Home / Browse projects / Mumbai City, Maharashtra / PALETTE

Registered Litigation declared Residential / Group Housing project

PALETTE

By SURAJ ESTATE DEVELOPERS LTD

RG-MH-24772 · RERA P51900008207 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Litigation declared, 2 cases
  • 4 complaints at MahaRERA
  • Completion date moved by 39 months
  • 3 extensions taken
  • Rs 175.00 crore secured on the land, in favour of INDUSIND BANK LTD

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 99%
20 of 152Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 210 documents Report an error

PALETTE is a Residential / Group Housing project by SURAJ ESTATE DEVELOPERS LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900008207 on 18 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 39 months from the original filing. 132 of the 152 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NamePALETTE
  • TypeResidential / Group Housing
  • Location
    • S.K.BOLE ROAD
    • DADAR-WEST
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900008207
  • ReraGenie IDRG-MH-24772

Builder

  • NameSURAJ ESTATE DEVELOPERS LTD
  • Entity typeCompany
  • CINU99999MH1986PTC040873
  • GSTIN27AAACS8375H1Z0
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorTHOMAS RAJAN
  • Other registrations14 more →
  • Completed4 of 15
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

1 months past promisethis monthRegisteredAug 2017First promiseJun 2023Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed210 files

Current status

87%132 of 152 units booked
98.8%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PALETTENA51391520152

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 99%.

PALETTE: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure99%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes40%
Open ParkingYes10%

Parking filed302

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots302
Closed/Covered284
Open Space18

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,267 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofINDUSIND BANK LTD
Secured amountRs 175.00 crore
CERSAI search filedYes
Declared on17 Dec 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI20468.69
Proposed, not sanctioned20,331 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR MARATHE UDYOG BHAVAN , APPASAHEB MARATHE MARG , NEXT TO SKODA SHOWROOM , PRABHADEVI , MUMBAI 400025
Estimated costRs 220.04 cr
Cost incurredRs 217.28 cr
Work done98.75%
BuildingWingEstimatedIncurred
-NARs 220.04 crRs 217.28 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyanka Rajaram Rahate
ArchitectArchvision Architects
EngineerMadhura Manjrekar
EngineerRohan Thanedar
EngineerMr Dayanand Gangawane
Chartered AccountantJigar Zaveri & Associates
Chartered AccountantRakesh jain
Chartered AccountantAbhishek Bajaj
PartnerRole in project
SURAJ ESTATE DEVELOPERS LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900016805Jun 2023 → Jun 2024

Reason as filed by the promoterWe have registered our building “PALETTE” with MahaRERA vide registration No. P51900008207. At the time of RERA registration of the said building, the original approved plans of the said building consisted of 2 wings viz Wing ‘A’ and Wing ‘B’ approved vide IOD No. EB/7240/GN/A dated 03/08/2015 utilizing the basic FSI available under Regulation 33(7) of DCR 1991 without utilizing fungible FSI etc. Wing ‘A’ of the said building consists of ground + 7 upper floors while wing ‘B’ was part basement + ground + 7 podium floors + 11 upper floors. The said plans were amended on 24/08/2018 under new fil

EXT51900019004Jun 2023 → Dec 2025

Reason as filed by the promoterWe have submitted for amendment of building plans for Ground + Service Floor + 2 a to 9th Residential Floor + Terrace and "B" Wing consisting of Part Basement +Ground / Stilt + 1st to 9th Podium + 10th Service Floor + 11th Amenity Floor +12th to 50* upper residential floor +Terrace and the Concessional Note for the same was approved by Municipal Commissioner on 15/09/2023. We need to obtain the approvals from MOEF and High Rise Committee respectively, we shall be in a position to approach MCGM to issue further CC for the full potential i.e. upto top of 50th floor. All these approvals are expec

