ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / VRAJ METROPOLIS SOUTH

Registered No litigation declared Others project

VRAJ METROPOLIS SOUTH

By SHREE INFRA SPACE

RG-MH-34656 · RERA P51600048726 · Last updated on MahaRERA portal: 16 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2032Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Internal walls, 90%
109 of 179Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

VRAJ METROPOLIS SOUTH is a Others project by SHREE INFRA SPACE in Nashik, Maharashtra, registered with MahaRERA as P51600048726 on 17 Jan 2023. Possession is promised by 31 Dec 2032. 70 of the 179 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameVRAJ METROPOLIS SOUTH
  • TypeOthers
  • Location
    • NEAR TRACTOR HOUSE
    • OPPOSITE DWARKA MSEB OFFICE
    • TAKLI ROAD
    • DWARKA
    • Nashik (M Corp.)
    • Nashik
    • 422011
  • Pincode422011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600048726
  • ReraGenie IDRG-MH-34656

Builder

  • NameSHREE INFRA SPACE
  • Entity typePartnership
  • GSTIN27AEAFS9458Q1Z1
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersVARSHA MANOJ LADANI, MANOJKUMAR JAMNADAS LADANI
  • Other registrations3 more →

Key dates

this monthRegisteredJan 2023PromisedDec 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2023
  • Promised completion31 Dec 2032
  • Revised completionNone
  • Buildings1 building record
  • Documents filed134 files

Current status

39%70 of 179 units booked
93.5%Work done, per cost certificate

Figures as on 16 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VRAJ METROPOLIS SOUTHNA121211960179

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

VRAJ METROPOLIS SOUTH: 84% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed121

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots121
Closed/Covered1
Open Space120

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,264 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI17433.01
Proposed, not sanctioned17,433 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGaikwad Corner, Near Indira Nagar Tunnel, Suchita Nagar, Nashik - 422009
Estimated costRs 35.40 cr
Cost incurredRs 33.08 cr
Work done93.45%
BuildingWingEstimatedIncurred
VRAJ METROPOLIS SOUTHNARs 34.40 crRs 32.68 cr
-NARs 1.00 crRs 40.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Sumit Kumath and Associates
EngineerSagar Shah
Chartered AccountantAnil K Dahiya
Chartered AccountantNirav Shailesh Shah & Co.
PartnerRole in project
SHREE INFRA SPACE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2032

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 25-26 Q4.pdf16 Jun 2026
Withdrawal Update Form 2File: Form 2 25-26 Q4.pdf16 Jun 2026
Withdrawal Update Form 3File: Form 3 SD 25-26 Q4.pdf16 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf6 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf6 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf6 Apr 2026
Form 1File: Form 1 25-26 Q3.pdf26 Mar 2026
Form 2File: Form 2 25-26 Q3.pdf26 Mar 2026
Form 3File: Form 3 SD 25-26 Q3.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: Inventory 31-12-2025.pdf26 Mar 2026
Form 5 (FY 2024-2025)File: Form-5 Shree Infra Spce-Vraj Metrol.pdf1 Dec 2025
Form 1File: Form 1 South 25-26 Q2.pdf28 Nov 2025
Form 2File: Form 2 South 25-26 Q2.pdf28 Nov 2025
Form 3File: Form 3 SD South 25-26 Q2.pdf28 Nov 2025
Disclosure of Sold and Booked InventoryFile: Inventory South 30-09-2025.pdf28 Nov 2025
Form 1File: Form 1.pdf3 Oct 2025
Form 2File: Form 2.pdf3 Oct 2025
Form 3File: Form 3 - Self Certification.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf3 Oct 2025
Form 1File: Form 1 Q3.pdf3 Oct 2025
Form 2File: Form 2 Q3.pdf3 Oct 2025
Form 3File: Form 3 SD Q3.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory Q3.pdf3 Oct 2025
Form 1File: Form 1 Q4.pdf3 Oct 2025
Form 2File: Form 2 Q4.pdf3 Oct 2025
Form 3File: Form 3.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory Q4.pdf3 Oct 2025
Form 1File: Form 1 FY 24 25 Q3.pdf3 Oct 2025
Form 2File: Form 2 FY 24 25 Q3.pdf3 Oct 2025
Form 3File: SC FY 24 25 Q3.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory 31122024.pdf3 Oct 2025
Form 1File: Form 1 24-25 Q4.pdf3 Oct 2025
Form 2File: Form 2 24-25 Q4.pdf3 Oct 2025
Form 3File: Form 3 SD 24-25 Q4.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory 31-03-2025.pdf3 Oct 2025
Form 1File: Form 1 25-26 Q1.pdf3 Oct 2025
Form 2File: Form 2 25-26 Q1.pdf3 Oct 2025
Form 3File: Form 3 SD 25-26 Q1.pdf3 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory 30-06-2025.pdf3 Oct 2025
Form 5 (FY 2022-2023)File: Form 5 - 2022-23.pdf3 Oct 2025
Form 5 (FY 2023-2024)File: Form 5 - 2023-24.pdf3 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24 25 Q1.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24 25 Q2.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24 25 Q3.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24 25 Q1.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24 25 Q2.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24 25 Q3.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 24 25 Q1.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 24 25 Q2.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 24 25 Q3.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: Inventory 31122024.pdf22 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf3 Dec 2024
Other - TechnicalFile: Application For Correction.pdf25 Jun 2024
Building plan approvalFile: SP 1.pdf12 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 1.pdf12 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Appendix F.pdf12 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Jun 2024
Other - TechnicalFile: Application For Correction.pdf12 Jun 2024
Other - TechnicalFile: Clarification - Extension of Completion Date.pdf12 Jun 2024
Declaration in FORM BFile: Form B.pdf4 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf4 Jun 2024
Building plan approvalFile: SP 1.pdf27 May 2024
Building plan approvalFile: SP 2.pdf27 May 2024
Building plan approvalFile: SP 3.pdf27 May 2024
Building plan approvalFile: SP 4.pdf27 May 2024
Building plan approvalFile: SP 5.pdf27 May 2024
Building plan approvalFile: SP 6.pdf27 May 2024
Building plan approvalFile: SP 7.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 1.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 2.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 3.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 4.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 5.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 6.pdf27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SP 7.pdf27 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf27 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf27 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2024.pdf27 May 2024

How this compares with Nashik

39%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRAJ METROPOLIS SOUTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DWARKA4,100+ in Nashik

2 kmVRAJ METROPOLIS SOUTHCompleted 134Lapsed / revoked 29Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 245 registered projects within 2 km.

Builder: SHREE INFRA SPACE

SHREE INFRA SPACE has 4 registrations on MahaRERA, including VRAJ LANDMARK 1A and VRAJ LANDMARK 1B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if VRAJ METROPOLIS SOUTH is delayed beyond 31 Dec 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRAJ METROPOLIS SOUTH?

The registered promoter entity is SHREE INFRA SPACE, a partnership as per the filing. Its GSTIN 27AEAFS9458Q1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRAJ METROPOLIS SOUTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRAJ METROPOLIS SOUTH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRAJ METROPOLIS SOUTH?

The professionals named in the filing: Architect: Ar. Sumit Kumath and Associates; Engineer: Sagar Shah; Chartered Accountant: Anil K Dahiya; Chartered Accountant: Nirav Shailesh Shah & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRAJ METROPOLIS SOUTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRAJ METROPOLIS SOUTH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRAJ METROPOLIS SOUTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.