Vishwakarma Heights
RG-MH-03289 · RERA P99000020857 · Last updated on MahaRERA portal: 8 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 17 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vishwakarma Heights is a Residential / Group Housing project by M/S. VISHWAKARMA NAGAR in Palghar, Maharashtra, registered with MahaRERA as P99000020857 on 15 May 2019. Possession is promised by 31 May 2027. The completion date has moved by 17 months from the original filing. 15 of the 104 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameVishwakarma Heights
- TypeResidential / Group Housing
- Location
- Survey No 200
- Plot No 30
- 33
- 36
- 37
- 38
- 39
- 40
- 43
- 44
- 45
- 46
- S No 21 H No 4
- 11
- S No 261
- 262
- VASAI
- Diwanman
- Palghar
- 401202
- Pincode401202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000020857
- ReraGenie IDRG-MH-03289
Builder
- NameM/S. VISHWAKARMA NAGAR
- Entity typePartnership
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 May 2019
- Promised completion31 May 2027
- Revised completionRevised to 31 May 2027 (originally 30 Dec 2025)
- Buildings1 building record
- Documents filed94 files
Current status
Figures as on 8 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 2 | NA | 24 | 21 | 104 | 0 | 104 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.
Building No 2: 53% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 5% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
Progress on shared amenities15
As on 8 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed227
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building No 2 | NA | Rs 7.00 cr | Rs 4.20 cr |
| - | NA | Rs 4.00 cr | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjay S Narang |
| Engineer | Ajay R Shah |
| Engineer | AAYUSH DUBEY |
| Engineer | RAJESH DUBEY |
| Chartered Accountant | ANKUR HITENDRA SHAH |
| Chartered Accountant | VIVEK JAYESH THAR |
| Chartered Accountant | Rishisekhriandassociates |
| Partner | Role in project |
|---|---|
| M/s VISHWAKARMA NAGAR | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAt the time of registration, the approved project plan consisted of 14 floors. Subsequently, the firm decided to extend the project up to 21 floors, and the same has been duly approved by the competent authority as per Order No. VVCMC/TP/RDP/VP0568/10/2025-26 dated 16.06.2025, issued by the Town Planning Authority. The revised approval along with the Commencement Certificate dated 16 June 2025 has already been uploaded on the MahaRERA portal.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Aug 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 May 2027
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form1.pdf | 8 Aug 2026 |
| Withdrawal Update Form 2File: form230062026.pdf | 8 Aug 2026 |
| Withdrawal Update Form 3File: form3finalupload.pdf | 8 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Final.pdf | 12 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Final.pdf | 12 Jun 2026 |
| Withdrawal Update Form 3File: Form3.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 31122025.pdf | 6 Mar 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 05032026.pdf | 6 Mar 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 05032026.pdf | 6 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 31122025.pdf | 4 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate 311220225.pdf | 4 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 17012026_compressed.pdf | 4 Mar 2026 |
| Withdrawal Update Form 1File: Vishwakarma form 1 Sep 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 2File: Vishwakarma form 2 Sep 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 3File: Vishwakarma Form-3 Sep 2025..pdf | 23 Feb 2026 |
| Withdrawal Update Form 1File: Vishwakarma form 1 Sep 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 1File: Vishwakarma form 1 Sep 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Vishwakarma form 2 Sep 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Vishwakarma form 2 Sep 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: Vishwakarma Form-3 Sep 2025..pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: Vishwakarma Form-3 Sep 2025..pdf | 20 Nov 2025 |
| Form 1File: form1march23.pdf | 15 Oct 2025 |
| Form 2File: Form2march23.pdf | 15 Oct 2025 |
