Home / Browse projects / Mumbai Suburban, Maharashtra / VINAYAK SHRADDHA TOWER

Registration lapsed No litigation declared Residential / Group Housing project

VINAYAK SHRADDHA TOWER

By K K KRISHNAN CONSTRUCTION COMPANY PVT LTD

RG-MH-10683 · RERA P51800003341 · Last updated on MahaRERA portal: 29 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 33 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
19 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

VINAYAK SHRADDHA TOWER is a Residential / Group Housing project by K K KRISHNAN CONSTRUCTION COMPANY PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003341 on 5 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 33 months from the original filing.

At a glance

Project

  • NameVINAYAK SHRADDHA TOWER
  • TypeResidential / Group Housing
  • Location
    • VIJAYNAGAR
    • BANDRA EAST
    • Andheri
    • Mumbai Suburban
    • 400051
  • Pincode400051
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003341
  • ReraGenie IDRG-MH-10683

Builder

  • NameK K KRISHNAN CONSTRUCTION COMPANY PVT LTD
  • Entity typeCompany
  • CINU70101MH1984PTC031742
  • GSTIN27AAACK2885L2Z3
  • ChairpersonsSHEEJA SURESH KRISHNAN, SULOCHANA KRISHNAN
  • Managing DirectorSURESH KRISHNAN
  • Other registrations3 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseMar 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2023)
  • Buildings3 building records
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INDIRAKRUPANA150000
VINAYAK SHRADDHA TOWERNA170000
MUNICIPAL PRIMARY SCHOOLNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 29 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

INDIRAKRUPA91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
VINAYAK SHRADDHA TOWER85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
MUNICIPAL PRIMARY SCHOOL47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered37
BuildingClosed/CoveredTotal
VINAYAK SHRADDHA TOWER3636
MUNICIPAL PRIMARY SCHOOL11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,845 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Mr. ANIL MEGHRAJ WADHAREAndheriMumbai Suburban

Approvals and building plan

Permissible FSI7346.7
Proposed, not sanctioned6,327 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR SAMARTHA VIDYALAYA OPP CST ROAD PETROL PUMP KALINA SANTACRUZ -EAST MUMBAI-400098

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
K K KRISHNAN CONSTRUCTION COMPANY PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800015267Mar 2023 → Dec 2024

Reason as filed by the promoterIt is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we were negotiating with several financial institutions and inventors. From which, we have introduced an investor as a co-promoter and resumed the construction activity in full threshold recently. We have received consent from existing allottees and seeking extension to complete the construction with complete willingness. Kindly grant us the extension

