24.pdf10 Jan 2025
Certificates of CA (Form 3)File: VR FORM 3 FY 2023_24.pdf2 Jan 2025
Disclosure of sold/ booked inventoryFile: Disc Of Sold OR Booked Inventory 31_08_24.pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: VR FORM 2 FY 2023_24.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VR FORM 5 FY 2023_24.pdf2 Jan 2025
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 31_03_24.pdf10 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Eng Cert for Quality Assurance Mar 22.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 Eng Cert for Quality Assurance Mar 23.pdf10 Jan 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architects Certificate.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 31_12_23.pdf8 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC of Vraj Tiara.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VR FORM 5 FY 2022_23.pdf5 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VR FORM 2 FY 2022_23.pdf30 Nov 2023
Certificates of CA (Form 3)File: VR FORM 3 FY 2022_23.pdf30 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Dt 28_08_2023.pdf1 Sep 2023
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 31_03_23.pdf28 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC OF VRAJ TIARA.pdf3 Mar 2023
CERSAI detailsFile: CERSAI vRAJ.pdf7 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: HMB INDIVIDUAL DISCLOSURE.pdf7 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: MKB INDIVIDUAL DISCLOSURE.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 04_01_23.pdf4 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: VR FORM 5 F Y 2021_22.pdf28 Dec 2022
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventory 30_09_22.pdf19 Oct 2022
Certificates of CA (Form 5)File: VR FORM 5 FY 2021_22.pdf14 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: VR FORM 5 FY 2021_22.pdf14 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VR FORM 2 FY 2021_22.pdf24 Aug 2022
Certificates of CA (Form 3)File: VR FORM 3 FY 2021_22.pdf24 Aug 2022
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventor 31_03_22.pdf23 Aug 2022
Disclosure of sold/ booked inventoryFile: Disc of Sold Or Booked Inventor 31_07_22.pdf23 Aug 2022
Building plan approvalFile: Sheet No_7.pdf14 Apr 2022
Building plan approvalFile: Sheet No_8.pdf14 Apr 2022
Building plan approvalFile: Sheet No_9.pdf14 Apr 2022
Building plan approvalFile: Sheet No_10.pdf14 Apr 2022
Building plan approvalFile: Sheet No_1.pdf14 Apr 2022
Building plan approvalFile: Sheet No_2.pdf14 Apr 2022
Building plan approvalFile: Sheet No_3.pdf14 Apr 2022
Building plan approvalFile: Sheet No_4.pdf14 Apr 2022
Building plan approvalFile: Sheet No_5.pdf14 Apr 2022
Building plan approvalFile: Sheet No_6.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_1.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_2.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_3.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_4.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_5.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_6.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_7.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_8.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_9.pdf14 Apr 2022
Building Plan Approval (IOD)File: Sheet No_10.pdf14 Apr 2022
Building plan approvalFile: Final Amended Plan 14_02_22.pdf31 Mar 2022
Building Plan Approval (IOD)File: Final Amended Plan 14_02_22.pdf31 Mar 2022
Declaration about Commencement CertificateFile: C C TILL 39TH FLOOR DT 17_11_2021.pdf10 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance FY 20_21.pdf10 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: VR FORM 5 F Y 20_21.pdf15 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VR FORM 2 F Y 20_21.pdf22 Dec 2021
Certificates of CA (Form 3)File: VR FORM 3 F Y 20_21.pdf22 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: FURTHER C C TILL 39TH FLOOR DT 17_11_2021.pdf19 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf21 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf21 Jul 2021
Disclosure of sold/ booked inventoryFile: Discolsure of Sold Or Booked Inventor of VRAJ REALTORS.pdf25 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC upto 36th floor_ dated_05_04_2021 (1).pdf12 Apr 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE CERTIFICATE_march_21_ qtr.pdf12 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VR FORM 2 _19_20.pdf5 Mar 2021
Certificates of CA (Form 3)File: VR FORM 3 _19_20.pdf5 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VR FORM 5_ 19-20.pdf5 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: CC UPTO 29TH FLOOR_DT 23_12_2020_1.pdf25 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: work progress certificate_22_06_20.pdf24 Jun 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Work Completion upto 20th Slab.pdf2 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: work completion upto 18th Slab.pdf23 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: CC up to 20th floor.pdf16 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Work Completion up to 14th Slab.pdf4 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: VRAJ REALTORS FORM 5_31_03_19.pdf4 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VRAJ REALTORS FORM 2_31_03_19.pdf30 Sep 2019
Certificates of CA (Form 3)File: VRAJ REALTORS FORM 3_31_03_19.pdf30 Sep 2019
Certificates of CA (Form 5)File: VRAJ REALTORS FORM 5_31_03_19.pdf30 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Work Completion up to 8th podium.pdf20 Aug 2019
OtherFile: MAHARERA_professionals details.pdf20 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: CC_upto 15th Floor.pdf3 May 2019
Building plan approvalFile: IOA_VRAJ REALTORS_2019.pdf29 Mar 2019
Building plan approvalFile: Sheet No 2.pdf29 Mar 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VRAJ LAL AANGANKANDIVALI WEST64CompletedMar 2016Late, Jun 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 12 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRAJ TIARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Worli780+ in Mumbai City

2 kmVRAJ TIARACompleted 27Lapsed / revoked 29Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 94 registered projects within 2 km.

Builder: VRAJ REALTORS

VRAJ REALTORS has 1 registration on MahaRERA, including VRAJ TIARA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if VRAJ TIARA is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRAJ TIARA?

The registered promoter entity is VRAJ REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRAJ TIARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRAJ TIARA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRAJ TIARA?

The professionals named in the filing: Architect: MR AMEET PAWAR; Engineer: J W CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRAJ TIARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRAJ TIARA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRAJ TIARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.