ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / ORNATE SERENITY

Registered No litigation declared Residential / Group Housing project

ORNATE SERENITY

By SAI ORNATE DEVELOPERS

RG-MH-05350 · RERA P99000051678 · Last updated on MahaRERA portal: 2 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
7 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 91%
160 of 363Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

ORNATE SERENITY is a Residential / Group Housing project by SAI ORNATE DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000051678 on 27 Jun 2023. Possession is promised by 31 Mar 2028. 203 of the 363 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameORNATE SERENITY
  • TypeResidential / Group Housing
  • Location
    • JUCHANDRA
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401202
  • Pincode401202
  • RERA no.P99000051678
  • ReraGenie IDRG-MH-05350

Builder

  • NameSAI ORNATE DEVELOPERS
  • Entity typePartnership
  • PartnerSunil Gupta
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2023
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed88 files

Current status

56%203 of 363 units booked
67.0%Work done, per cost certificate

Figures as on 2 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ornate Serenity A Wing Building No 17NA31311390139
Ornate Serenity B Wing Building No 16NA31312240224

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 91%.

Ornate Serenity A Wing Building No 1759%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure74%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Ornate Serenity B Wing Building No 1652%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure91%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered78
BuildingClosed/CoveredTotal
Ornate Serenity A Wing Building No 173232
Ornate Serenity B Wing Building No 164646

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,420 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jul 2025

Approvals and building plan

Sanctioning authorityVASAI VIRAL CITY MUNCIPAL CORARATION
Permissible FSI35821.08
Proposed, not sanctioned26,346 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchANDHERI EAST
Estimated costRs 160.00 cr
Cost incurredRs 107.21 cr
Work done67.01%
BuildingWingEstimatedIncurred
Ornate Serenity A Wing Building No 17NARs 80.00 crRs 53.61 cr
Ornate Serenity B Wing Building No 16NARs 80.00 crRs 53.61 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANJAY NARANG
EngineerMr. Milind Wajekar
Chartered AccountantJAIN SINGH & CO
Chartered AccountantAgarwala Sourav & Associates
Chartered AccountantANUSAYA SINGH & COMPANY
PartnerRole in project
SAI ORNATE DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf2 May 2026
Withdrawal Update Form 2File: form 2.pdf2 May 2026
Withdrawal Update Form 3File: FORM 3 (7).pdf2 May 2026
Withdrawal Update Form 1File: Architect Certificate Serinity- Oct 25 to Dec 25.pdf19 Feb 2026
Withdrawal Update Form 2File: ENGINEERING CERTIFICATE.pdf19 Feb 2026
Withdrawal Update Form 3File: CA Certificate - Revised.pdf19 Feb 2026
Withdrawal Update Form 1File: Architect Cert.pdf10 Dec 2025
Withdrawal Update Form 2File: form 2.pdf10 Dec 2025
Withdrawal Update Form 3File: Sai Ornate Developers (Ornate Serenity) Q2 25-26 (6) signed (1)_compressed.pdf10 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate SOD.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Mar-25.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf23 Oct 2024
Details of encumbrances concerned to FinanceFile: ORNATE SERENITY - A WING.pdf29 Jul 2024
Details of encumbrances concerned to FinanceFile: ORNATE SERENITY- B WING.pdf29 Jul 2024
Details of encumbrances concerned to LegalFile: ORNATE SERENITY - A WING.pdf29 Jul 2024
Details of encumbrances concerned to LegalFile: ORNATE SERENITY- B WING.pdf29 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ORNATE SERENITY ARCHITECT CERTIFICATE.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate_Ornate Serenity.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Ornate Serenity- Q1-24-25 Signed.pdf26 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: CC mail.pdf21 May 2024
Other - TechnicalFile: CC mail.pdf21 May 2024
Declaration about Commencement CertificateFile: DECLERATION OF CC FORMAT D.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate of SOD.pdf18 May 2024
Declaration about Commencement CertificateFile: DECLERATION OF CC FORM D.pdf30 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A declaration.pdf13 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-declaration.pdf13 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ornate Serenity.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Inventory_11zon.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sai Ornate_compressed.pdf12 Mar 2024
Building plan approvalFile: 2_compressed.pdf29 Feb 2024
Building plan approvalFile: 3_compressed.pdf29 Feb 2024
Building plan approvalFile: 4_compressed.pdf29 Feb 2024
Building plan approvalFile: 5_compressed.pdf29 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf29 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf29 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 4_compressed.pdf29 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 5_compressed.pdf29 Feb 2024
Declaration about Commencement CertificateFile: Format D.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf6 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 OLD.pdf11 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory Serenity.pdf5 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE_ORNATE SERENITY.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE_SERENITY_SIGN.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA RERA CERTIFICATE SOD SERENITY_Sign.pdf20 Oct 2023
Layout approvalFile: Ornate Serenity CC Plan 1 22-08-2023.pdf27 Sep 2023
Layout approvalFile: Ornate Serenity CC Plan 2 22-08-2023.pdf27 Sep 2023
Layout approvalFile: Ornate Serenity CC Plan 3 22-08-2023.pdf27 Sep 2023
Layout approvalFile: Ornate Serenity CC Plan 4 22-08-2023.pdf27 Sep 2023
Copy of Layout Approval (in case of layout)File: Ornate Serenity CC Plan 1 22-08-2023.pdf27 Sep 2023
Copy of Layout Approval (in case of layout)File: Ornate Serenity CC Plan 2 22-08-2023.pdf27 Sep 2023
Copy of Layout Approval (in case of layout)File: Ornate Serenity CC Plan 3 22-08-2023.pdf27 Sep 2023
Copy of Layout Approval (in case of layout)File: Ornate Serenity CC Plan 4 22-08-2023.pdf27 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: Ornate Serenity CC 22-08-2023.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CERTIFICATE SOD signed 23 05 2023.pdf23 May 2023
Layout approvalFile: Layout (2) (1).pdf19 May 2023
Building plan approvalFile: Layout (2) (1).pdf19 May 2023
Layout approvalFile: plan compress.pdf19 May 2023
Building plan approvalFile: plan compress.pdf19 May 2023
Copy of Layout Approval (in case of layout)File: Layout (2) (1).pdf19 May 2023
Copy of Layout Approval (in case of layout)File: plan compress.pdf19 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout (2) (1).pdf19 May 2023
Building Plan Approval / NA Order for plotted developmentFile: plan compress.pdf19 May 2023
Declaration about Commencement CertificateFile: Revise CC declaration.pdf19 May 2023
Proforma of Agreement for saleFile: afs ornate serenity final.pdf19 May 2023
Details of encumbrances concerned to FinanceFile: No encumbrance.pdf17 Apr 2023
Details of encumbrances concerned to LegalFile: No encumbrance.pdf17 Apr 2023
CERSAI detailsFile: Cersai.pdf17 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details.pdf17 Apr 2023

How this compares with Palghar

56%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ORNATE SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JUCHANDRA3,200+ in Palghar

Builder: SAI ORNATE DEVELOPERS

Sai Ornate Developers has 3 registrations on MahaRERA, including Ornate Galaxy Phase I and ORNATE GALAXY PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if ORNATE SERENITY is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORNATE SERENITY?

The registered promoter entity is SAI ORNATE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORNATE SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ORNATE SERENITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORNATE SERENITY?

The professionals named in the filing: Architect: ANJAY NARANG; Engineer: Mr. Milind Wajekar; Chartered Accountant: JAIN SINGH & CO; Chartered Accountant: Agarwala Sourav & Associates; Chartered Accountant: ANUSAYA SINGH & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORNATE SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORNATE SERENITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORNATE SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.