Home / Browse projects / Mumbai City, Maharashtra / VISION CREST

Registered Litigation declared Residential / Group Housing project

VISION CREST

By West Avenue Realtors Private Limited

RG-MH-07307 · RERA P51900077183 · Last updated on MahaRERA portal: 4 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
8 of 11Construction stages donefurthest along: Internal walls, 95%
38 of 46Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

VISION CREST is a Residential / Group Housing project by West Avenue Realtors Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900077183 on 29 Jul 2024. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 8 of the 46 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVISION CREST
  • TypeResidential / Group Housing
  • Location
    • D. S. Babrekar Marg
    • Dadar
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900077183
  • ReraGenie IDRG-MH-07307

Builder

  • NameWest Avenue Realtors Private Limited
  • Entity typeCompany
  • DirectorSharad Ramchandra Jadhav
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2024First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2024
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed90 files

Current status

17%8 of 46 units booked
62.8%Work done, per cost certificate

Figures as on 4 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VISION CRESTNA362946046

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

VISION CREST: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 4 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,050 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Dec 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2128.88
Proposed, not sanctioned2,129 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch81, Dev Kunj, Veer Savarkar Marg, Shivaji Park, Dadar, Mumbai 400028
Estimated costRs 13.59 cr
Cost incurredRs 8.54 cr
Work done62.82%
BuildingWingEstimatedIncurred
VISION CRESTNARs 12.09 crRs 7.64 cr
-NARs 1.50 crRs 90.00 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS AVCHAT & ASSOCIATES
EngineerVijay VItthalrao Kulkarni
EngineerSihavat Consultancy Services
EngineerAjit Deshpande
EngineerHemant Pingulkar
Chartered AccountantD P J & Co
Chartered AccountantSVH & Associates
Chartered AccountantHiren Vora
PartnerRole in project
West Avenue Realtors Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27012619591Dec 2025 → Dec 2027

Reason as filed by the promoter1) The said real estate project was originally completed in 2011 with provision made in the structure of the building to accommodate additional FSI of 0.5 subject to revision of CRZ norms. The said extra FSI of 0.5 became available to Promoter after revised CRZ notification was issued by Government of India 2) The Promoter had registered the project with MahaRERA after getting all the approvals from Municipal Corporation of Greater Mumbai and after the order dated 01.11.2023 passed by Hon'ble Bombay High Court in Writ Petition (L) No. 28997 of 2021, wherein Promoter was granted permission to c