| Form 3File: form3march2023.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1june23.pdf | 15 Oct 2025 |
| Form 2File: form2 june 23.pdf | 15 Oct 2025 |
| Form 3File: Form3june23.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure inventory.pdf | 15 Oct 2025 |
| Form 1File: form1sept23.pdf | 15 Oct 2025 |
| Form 2File: form2sept23.pdf | 15 Oct 2025 |
| Form 3File: form3sept2023.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1dec23.pdf | 15 Oct 2025 |
| Form 2File: form2dec23.pdf | 15 Oct 2025 |
| Form 3File: form3dec23.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1march24.pdf | 15 Oct 2025 |
| Form 2File: Form2march24.pdf | 15 Oct 2025 |
| Form 3File: Form3march24.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1june24.pdf | 15 Oct 2025 |
| Form 2File: Form2june24.pdf | 15 Oct 2025 |
| Form 3File: Form3 June 2024.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1sept24.pdf | 15 Oct 2025 |
| Form 2File: form2sept24.pdf | 15 Oct 2025 |
| Form 3File: Form3sept 2024.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure.pdf | 15 Oct 2025 |
| Form 1File: form1dec24.pdf | 15 Oct 2025 |
| Form 2File: form2dec24.pdf | 15 Oct 2025 |
| Form 3File: Form3Dec 2024_compressed.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 15 Oct 2025 |
| Layout approvalFile: LAYOUT_compressed.pdf | 16 Aug 2025 |
| Building plan approvalFile: page1.pdf | 16 Aug 2025 |
| Building plan approvalFile: page2.pdf | 16 Aug 2025 |
| Building plan approvalFile: page3.pdf | 16 Aug 2025 |
| Form 1File: form1 jun25 07-Aug-2025 17-12-57.pdf | 16 Aug 2025 |
| Form 2File: FORM 2_ENGINEER'S CERTIFICATE-JUNE 25.pdf | 16 Aug 2025 |
| Form 3File: Form -3 final vishvakarma signed_compressed.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure jun 16-Aug-2025 16-11-20.pdf | 16 Aug 2025 |
| Form 5 (FY 2022-2023)File: Form5 2022-2023.pdf | 5 Aug 2025 |
| Form 5 (FY 2023-2024)File: Form5 2023-2024 Sigmed.pdf | 5 Aug 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Signed.pdf | 5 Aug 2025 |
| Form 1File: Form-1.pdf | 1 Aug 2025 |
| Form 2File: FORM 2.pdf | 1 Aug 2025 |
| Form 3File: Form3.pdf | 1 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure March 2025.pdf | 1 Aug 2025 |
| Form 2A (FY 2019-2020)File: Form2A2019-2020.pdf | 26 Jul 2025 |
| Form 2A (FY 2020-2021)File: form2a 2020-2021.pdf | 26 Jul 2025 |
| Form 2A (FY 2021-2022)File: Form2A2021-2022.pdf | 26 Jul 2025 |
| Form 2A (FY 2022-2023)File: Form2A2022-2023.pdf | 26 Jul 2025 |
| Form 2A (FY 2023-2024)File: form2A 2023-2024.pdf | 26 Jul 2025 |
| Form 2A (FY 2024-2025)File: Form2A 2024-2025.pdf | 26 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 VNAGAR_compressed.pdf | 23 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Vishwakarma Nagar.pdf | 8 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 VNAGAR.pdf | 2 Apr 2021 |
| Building plan approvalFile: Plan Bldg 2 Sheet 2 compressed.pdf | 4 May 2019 |
| Layout approvalFile: Layout Plan-min-compressed (2) (1).pdf | 4 May 2019 |
| PAN CardFile: PAN Vishwakarma Nagar.pdf | 4 May 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vishwakarma Heights on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VASAI3,200+ in Palghar
PEARL GARDENS
Mansarovar Lifespaces LLP
ORNATE SERENITY
SAI ORNATE DEVELOPERS
FLAMINGO RESIDENCY
SHANTEE REALTY AND LIFE SPACE
ALTURA UMELE
RUBY LIFESPACES
RBI EmployeesGokul Co-Op. Housing Society Ltd,
SW REALTORS
J V NAGAR
JONES VEGAS BUILDERS
See every Palghar project, with the district possession charts
Builder: M/S. VISHWAKARMA NAGAR
M/S. VISHWAKARMA NAGAR has 1 registration on MahaRERA, including Vishwakarma Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Vishwakarma Heights is delayed beyond 31 May 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vishwakarma Heights?
The registered promoter entity is M/S. VISHWAKARMA NAGAR, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vishwakarma Heights?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vishwakarma Heights?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vishwakarma Heights?
The professionals named in the filing: Architect: Sanjay S Narang; Engineer: Ajay R Shah; Engineer: AAYUSH DUBEY; Engineer: RAJESH DUBEY; Chartered Accountant: ANKUR HITENDRA SHAH; Chartered Accountant: VIVEK JAYESH THAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vishwakarma Heights?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback