Home / Browse projects / Mumbai Suburban, Maharashtra / VINIYOG CHS LTD.

Completed No litigation declared Residential / Group Housing project

VINIYOG CHS LTD.

By VINAYAK DEVELOPERS

RG-MH-40422 · RERA P51800008768 · Last updated on MahaRERA portal: 16 Dec 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

VINIYOG CHS LTD. is a Residential / Group Housing project by VINAYAK DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008768 on 19 Aug 2017. The registration is recorded completed; possession was promised by 30 Jul 2022. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameVINIYOG CHS LTD.
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400062
  • Pincode400062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008768
  • ReraGenie IDRG-MH-40422

Builder

  • NameVINAYAK DEVELOPERS
  • Entity typePartnership
  • PartnersKUNDALSINGH MADHAVSINGH IGRAL, RAJKUMAR MADHAVSINGH IGRAL, MAHENDRA MADHAVSINGH IGRAL
  • Other registrations16 more →
  • Completed6 of 17
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects10 →

Key dates

this monthRegisteredAug 2017First promiseJul 2020Revised toJul 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion30 Jul 2022
  • Revised completionRevised to 30 Jul 2022 (originally 30 Jul 2020)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VINIYOG CHS LTDNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

VINIYOG CHS LTD: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered1
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area461 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1244.56
Proposed, not sanctioned381 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIKAS CHAMBER, MARVE LINK ROAD JUNCTION, MALAD WEST MUMBAI 400064

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR NANDKUMAR CHOGLE OF CHOGLE & ASSOCIATES
EngineerMr Haresh Laxmanbhai Patel
PartnerRole in project
VINAYAK DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009112Jul 2020 → Jan 2022

Reason as filed by the promoterDue to Covid Lock down the project was not able to get completed on the above mentioned date and we were not able to provide possession to our Clint

EXT51800002529Jul 2020 → Jul 2020

Reason as filed by the promoterDue to approval from MCGM

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Dec 2022

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: form 4.pdf16 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VINIYOG FORM 4 .pdf9 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Viniyog.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.pdf27 Dec 2019
Building plan approvalFile: FINAL DRAWING_compressed.pdf15 Oct 2019
Building Plan Approval (IOD)File: FINAL DRAWING_compressed.pdf15 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: FINAL CC.pdf15 Oct 2019
Building plan approvalFile: Issue_letter 11082017.pdf18 Mar 2019
Building plan approvalFile: Amended issue letter 19032018.pdf18 Mar 2019
Building Plan Approval (IOD)File: Issue_letter 11082017.pdf18 Mar 2019
Building Plan Approval (IOD)File: Amended issue letter 19032018.pdf18 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: CC FOR 5TH AND 6TH PART.pdf18 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf18 Mar 2019
Certificates of CA (Form 5)File: form 5.pdf22 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: CC UP TO FORTH FLOOR VINIYOG.pdf16 Nov 2017
Building plan approvalFile: IOD LETTER VINIYOG.pdf31 Jul 2017
Layout approvalFile: approved plan.pdf31 Jul 2017
Copy of the legal title reportFile: legal title certificate_opt.pdf31 Jul 2017
Details of encumbrancesFile: encumbrance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: approved plan.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD LETTER VINIYOG.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC VINIYOG.pdf31 Jul 2017
Declaration in FORM BFile: under taking_opt.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect_opt.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rcc engineer.pdf31 Jul 2017
Certificates of CA (Form 3)File: c a certificate 1-4_opt.pdf31 Jul 2017
Certificates of CA (Form 3)File: c a certificate - 5-7_opt.pdf31 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER AND DRAFT OF SALE.pdf31 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
MANALI CO-OPERTIVE HOUSING SOCIETY LTDPLOT NO 8 L T NAGAR ROAD NO 1 M G CROSS ROAD GOREGAON WEST MUMBAI 40010421CompletedApr 2017Apr 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VINIYOG CHS LTD. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmVINIYOG CHS LTD.Completed 136Lapsed / revoked 71Abeyance 1Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 344 registered projects within 2 km.

Builder: VINAYAK DEVELOPERS

Vinayak Developers has 17 registrations on MahaRERA, including Durvankur Apartment and Jessika Chs.Ltd.. Its filings disclose 10 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VINIYOG CHS LTD. is delayed beyond 30 Jul 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VINIYOG CHS LTD.?

The registered promoter entity is VINAYAK DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VINIYOG CHS LTD.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VINIYOG CHS LTD.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VINIYOG CHS LTD.?

The professionals named in the filing: Architect: MR NANDKUMAR CHOGLE OF CHOGLE & ASSOCIATES; Engineer: Mr Haresh Laxmanbhai Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VINIYOG CHS LTD.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VINIYOG CHS LTD.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VINIYOG CHS LTD. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.