Home / Browse projects / Mumbai City, Maharashtra / Eon One

Registration lapsed No litigation declared Residential / Group Housing project

Eon One

By Firstlight Properties Private Limited

RG-MH-25686 · RERA P51900011726 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
87 of 149Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 233 documents Report an error

Eon One is a Residential / Group Housing project by Firstlight Properties Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900011726 on 31 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 30 months from the original filing. 62 of the 149 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameEon One
  • TypeResidential / Group Housing
  • Location
    • S K Bole Road
    • Near Siddhivinayak Temple
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900011726
  • ReraGenie IDRG-MH-25686

Builder

  • NameFirstlight Properties Private Limited
  • Entity typeCompany
  • Managing DirectorBharat Shah

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed233 files

Current status

42%62 of 149 units booked
97.1%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Eon OneNA44361418149

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Eon One: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed169

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots169
Closed/Covered169

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,044 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI10662.81
Proposed, not sanctioned9,942 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch101 -104 Tulsiani Chambers Free Press Journal Marg Nariman Point Mumbai 400021
Estimated costRs 124.25 cr
Cost incurredRs 120.63 cr
Work done97.08%
BuildingWingEstimatedIncurred
Eon OneNARs 118.04 crRs 118.04 cr
-NARs 6.21 crRs 2.59 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPlanet E Consultants
EngineerSK Consultants & Engineers
EngineerMS CONSULTANTS AND ENGINEERS
Chartered AccountantNB Sayed & Associates
Chartered AccountantVinod Patil & Associates
PartnerRole in project
Firstlight Properties Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900010884Dec 2023 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 58.33% allottees for purpose of extension of RERA registration period of the said project.

EA03122518521Dec 2023 → Jun 2026

Reason as filed by the promoterWe would like to request an extension for the project completion timeline. The recent increase in the Floor Space Index (FSI) has expanded the overall scope of work, requiring additional time to incorporate the necessary changes. In addition, there has been a delay in obtaining the amended MOEF (Ministry of Environment and Forests) NOC, which has further affected the project schedule. We want to ensure that the project is completed to the highest standards of quality and within the expectations set. Granting this extension will allow us to manage the revised scope efficiently and deliver the b

Litigation declared3

CaseCourtStatus
5570/2005City CivilPending
600/2014High CourtDisposed Off
1861/2013High Courtpending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000056070Kishor Shamji Thakker, Kamla Kishor Thakker, Vinay Kishor ThakkerSumer Builders Pvt. Ltd., Bharat Shah, Ramesh Shah, Rahul Shah, Manish Bafna05/09/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Mar 2024

