Home / Browse projects / Pune, Maharashtra / VNSVL Shubh Nirvana - Phase II

Registration lapsed No litigation declared Residential / Group Housing project

VNSVL Shubh Nirvana - Phase II

By Viman Nagar Shubh Ventures LLP

RG-MH-99201 · RERA P52100050937 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Rs 60.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
21 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
2 of 114Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 141 documents Report an error

VNSVL Shubh Nirvana - Phase II is a Residential / Group Housing project by Viman Nagar Shubh Ventures LLP in Pune, Maharashtra, registered with MahaRERA as P52100050937 on 15 May 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 112 of the 114 units on this registration are recorded sold or booked, and 21 of 22 construction stages are filed complete.

At a glance

Project

  • NameVNSVL Shubh Nirvana - Phase II
  • TypeResidential / Group Housing
  • Location
    • Viman Nagar
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050937
  • ReraGenie IDRG-MH-99201

Builder

  • NameViman Nagar Shubh Ventures LLP
  • Entity typePartnership
  • PartnersVishal Sumerchand Agarwal, Suraj Sumerchand Agarwal, Rameshchand Sitaram Agarwal, Sagar Rameshchand Agarwal, Kailash Ramkumar Agarwal, Jagmohan Satyanarayan Mittal, Anand Hariram Bansal, Anuj Balkrishan Agarwal, Rajesh Satyanarayan Mittal, Anshul Anand Bansal
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

4 months past promisethis monthRegisteredMay 2023PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 May 2023
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed141 files

Current status

98%112 of 114 units booked
70.5%Work done, per cost certificate

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing DNA131055055
Wing GNA141159059

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

Wing D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing G91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes80%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed72

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots72
Closed/Covered72
BuildingClosed/CoveredTotal
Wing D2020
Wing G5252

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,931 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 60.00 crore
CERSAI search filedYes
Declared on25 Mar 2026

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI17557.99
Proposed, not sanctioned14,692 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch9/2, Kalpataru Gardens, Boat Club Road, Pune
Estimated costRs 91.65 cr
Cost incurredRs 64.57 cr
Work done70.45%
BuildingWingEstimatedIncurred
Wing GNARs 30.55 crRs 21.52 cr
-NARs 30.55 crRs 21.52 cr
Wing DNARs 30.55 crRs 21.52 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCubix Architects Associates
EngineerPlanedge Consultants Pvt Ltd
EngineerSangram Yadav
EngineerSuhas Baban Patil
Chartered AccountantAgarwal & Co
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates
Chartered AccountantPatel and Sharma Chartered Accountants
Chartered AccountantDipali Shelar & Company
PartnerRole in project
Viman Nagar Shubh Ventures LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed141