Litigation declared1

CaseCourtStatus
PILL/45/2019/2019Bombay High CourtOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503341West Avenue Realtors Private LimitedShailesh Gopal Mhaske and Kimaya Shailesh Mhaske alias Kimaya Gajanan Pol18/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Vision Crest Form-1 Jun 26.pdf4 Sep 2026
Withdrawal Update Form 1File: Vision Crest Form-1 Mar 26.pdf4 Sep 2026
Withdrawal Update Form 2File: Vision Crest Form-2 Jun 26.pdf4 Sep 2026
Withdrawal Update Form 2File: Vision Crest Form-2 Mar 26.pdf4 Sep 2026
Withdrawal Update Form 3File: Vision Crest Form-3 Jun 26.pdf4 Sep 2026
Withdrawal Update Form 3File: Vision Crest Form-3 Mar 26.pdf4 Sep 2026
Withdrawal Update Form 1File: Form 1 Vision Crest_June 2025.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Vision Crest Dec25 Signed.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 Vision Crest Dec25 Signed.pdf27 Jan 2026
Withdrawal Update Form 1File: Form 1 Vision Crest_June 2025.pdf10 Jan 2026
Withdrawal Update Form 1File: Form 1 Vision Crest_June 2025.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2 Vision Crest_June 2025.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2 Vision Crest_June 2025.pdf10 Jan 2026
Withdrawal Update Form 3File: Vision Crest Form-3 June 2025.pdf10 Jan 2026
Withdrawal Update Form 3File: Vision Crest Form-3 June 2025.pdf10 Jan 2026
Form 1File: VC ARch Form1 Sept24.pdf31 Dec 2025
Form 2File: VC Engr Form 2 Sept24.pdf31 Dec 2025
Form 3File: VC CA Form 3 Sept24.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: VC sold Booked Unsold Inventory Sept24.pdf31 Dec 2025
Form 1File: VC Arch Form 1 202412.pdf31 Dec 2025
Form 2File: VC Engr Form 2 202412.pdf31 Dec 2025
Form 3File: VC CA Form 3 202412.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: VC_Sold Booked Unsold Inventory Dec24.pdf31 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Vision Crest Mar25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Vision Crest Mar25.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vision Crest Mar25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: VC Sold-Unsold Inv Dec24.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Vision CrestDec2024.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Vision CrestDec2024.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vision CrestDec2024.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Vision CrestDec2024.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Vision CrestDec2024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vision CrestDec2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: VCsoldBookedUnsold InventorySept24.pdf7 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Vision CrestSept24.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Vision CrestSept24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vision CrestSept24.pdf24 Dec 2024
Other - LegalFile: 19D_Legal Representation.pdf22 Jul 2024
Other - TechnicalFile: 19A_Technical_Sale Society Consent.pdf24 May 2024
Other - TechnicalFile: 19A_Technical_Rehab Society consent.pdf24 May 2024
Other - TechnicalFile: 1 Other - Technical.pdf24 May 2024
Other - TechnicalFile: 19_Technical.pdf24 May 2024
Other - TechnicalFile: 19C_Legal_Ann-C.pdf24 May 2024
Other - TechnicalFile: Vision Crest-PR Card.pdf24 May 2024
Other - LegalFile: 19C_Legal_Ann-C.pdf11 May 2024
Other - LegalFile: Vision Crest-DA-Tripartite Agreement.PDF11 May 2024
Other - LegalFile: Vision Crest-POA.PDF11 May 2024
Other - LegalFile: Vision Crest-PR Card.pdf11 May 2024
Proforma of Agreement for saleFile: 13_AfS_New.pdf10 May 2024
Deviation Report with respect to model copy of AgreementFile: 13A_AfS Deviation_new.pdf10 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 18_Bank Declaration_new.pdf6 May 2024
Other - LegalFile: 19A_Technical_Rehab Society consent.pdf6 May 2024
Other - LegalFile: 19A_Technical_Sale Society Consent.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11_CA_Revised.pdf25 Apr 2024
Building plan approvalFile: IoD Plans_Part1.pdf24 Apr 2024
Building plan approvalFile: IoD Plans_Part2.pdf24 Apr 2024
Building plan approvalFile: IoD Plans_Part3.pdf24 Apr 2024
Building plan approvalFile: IoD Plans_Part4.pdf24 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part1.pdf24 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part2.pdf24 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part3.pdf24 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part4.pdf24 Apr 2024
Other - LegalFile: 19_Legal_Declaration.pdf24 Apr 2024
CERSAI detailsFile: VC-CERSAI Undertaking Report.pdf5 Apr 2024
Proforma of Allotment letterFile: Allotment Letter.pdf5 Apr 2024
Deviation Report with respect to Allotment letterFile: VC-Deviation Report for Allotment Letter.pdf5 Apr 2024
Layout approvalFile: 07-1 Copy of Layout Approval.pdf7 Mar 2024
Building plan approvalFile: 4_Layout.pdf7 Mar 2024
Building plan approvalFile: IoD Plans_Part2.pdf7 Mar 2024
Building plan approvalFile: IoD Plans_Part3.pdf7 Mar 2024
Building plan approvalFile: IoD Plans_Part4.pdf7 Mar 2024
Copy of Layout Approval (in case of layout)File: 07-1 Copy of Layout Approval.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 4_Layout.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part2.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part3.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: IoD Plans_Part4.pdf7 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: 09-1 Commencement Certificates.pdf7 Mar 2024
Other - TechnicalFile: 19_REg Declaration.pdf7 Mar 2024
PAN CardFile: 01-West Avenue-Pan Card.pdf16 Dec 2023
Copy of the legal title reportFile: 02-1 Copy of the legal title report.pdf16 Dec 2023

How this compares with Mumbai City

17%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 24 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VISION CREST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dadar780+ in Mumbai City

2 kmVISION CRESTCompleted 59Lapsed / revoked 53Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: West Avenue Realtors Private Limited

West Avenue Realtors Private Limited has 2 registrations on MahaRERA, including Deluxe Apartments and VISION CREST. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if VISION CREST is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISION CREST?

The registered promoter entity is West Avenue Realtors Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISION CREST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VISION CREST?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VISION CREST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISION CREST?

The professionals named in the filing: Architect: VILAS AVCHAT & ASSOCIATES; Engineer: Vijay VItthalrao Kulkarni; Engineer: Sihavat Consultancy Services; Engineer: Ajit Deshpande; Engineer: Hemant Pingulkar; Chartered Accountant: D P J & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISION CREST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISION CREST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISION CREST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.