Documents filed233

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 233 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Eon One as on June 2026.pdf10 Aug 2026
Withdrawal Update Form 2File: Form 2 - Eon One as on June 2026.pdf10 Aug 2026
Withdrawal Update Form 3File: Form 3 - Eon One as on June 2026.pdf10 Aug 2026
Form 2A (FY 2020-2021)File: Eon one Form 2A 2020-21.pdf2 Jul 2026
Form 2A (FY 2021-2022)File: Eon one Form 2A 2021-22.pdf1 Jul 2026
Form 2A (FY 2022-2023)File: Eon one Form 2A 2022-23.pdf1 Jul 2026
Form 2A (FY 2023-2024)File: Eon one Form 2A 2023-24.pdf1 Jul 2026
Form 2A (FY 2025-2026)File: Eon one Form 2A 2025-26.pdf1 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25 Eon One.pdf18 Jun 2026
Form 5 (FY 2023-2024)File: Form-5 Eon One For 2023-24.pdf17 Jun 2026
Form 5 (FY 2024-2025)File: Form-5 Eon One For 2024-25.pdf17 Jun 2026
Withdrawal Update Form 1File: Form 1 - Eon One as on March 2026.pdf11 Jun 2026
Withdrawal Update Form 2File: Form 2 - Eon One as on March 2026.pdf11 Jun 2026
Withdrawal Update Form 3File: Form 3 - Eon One as on March 2026.pdf11 Jun 2026
Withdrawal Update Form 1File: Form 1 - Eon One as on Dec 2025.pdf6 Jun 2026
Withdrawal Update Form 2File: Form 2 - Eon One as on Dec 2025.pdf6 Jun 2026
Withdrawal Update Form 3File: Form 3 Eon One 31-12-2025.pdf6 Jun 2026
Withdrawal Update Form 1File: Form 1 - Eon One as on June 2025.pdf3 Dec 2025
Withdrawal Update Form 1File: Form 1 - Eon One as on Sep 2025.pdf3 Dec 2025
Withdrawal Update Form 2File: Form 2 - Eon One as on June 2025.pdf3 Dec 2025
Withdrawal Update Form 2File: Form 2 - Eon One as Sep 2025.pdf3 Dec 2025
Withdrawal Update Form 3File: Form 3 - Eon One as on June 2025.pdf3 Dec 2025
Withdrawal Update Form 3File: Form 3 - Eon One as Sep 2025.pdf3 Dec 2025
Details of encumbrancesFile: Encumbrance Letter-Finance.pdf9 Jul 2025
Layout approvalFile: Plan 1.pdf7 Apr 2025
Building plan approvalFile: Plan 2.pdf7 Apr 2025
Building plan approvalFile: Plan 3.pdf7 Apr 2025
Building plan approvalFile: Plan 4.pdf7 Apr 2025
Building plan approvalFile: Plan 5.pdf7 Apr 2025
Building plan approvalFile: Plan 6.pdf7 Apr 2025
Building plan approvalFile: Plan 7.pdf7 Apr 2025
Building plan approvalFile: Plan 8.pdf7 Apr 2025
Building plan approvalFile: Plan 9.pdf7 Apr 2025
Building plan approvalFile: Plan 10.pdf7 Apr 2025
Building plan approvalFile: Plan 11.pdf7 Apr 2025
Building plan approvalFile: Plan 12.pdf7 Apr 2025
Building plan approvalFile: Plan 13.pdf7 Apr 2025
Building plan approvalFile: Plan 14.pdf7 Apr 2025
Building plan approvalFile: Plan 15.pdf7 Apr 2025
Building plan approvalFile: Plan 16.pdf7 Apr 2025
Building plan approvalFile: Plan 17.pdf7 Apr 2025
Building plan approvalFile: Plan 18.pdf7 Apr 2025
Building plan approvalFile: Plan 19.pdf7 Apr 2025
Building plan approvalFile: Plan 20.pdf7 Apr 2025
Building plan approvalFile: Plan 21.pdf7 Apr 2025
Building plan approvalFile: Plan 22.pdf7 Apr 2025
Copy of Layout Approval (in case of layout)File: Plan 1.pdf7 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 22.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 21.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 20.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 19.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 18.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 17.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 16.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 15.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 14.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 13.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 12.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 11.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 10.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 9.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 8.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 7.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 6.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 5.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 4.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 3.pdf7 Apr 2025
Building Plan Approval (IOD)File: Plan 2.pdf7 Apr 2025
Certificates of CA (Form 3)File: Form 3 - Eon One as on Dec 2024.pdf12 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Eon One as on Dec 2024.pdf12 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf15 Feb 2025
Certificates of CA (Form 3)File: 25 Certificates of CA (Form 3).pdf15 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf15 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Eon One as on Dec 2024.pdf21 Jan 2025
Layout approvalFile: 1.pdf8 Jan 2025
Building plan approvalFile: 2.pdf8 Jan 2025
Building plan approvalFile: 3.pdf8 Jan 2025
Building plan approvalFile: 4.pdf8 Jan 2025
Building plan approvalFile: 5.pdf8 Jan 2025

How this compares with Mumbai City

42%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 30 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Eon One on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Siddhivinayak Temple780+ in Mumbai City

2 kmEon OneCompleted 85Lapsed / revoked 62Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 248 registered projects within 2 km.

Builder: Firstlight Properties Private Limited

Firstlight Properties Private Limited has 1 registration on MahaRERA, including Eon One. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Eon One shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Eon One is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Eon One?

The registered promoter entity is Firstlight Properties Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Eon One?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Eon One?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Eon One?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Eon One?

The professionals named in the filing: Architect: Planet E Consultants; Engineer: SK Consultants & Engineers; Engineer: MS CONSULTANTS AND ENGINEERS; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Vinod Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Eon One?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Eon One. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Eon One to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.