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Fy 25-226 Signed.pdf14 Jul 2026
Form 5 (FY 2025-2026)File: Form 5 FY 2025-26 Nirvana Phase II.pdf8 Jul 2026
Form 2A (FY 2023-2024)File: Form 2A.pdf2 Jul 2026
Form 5 (FY 2023-2024)File: Form 5.pdf2 Jul 2026
Form 1File: Form 1 Phase 2 Jun 24.pdf16 May 2026
Form 2File: Form 2 Nirvana Phase II Jun 24.pdf16 May 2026
Form 3File: Form 3 Nirvana Phase II Jun 24.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Nirvana phase 2 jun 24.pdf16 May 2026
Form 1File: Form 1 Phase 2 Sept 24.pdf16 May 2026
Form 2File: Form 2 Phase 2 Sept 24.pdf16 May 2026
Form 3File: Form-3 Shubh Nirvana Phase II- Sept 24_removed.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Phase 2 Sept 24.pdf16 May 2026
Form 1File: Form 1 Nirvana Phase 2 Dec 24.pdf16 May 2026
Form 2File: Form 2 Nirvana Phase II Dec 24.pdf16 May 2026
Form 3File: Form 3 Nirvana Phase II Dec 24.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Phase 2 Dec 24.pdf16 May 2026
Withdrawal Update Form 1File: FORM 1 PHASE II MAR 26.pdf16 May 2026
Withdrawal Update Form 2File: FORM 2 PHASE II MAR 26.pdf16 May 2026
Withdrawal Update Form 3File: Form 3 PHASE II (2) Mar 26.pdf16 May 2026
Withdrawal Update Form 1File: Form1 Phase II Dec 25.pdf9 Feb 2026
Withdrawal Update Form 2File: Form2 Phase II Dec 25.pdf9 Feb 2026
Withdrawal Update Form 3File: Form3 Phase II Dec 25.pdf9 Feb 2026
Form 1File: 00 Architect Certificate - 30062023 Rearrange.pdf23 Dec 2025
Form 2File: 00 Engg Certi 30062023.pdf23 Dec 2025
Form 3File: 00 CA Certificate - 30062023.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: 00 SOLD_BOOKED INVENTORY - 30062023.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: 01 SOLD_BOOKED INVENTORY - 30092023.pdf23 Dec 2025
Form 1File: 01 Architect Certificate - 30092023 Rearrange.pdf23 Dec 2025
Form 2File: 01 Engg Certi 30092023.pdf23 Dec 2025
Form 3File: 01 CA Certificate - 30092023.pdf23 Dec 2025
Form 3File: 02 CA Certificate - 31122023.pdf23 Dec 2025
Form 1File: 02 Architect Certificate - 31122023 Rearrange.pdf23 Dec 2025
Form 2File: 02 Engg Certi 31122023.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: 03 SOLD_BOOKED INVENTORY - 31122023.pdf23 Dec 2025
Form 1File: 03 Architect Certificate - 31032024 Rearrange.pdf23 Dec 2025
Form 2File: 02 Engg Certi 31032024.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD_BOOKED INVENTORY - 31032024.pdf23 Dec 2025
Form 3File: Form 3 Signed.pdf23 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf5 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf5 Dec 2025
Withdrawal Update Form 1File: Form1.pdf22 Nov 2025
Withdrawal Update Form 2File: ENGINEERu0027S CERTIFICATE PHASE II.pdf22 Nov 2025
Withdrawal Update Form 3File: CA CERTIFICATE PHASE II.pdf22 Nov 2025
Form 2A (FY 2024-2025)File: FORM 2A- PHASE II FY 24-25.pdf15 Nov 2025
Form 5 (FY 2024-2025)File: FORM5 - PHASE II FY 24-25.pdf15 Nov 2025
Form 1File: Form 1.pdf26 Sep 2025
Form 2File: FORM 2.pdf26 Sep 2025
Form 3File: FORM 3.pdf26 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold phase II.pdf26 Sep 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph 2 June 24_0001.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph 2 sept 24_0001.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph 2 dec 24_0001.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Shubh Nirvana phase 2 compressed.pdf13 Feb 2025
Details of encumbrances concerned to FinanceFile: Financial Encumbrance Phase 2.pdf12 Dec 2024
Details of encumbrances concerned to LegalFile: Financial Encumbrance Phase 2.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VNSVL - Shubh Nirvana Phase 2.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Shubh Nirvana phase 2_30jun.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Shubh Nirvana phase 2_30jun.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VNSVL - Shubh Nirvana Phase 2.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VNSVL - Shubh Nirvana Phase 2.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VNSVL - Shubh Nirvana Phase 2.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shubh Nirvana Ph 2 Mar 24_compressed.pdf27 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 00 Architect Certificate - 30062023 Rearrange.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 Architect Certificate - 30092023 Rearrange.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 02 Architect Certificate - 31122023 Rearrange.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 03 Architect Certificate - 31032024 Rearrange.pdf16 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 00 Engg Certi 30062023.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 01 Engg Certi 30092023.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Engg Certi 31122023.pdf15 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Engg Certi 31032024.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: 00 SOLD_BOOKED INVENTORY - 30062023.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: 01 SOLD_BOOKED INVENTORY - 30092023.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: 03 SOLD_BOOKED INVENTORY - 31122023.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: SOLD_BOOKED INVENTORY - 31032024.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 00 CA Certificate - 30062023.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 01 CA Certificate - 30092023.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 02 CA Certificate - 31122023.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf15 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Nirvana Phase II-Declaration for separate bank account.pdf19 Dec 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VNSVL Shubh Nirvana Phase IVP52100055359Viman Nagar, Pune136Mar 2024OngoingJun 2027Not due yet
VNSVL Shubh Nirvana Phase IIIP52100055241Viman Nagar, Pune132Mar 2024OngoingDec 2026Not due yet
VNSVL Shubh Nirvana Phase 1P52100031263Viman Nagar, Pune158Oct 2021OngoingDec 2025Not delivered

How this compares with Pune

98%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VNSVL Shubh Nirvana - Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Viman Nagar13,700+ in Pune

2 kmVNSVL Shubh Nirvana - PhCompleted 14Lapsed / revoked 10Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: Viman Nagar Shubh Ventures LLP

Viman Nagar Shubh Ventures LLP has 6 registrations on MahaRERA, including VNSVL Shubh Infinity and VNSVL Shubh Nirvana Phase 1. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that VNSVL Shubh Nirvana - Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VNSVL Shubh Nirvana - Phase II is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VNSVL Shubh Nirvana - Phase II?

The registered promoter entity is Viman Nagar Shubh Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VNSVL Shubh Nirvana - Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VNSVL Shubh Nirvana - Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VNSVL Shubh Nirvana - Phase II?

The professionals named in the filing: Architect: Cubix Architects Associates; Engineer: Planedge Consultants Pvt Ltd; Engineer: Sangram Yadav; Engineer: Suhas Baban Patil; Chartered Accountant: Agarwal & Co; Chartered Accountant: Patel & Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VNSVL Shubh Nirvana - Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VNSVL Shubh Nirvana - Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VNSVL Shubh Nirvana - Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.