Home / Browse projects / Pune, Maharashtra / VNSVL Shubh Nirvana Phase IV

Registered No litigation declared Others project

VNSVL Shubh Nirvana Phase IV

By Viman Nagar Shubh Ventures LLP

RG-MH-96437 · RERA P52100055359 · Last updated on MahaRERA portal: 26 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 4 months from the original
12 of 21Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
117 of 136Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

VNSVL Shubh Nirvana Phase IV is a Others project by Viman Nagar Shubh Ventures LLP in Pune, Maharashtra, registered with MahaRERA as P52100055359 on 22 Mar 2024. Possession is promised by 30 Oct 2027. The completion date has moved by 4 months from the original filing. 19 of the 136 units on this registration are recorded sold or booked, and 12 of 21 construction stages are filed complete.

At a glance

Project

  • NameVNSVL Shubh Nirvana Phase IV
  • TypeOthers
  • Location
    • Viman Nagar
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055359
  • ReraGenie IDRG-MH-96437

Builder

  • NameViman Nagar Shubh Ventures LLP
  • Entity typePartnership
  • PartnersVishal Sumerchand Agarwal, Suraj Sumerchand Agarwal, Rameshchand Sitaram Agarwal, Sagar Rameshchand Agarwal, Kailash Ramkumar Agarwal, Jagmohan Satyanarayan Mittal, Anand Hariram Bansal, Anuj Balkrishan Agarwal, Rajesh Satyanarayan Mittal, Anshul Anand Bansal
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2024First promiseJun 2027Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Mar 2024
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2027)
  • Buildings2 building records
  • Documents filed119 files

Current status

14%19 of 136 units booked
84.9%Work done, per cost certificate

Figures as on 26 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing JNA1411581068
Wing INA141160868

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 26 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 21 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

Wing J72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Wing I69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 26 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYesNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYesNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYesNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed450

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots450
Closed/Covered450
BuildingClosed/CoveredTotal
Wing J228228
Wing I222222

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,420 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Aug 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI26228.0
Proposed, not sanctioned26,228 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch9/2 KALPATARU GARDENS BOAT CLUB ROAD PUNE - 411001
Estimated costRs 70.00 cr
Cost incurredRs 59.45 cr
Work done84.93%
BuildingWingEstimatedIncurred
Wing JNARs 28.00 crRs 23.78 cr
Wing INARs 28.00 crRs 23.78 cr
-NARs 14.00 crRs 11.89 cr

