Home / Browse projects / Mumbai Suburban, Maharashtra / VISHRAM

Registration lapsed No litigation declared Residential / Group Housing project

VISHRAM

By JEEVANDEEP DEVELOPERS

RG-MH-45009 · RERA P51800014810 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 87 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0 of 10Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

VISHRAM is a Residential / Group Housing project by JEEVANDEEP DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014810 on 2 Jan 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 87 months from the original filing. 10 of the 10 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameVISHRAM
  • TypeResidential / Group Housing
  • Location
    • BORIVALI
    • Mumbai Suburban
    • 400016
  • Pincode400016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800014810
  • ReraGenie IDRG-MH-45009

Builder

  • NameJEEVANDEEP DEVELOPERS
  • Entity typePartnership
  • PartnersDEEPA BHUVANESH WARDE, AMEYA UDAY RAWOOL
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

4 months past promisethis monthRegisteredJan 2018First promiseMar 2019Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Jan 2018
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed122 files

Current status

100%10 of 10 units booked
75.0%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VISHRAMNA9710010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

VISHRAM: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area225 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMUNICIPAT CORPORAIION OF GREATER MUMBAI
Permissible FSI820.34
Proposed, not sanctioned820 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVAJI PARK,RIGVED, GROUND FLOOR,VEER SAVARKAR MARG,DADAR WEST, MUMBAI-400028
Estimated costRs 2.10 cr
Cost incurredRs 1.57 cr
Work done75.0%
BuildingWingEstimatedIncurred
VISHRAMNARs 1.95 crRs 1.57 cr
-NARs 15.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUMEDHA GORE
EngineerUDAY D CHANDE
Chartered AccountantSukhwal And Associates
PartnerRole in project
JEEVANDEEP DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011453Mar 2019 → Aug 2023

Reason as filed by the promoter1. We had obtained RERA Registration For “Vishram” Project under No. P51800014810 dated 2/1/2018 2. Registration was valid till 20/06/2021 3. The project Comprises of one building. The work has been delayed as IOD obtained under DCR 1991 could not be revalidated. We have commencement certificate 24/10/19 and the commencement certificate on 24/10/19. Due to covid pandemic we could not commence the work till Augest 2020. At present we have completed work uptoplinth level 4. We Request you to extend the date of completion to 30/08/2023 to give possession to the allotees of flats

EXT51800003639Mar 2019 → Dec 2020

Reason as filed by the promoterWe had obtained RERA registration for “vishram” project under No. P51800014810 dated 02/01/2018. Registration was valid till 31/03/2019. The project comprises of one building. The work has been delayed as IOD obtained under DCR 1991 could not be revalidated. We have obtained IOD under new DCPR 2034 on 24/10/19 and have started the process of completing compliances for obtaining commencement certificate We request you to extend the date of completion to 20/12/2020 to give possession to the allottees of flats.

EXT51800027204Mar 2019 → Jun 2026

Reason as filed by the promoter1) We had obtained RERA Registration for "Nehru Nagar Vishwadham" project under No. P51800015420 dated 23.02.2018 2) Registration was valid till 30.12.2024 3) We applied for upper floors i.e 17th to 20th floors NOC's/Permission like EETC Remark, CFO, FSI NOC, Concession, Amended Plan and Commencement Certificate from BMC and MHADA. We will complete the project within stipulated period of time declarations and explanations about the same is provided to you. In view of the above, we could not complete the proposed development as per prescribed schedule due to above reasons. We therefore request

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Dec 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Dec 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf4 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf4 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf4 Jul 2026
Withdrawal Update Form 3File: Form 3 (1).pdf4 Jul 2026
Withdrawal Update Form 3File: Form 3 (1).pdf4 Jul 2026
Withdrawal Update Form 3File: Form 3 (1).pdf4 Jul 2026
Form 1File: Rera Form 5 23-24.pdf27 Jul 2025
Form 3File: FORM 3 RERA .pdf27 Jul 2025
Form 2File: RERA FORM 2A .pdf27 Jul 2025
OthersFile: FORM 2 RERA ACT .pdf27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DECLERATION.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025
Form 3File: FORM 3 CA CERTIFICATE.PDF27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf27 Jul 2025
Form 1File: FORM 1 ARCHITECH CERTIFICATE .pdf27 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE .pdf27 Jul 2025

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 87 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VISHRAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI6,700+ in Mumbai Suburban

2 kmVISHRAMCompleted 136Lapsed / revoked 74Other 181Dot size: filed unitsN

Filed coordinates, straight-line distance. 391 registered projects within 2 km.

Builder: JEEVANDEEP DEVELOPERS

JEEVANDEEP DEVELOPERS has 2 registrations on MahaRERA, including SHRI YAMAI KRUPA and VISHRAM. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VISHRAM shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VISHRAM is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISHRAM?

The registered promoter entity is JEEVANDEEP DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISHRAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VISHRAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISHRAM?

The professionals named in the filing: Architect: SUMEDHA GORE; Engineer: UDAY D CHANDE; Chartered Accountant: Sukhwal And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISHRAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISHRAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISHRAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.