EA24122518974Jun 2023 → Sep 2026

Reason as filed by the promoter23 December 2025 To, The Chairman, MahaRERA, Bandra (E), Mumbai. Dear Sir, Ref.: Project known as “Palette” bearing MahaRERA Registration No. P51900008207 Sub.: Extension of project completion date upto 30/09/2026 We have registered our building “Palette” with MahaRERA vide Registration No. P51900008207. At the time of the Chief Fire Officer granting approval for the project in the year 2018, there was a condition introduced in the Fire NOC directing that an “Ascending Descending Evacuation System” should be installed on the external face of the building from the terrace with guideline along w

Litigation declared2

CaseCourtStatus
CC006000000590990/2024MAHARASHTRA REAL ESTATE REGULATORY AUTHORITYOngoing
CC006000000591019/2024MAHARASHTRA REAL ESTATE REGULATORY AUTHORITYOngoing

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000590990Prasad TulaskarSuraj Estate Developers Ltd02/07/2024
CC006000000591019Anirudha Suraj DagaSUraj Estate Developers Pvt Ltd04/07/2024
CC12400728Salil Dattakumar DeshmukhSURAJ ESTATE DEVELOPERS LTD11/11/2024
CC12401299AKSHAY RAMESH GUTKASURAJ ESTATE DEVELOPERS LTD31/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed210