Certifying professionals and partners13

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCubix Architects Associates
EngineerSuhas Baban Patil
EngineerSangram Yadav
EngineerPlanedge Consultants Pvt Ltd
Chartered AccountantA S A K & Co ANUJ Agrawal
Chartered AccountantRAHUL SARAWGI
Chartered AccountantA S A K & Co
Chartered AccountantAgarwal & Co
Chartered AccountantPatel and Sharma Chartered Accountants
Chartered AccountantAgarwal Sarawgi & Company
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates
PartnerRole in project
Viman Nagar Shubh Ventures LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100055359/WarJun 2027 → Oct 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Phase IV NIRVANA - FORM 2A-FY 25-26.pdf26 Sep 2026
Form 5 (FY 2025-2026)File: Phase IV NIRVANA - FORM 5 FY 2025-26.pdf16 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf27 Aug 2026
Layout approvalFile: 01-45 Layout- Highlighted- 11Zon.pdf23 May 2026
Layout approvalFile: 02-45 Parking Layout_11zon.pdf23 May 2026
Building plan approvalFile: 24-45 Wing I_11zon.pdf23 May 2026
Building plan approvalFile: 26-45 Wing I 2_11zon.pdf23 May 2026
Building plan approvalFile: 27-45 WIng I 3.pdf23 May 2026
Building plan approvalFile: 28-45 WIng I Sec Elevation.pdf23 May 2026
Building plan approvalFile: 29-45 Wing I Elevation.pdf23 May 2026
Building plan approvalFile: 30-45 Wing J.pdf23 May 2026
Building plan approvalFile: 31-45 Wing J 1.pdf23 May 2026
Building plan approvalFile: 32-45 Wing J 2.pdf23 May 2026
Building plan approvalFile: 33-45 Wing J 3.pdf23 May 2026
Building plan approvalFile: 34-45 Wing J Sec.pdf23 May 2026
Building plan approvalFile: 35-45 Wing J Elecation.pdf23 May 2026
Withdrawal Update Form 1File: Form 1 Phase IV Mar 26.pdf22 May 2026
Withdrawal Update Form 2File: Form 2 Nirvana Phase II March 26 Copy.pdf22 May 2026
Withdrawal Update Form 3File: Form 3 Phase IV Mar 26.pdf22 May 2026
Withdrawal Update Form 1File: Form1 Phase IV Dec 25.pdf16 May 2026
Withdrawal Update Form 2File: Form2 Phase IV Dec 25.pdf16 May 2026
Withdrawal Update Form 3File: Form3 Phase IV Dec 25.pdf16 May 2026
Form 1File: Form 1 Phase 4 Dec 24.pdf12 Feb 2026
Form 2File: Form 2 Phase 4 Dec 24.pdf12 Feb 2026
Form 3File: Form 3 Phase 4 Dec 24.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Phase 4 Dec 24.pdf12 Feb 2026
Form 1File: Form 1 Phase 4 Sept 24.pdf12 Feb 2026
Form 2File: Form 2 Phase 4 Sept 24.pdf12 Feb 2026
Form 3File: Form 3 Phase 4 Sept 24.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Phase 4 Sept 24.pdf12 Feb 2026
Form 1File: Form 1 Phase 4 Jun 24.pdf12 Feb 2026
Form 2File: Form 2 Phase 4 Jun 24.pdf12 Feb 2026
Form 3File: Form 3 Phase 4 Jun 24.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Phase 4 Jun 24.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf5 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf5 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf4 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf4 Dec 2025
Form 2A (FY 2024-2025)File: FORM 2A- PHASE IV FY 24-25.pdf15 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 - PHASE IV FY 24-25.pdf13 Oct 2025
Form 1File: Form 1 Phase 4 Mar.pdf17 Sep 2025
Form 2File: FORM 2.pdf17 Sep 2025
Form 3File: Form 3.pdf17 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf17 Sep 2025
Form 1File: Form 1 Mar 24 Phase 4.pdf18 Aug 2025
Form 2File: Form 2 Mar 24 Phase 4.pdf18 Aug 2025
Form 3File: Form 3 Mar 24 Phase 4.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOld Unsold Mar 24 phase 4.pdf18 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fomr-3 ph 4 dec 24_0001-signed.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ph 4 june 24_0001.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ph 4 sept 24_0001.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ph 4 dec 24_0001.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan_0001signed_compressed.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Shubh Nirvana Ph 4_30jun.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Shubh Nirvana Ph 4_30jun.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VNSVL - Shubh Nirvana Phase 4.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VNSVL - Shubh Nirvana Phase 4.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTI PHASE IV - 31-03-24_organized.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTI PHASE IV - 31-03-2024.pdf4 Jun 2024
Disclosure of sold/ booked inventoryFile: I wing_Sold Unsold.pdf4 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - PHASE IV (31-03-2024).pdf4 Jun 2024
Declaration about Commencement CertificateFile: CC - Declaration Shubh.pdf21 Mar 2024
CERSAI detailsFile: Decleration Cersai Phase IV.pdf9 Mar 2024
Other - FinanceFile: Decleration Cersai Phase IV.pdf9 Mar 2024
Other - TechnicalFile: SS for Order 45.pdf8 Mar 2024
Other - TechnicalFile: ANNEXURE'A'.pdf12 Feb 2024
Layout approvalFile: scan 1 - Layout (Highlight).pdf10 Feb 2024
Building plan approvalFile: scan 2 - Basement Floor Plan (All Building)_4_11zon.pdf10 Feb 2024
Building plan approvalFile: scan 24 - Wing I Floor Plan_3_11zon.pdf10 Feb 2024
Building plan approvalFile: scan 25 - Wing I Floor Plan_1_11zon.pdf10 Feb 2024
Building plan approvalFile: scan 26 - Wing I Floor Plan_2_11zon.pdf10 Feb 2024
Building plan approvalFile: scan 27 - Wing I Floor Plan.pdf10 Feb 2024
Building plan approvalFile: scan 28 - Wing I Elevation.pdf10 Feb 2024
Building plan approvalFile: scan 29 - Wing I Elevation.pdf10 Feb 2024
Copy of the legal title reportFile: Legal Title Report.pdf10 Feb 2024
Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf10 Feb 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VNSVL Shubh Nirvana Phase IIIP52100055241Viman Nagar, Pune132Mar 2024OngoingDec 2026Not due yet
VNSVL Shubh Nirvana - Phase IIP52100050937Viman Nagar, Pune114May 2023OngoingJun 2026Not delivered
VNSVL Shubh Nirvana Phase 1P52100031263Viman Nagar, Pune158Oct 2021OngoingDec 2025Not delivered

How this compares with Pune

14%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VNSVL Shubh Nirvana Phase IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Viman Nagar13,700+ in Pune

2 kmVNSVL Shubh Nirvana PhasCompleted 14Lapsed / revoked 11Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: Viman Nagar Shubh Ventures LLP

Viman Nagar Shubh Ventures LLP has 6 registrations on MahaRERA, including VNSVL Shubh Infinity and VNSVL Shubh Nirvana Phase 1. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VNSVL Shubh Nirvana Phase IV is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VNSVL Shubh Nirvana Phase IV?

The registered promoter entity is Viman Nagar Shubh Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VNSVL Shubh Nirvana Phase IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VNSVL Shubh Nirvana Phase IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VNSVL Shubh Nirvana Phase IV?

The professionals named in the filing: Architect: Cubix Architects Associates; Engineer: Suhas Baban Patil; Engineer: Sangram Yadav; Engineer: Planedge Consultants Pvt Ltd; Chartered Accountant: A S A K & Co ANUJ Agrawal; Chartered Accountant: RAHUL SARAWGI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VNSVL Shubh Nirvana Phase IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VNSVL Shubh Nirvana Phase IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VNSVL Shubh Nirvana Phase IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.