EXT51800025923Mar 2023 → Dec 2025

Reason as filed by the promoterWe faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab and new buyers are aware of the situation and they are supporting us to complete the construction hence given consent for extension. With new co-promoter, we are settling the funding issue and hoping to complete the work in coming months.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FOR VST.pdf29 Jul 2025
Disclosure of sold/ booked inventoryFile: VST Sold and Unsold As On 30 June 2025.pdf29 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_2024.pdf29 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 23-24 VST.pdf29 Jul 2025
Certificates of CA (Form 3)File: Form-3_Mar25_compressed.pdf24 Jul 2025
Certificates of CA (Form 3)File: Form-3_Jun25_compressed.pdf24 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form-5_Mar25.pdf24 Jul 2025
Certificates of CA (Form 3)File: Form3_31Dec24.pdf26 Jun 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure Dec24.pdf26 Jun 2025
Declaration in FORM BFile: Form-B.pdf27 Dec 2024
Declaration in FORM BFile: Form-B Co-promoter.pdf27 Dec 2024
Certificates of CA (Form 3)File: Form3 Dec.pdf27 Dec 2024
Other - TechnicalFile: Pert Chart.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A VST.pdf27 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 VST.pdf22 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 VST.pdf22 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 VST.pdf22 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf22 Feb 2024
Certificates of CA (Form 3)File: VST Form-3.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other projects _ KK Krishnan.pdf1 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold flats in Vinayak Complex.pdf31 Mar 2023
Certificates of CA (Form 3)File: Form-03_Vinayak Complex _KKKrishnan_17March2023 BY G C PATEL.pdf31 Mar 2023
Certificates of CA (Form 3)File: Form-03_Vinayak Complex _Shraddha_17March2023 BY G C PATEL.pdf31 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-2019 of Vinayak complex.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019 to 2020 of Vinayak Complex.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021 of Vinayak Complex.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022 of Vinayak Complex.pdf31 Mar 2023
Details of encumbrances concerned to FinanceFile: Declaration of No Encumbrances to Legal _Vinayak Complex.pdf5 Mar 2023
Details of encumbrances concerned to LegalFile: Declaration of No Encumbrances to Legal _Vinayak Complex.pdf5 Mar 2023
Declaration about Commencement CertificateFile: Form D Declaration about CC of Vinayak Complex.pdf5 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect's Certificate Vinayak Complex.pdf5 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer Certiifcate for Vinayak Complex_2022.pdf5 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_2023_Quality Assurance.pdf5 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_2023_Quality Assurance.pdf5 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_2023_Quality Assurance.pdf5 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report Vinayak Tower.pdf5 Mar 2023
Proforma of Agreement for saleFile: RERA SALE AGREEMENT - Vinayak Complex.pdf5 Mar 2023
Proforma of Allotment letterFile: Proforma of allotment letter.pdf5 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with Allotment letter in respect of Vinayak Complex.pdf5 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with Agreement for sale Vinayak Complex.pdf5 Mar 2023
Details of Restarting of Construction work post lockdownFile: vinayaka tower final ammended signed.pdf4 Sep 2021
Details of Restarting of Construction work post lockdownFile: VINAYAK TOWER SIGNED PLAN.pdf4 Sep 2021
OtherFile: MCHI PDF RESIZER.pdf12 Nov 2019
OtherFile: MCHI PDF RESIZER.pdf12 Nov 2019
OtherFile: MCHI PDF RESIZER.pdf12 Nov 2019
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 all rera.pdf26 Aug 2019
Status of ConveyanceFile: LOI pg 1PDF.pdf26 Aug 2019
Status of ConveyanceFile: LOI pg 2-PDF.pdf26 Aug 2019
OtherFile: 1ST FLOOR (1).pdf3 Aug 2019
OtherFile: 2ND FLOOR.pdf3 Aug 2019
OtherFile: 3RD TO 7TH FLOOR.pdf3 Aug 2019
OtherFile: 8TH FLOOR plan.pdf3 Aug 2019
OtherFile: 9TH 13TH 15 TH 16TH.pdf3 Aug 2019
OtherFile: 14TH FLOOR PLAN.pdf3 Aug 2019
OtherFile: 14TH FLOOR PLAN.pdf3 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 02 VINAYAK 26 10 2017 July to Sept.pdf29 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 02 SCHOOL 26 10 2017 July to Sept 17.pdf29 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf28 Jul 2017
Certificates of CA (Form 3)File: C A Certificatev.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certifcate Vinayak Complex.pdf27 Jul 2017
Building plan approvalFile: IOA 1 MB.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOA 1 MB.pdf25 Jul 2017
OtherFile: Municipal approval School Vinayak Complex.pdf25 Jul 2017
Layout approvalFile: indrakrupa layout.pdf24 Jul 2017
Details of encumbrancesFile: Non encumbrance certificate PDF.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: indrakrupa layout.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc MERGE.pdf24 Jul 2017
Proforma of Allotment letterFile: Allottment Letter and Agreement for sale merge.pdf24 Jul 2017
PAN CardFile: pan card.pdf19 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf19 Jul 2017
Declaration in FORM BFile: fORM B.pdf19 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Aksh DarshanMumbai 40009855CompletedJun 2017Jun 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 33 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VINAYAK SHRADDHA TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANDRA EAST6,700+ in Mumbai Suburban

2 kmVINAYAK SHRADDHA TOWERCompleted 32Lapsed / revoked 18Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: K K KRISHNAN CONSTRUCTION COMPANY PVT LTD

K K KRISHNAN CONSTRUCTION COMPANY PVT LTD has 4 registrations on MahaRERA, including VINAYAK SHRADDHA TOWER and MONIZ SHRADDHA HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VINAYAK SHRADDHA TOWER shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VINAYAK SHRADDHA TOWER is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VINAYAK SHRADDHA TOWER?

The registered promoter entity is K K KRISHNAN CONSTRUCTION COMPANY PVT LTD, a company as per the filing. Its CIN U70101MH1984PTC031742 and GSTIN 27AAACK2885L2Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VINAYAK SHRADDHA TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VINAYAK SHRADDHA TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in VINAYAK SHRADDHA TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VINAYAK SHRADDHA TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VINAYAK SHRADDHA TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.