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 210 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1 jUNE 2026 Palette (1).pdf24 Jul 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE - Palette - March 2026.pdf24 Jul 2026
Withdrawal Update Form 3File: RERA Form 3_Certificate_Palette_24072026.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1 FP 823 23-06-2026.pdf23 Jun 2026
Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE - Palette - Dec 2025.pdf23 Jun 2026
Withdrawal Update Form 3File: form 3 -sep.pdf23 Jun 2026
Withdrawal Update Form 1File: SIGNED COPY fORM 1 JUNE 25.pdf22 Dec 2025
Withdrawal Update Form 1File: september 25.pdf22 Dec 2025
Withdrawal Update Form 1File: september 25.pdf22 Dec 2025
Withdrawal Update Form 2File: Engineers Certificate JUNE 25.pdf22 Dec 2025
Withdrawal Update Form 2File: Engineers Certificate JUNE 25.pdf22 Dec 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf22 Dec 2025
Withdrawal Update Form 3File: form 3 - june SIGNED SCAN.pdf22 Dec 2025
Withdrawal Update Form 3File: form 3 -sep.pdf22 Dec 2025
Withdrawal Update Form 3File: form 3 -sep.pdf22 Dec 2025
Form 2A (FY 2024-2025)File: Quality ASSURANCE Certificate - March -2025 (1).pdf16 Dec 2025
Form 5 (FY 2024-2025)File: form -5.pdf16 Dec 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: pALETTE.pdf15 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Palette.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PALETTE.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: palette.pdf15 Jan 2025
Certificates of CA (Form 3)File: Form-3_compressed.pdf23 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sept Palette_compressed.pdf18 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 2446884_FurtherCC_signed.pdf10 Dec 2024
Other - TechnicalFile: MOEF NOC.pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 823_work completion.pdf27 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE - FP 823 - September 2024.pdf27 Nov 2024
OtherFile: Certificate335969.pdf27 Nov 2024
OtherFile: Rera Training Certificate_280000804_9_4_2023.pdf27 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Old bank details.pdf14 Nov 2024
Building plan approvalFile: PLAN 1.pdf8 Nov 2024
Building plan approvalFile: PLAN 2.pdf8 Nov 2024
Building plan approvalFile: 3.pdf8 Nov 2024
Building plan approvalFile: 4.pdf8 Nov 2024
Building plan approvalFile: 5.pdf8 Nov 2024
Building plan approvalFile: 6.pdf8 Nov 2024
Building plan approvalFile: 7.pdf8 Nov 2024
Building plan approvalFile: 8.pdf8 Nov 2024
Building plan approvalFile: 9.pdf8 Nov 2024
Building plan approvalFile: 10.pdf8 Nov 2024
Building plan approvalFile: 11.pdf8 Nov 2024
Building plan approvalFile: 12.pdf8 Nov 2024
Building plan approvalFile: 13.pdf8 Nov 2024
Building plan approvalFile: 14.pdf8 Nov 2024
Building plan approvalFile: 15.pdf8 Nov 2024
Building plan approvalFile: 16.pdf8 Nov 2024
Building plan approvalFile: Letter.pdf8 Nov 2024
Building plan approvalFile: 1 SHEET.pdf8 Nov 2024
Building Plan Approval (IOD)File: 4.pdf8 Nov 2024
Building Plan Approval (IOD)File: 5.pdf8 Nov 2024
Building Plan Approval (IOD)File: 6.pdf8 Nov 2024
Building Plan Approval (IOD)File: 7.pdf8 Nov 2024
Building Plan Approval (IOD)File: 8.pdf8 Nov 2024
Building Plan Approval (IOD)File: 9.pdf8 Nov 2024
Building Plan Approval (IOD)File: 10.pdf8 Nov 2024
Building Plan Approval (IOD)File: 11.pdf8 Nov 2024
Building Plan Approval (IOD)File: 12.pdf8 Nov 2024
Building Plan Approval (IOD)File: 13.pdf8 Nov 2024
Building Plan Approval (IOD)File: 14.pdf8 Nov 2024
Building Plan Approval (IOD)File: 15.pdf8 Nov 2024
Building Plan Approval (IOD)File: 16.pdf8 Nov 2024
Building Plan Approval (IOD)File: Letter.pdf8 Nov 2024
Building Plan Approval (IOD)File: 1 SHEET.pdf8 Nov 2024
Building Plan Approval (IOD)File: PLAN 2.pdf8 Nov 2024
Building Plan Approval (IOD)File: PLAN 1.pdf8 Nov 2024
Building Plan Approval (IOD)File: 3.pdf8 Nov 2024
Building plan approvalFile: Drawing - A-1.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-2.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-3.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-4.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-4.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-5.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-6.pdf5 Nov 2024
Building plan approvalFile: Drawing - B-1_11zon.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-1_11zon.pdf5 Nov 2024
Building plan approvalFile: Drawing - A-3_11zon (1).pdf5 Nov 2024
Building Plan Approval (IOD)File: Drawing - A-1.pdf5 Nov 2024
Building Plan Approval (IOD)File: Drawing - A-2.pdf5 Nov 2024
Building Plan Approval (IOD)File: Drawing - A-3.pdf5 Nov 2024
Building Plan Approval (IOD)File: Drawing - A-4.pdf5 Nov 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
HALLMARKCS 104 BHIMWADI WADALA EAST MUMBAI7CompletedJul 2016Late, Nov 2016
ETERNITY APARTMENTFP 469 MMC CROSS ROAD MAHIM WEST MUMBAI 40001616CompletedAug 2011Aug 2011
PARK SIDEFP 888 DATTA RAUL ROAD DADAR WEST MUMBAI 40002828CompletedJul 2010Late, Feb 2011

How this compares with Mumbai City

87%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 39 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PALETTE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DADAR-WEST780+ in Mumbai City

2 kmPALETTECompleted 55Lapsed / revoked 53Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 199 registered projects within 2 km.

Builder: SURAJ ESTATE DEVELOPERS LTD

SURAJ ESTATE DEVELOPERS LTD has 15 registrations on MahaRERA, including ST ANTHONY APARTMENT and TRANQUIL BAY. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if PALETTE is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALETTE?

The registered promoter entity is SURAJ ESTATE DEVELOPERS LTD, a company as per the filing. Its CIN U99999MH1986PTC040873 and GSTIN 27AAACS8375H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALETTE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PALETTE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PALETTE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALETTE?

The professionals named in the filing: Architect: Priyanka Rajaram Rahate; Architect: Archvision Architects; Engineer: Madhura Manjrekar; Engineer: Rohan Thanedar; Engineer: Mr Dayanand Gangawane; Chartered Accountant: Jigar Zaveri & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALETTE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALETTE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALETTE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.