ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Sahakar excel Acropolis - I

Registered No litigation declared Residential / Group Housing project

Sahakar excel Acropolis - I

By EXCEL ENTERPRISES REALTY LLP

RG-MH-17996 · RERA P51800077177 · Last updated on MahaRERA portal: 6 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Staircases, 60%
160 of 180Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

Sahakar excel Acropolis - I is a Residential / Group Housing project by EXCEL ENTERPRISES REALTY LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077177 on 29 Jul 2024. Possession is promised by 31 Mar 2028. 20 of the 180 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSahakar excel Acropolis - I
  • TypeResidential / Group Housing
  • Location
    • KHER NAGAR
    • BANDRA EAST
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400051
  • Pincode400051
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800077177
  • ReraGenie IDRG-MH-17996

Builder

  • NameEXCEL ENTERPRISES REALTY LLP
  • Entity typePartnership
  • PartnersVIJAYKUMAR PODDAR, KISHOR AGARWAL, VIRENDRA VORA, NEMIN VORA
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2024PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2024
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed71 files

Current status

11%20 of 180 units booked
35.4%Work done, per cost certificate

Figures as on 6 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sahakar Excel Acropolis- INA24161800180

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 60%.

Sahakar Excel Acropolis- I: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,924 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
KHER NAGARSHANTI BHAVAN CHSLBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMGCM
Permissible FSI12681.0
Proposed, not sanctioned8,426 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB-10, Gopi chambers, new link road, andheri west, 400053
Estimated costRs 91.96 cr
Cost incurredRs 32.59 cr
Work done35.43%
BuildingWingEstimatedIncurred
Sahakar Excel Acropolis- INARs 82.77 crRs 32.59 cr
-NARs 9.20 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectELLORA PROJECT CONSULTANT PVT LTD
EngineerVINAYAK CHOPDEKAR
EngineerAditya Dinesh Mehta
Chartered AccountantINANI & ASSOCIATES
Chartered AccountantRahul Sukwal
PartnerRole in project
EXCEL ENTERPRISES REALTY LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 May 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form -5 Sahakar Excel Acropolis - I.pdf6 Jun 2026
Commencement certificateFile: BLDG NO 19 CC UP TO 12TH FLOOR.pdf13 May 2026
Withdrawal Update Form 1File: Form - 1 Architect Cert Acropolis - I Sign.pdf13 May 2026
Withdrawal Update Form 2File: Form - 2 Eng Cert Acropolis - I.pdf13 May 2026
Withdrawal Update Form 3File: Form - 3 Acropolis - I Q-4_Signed.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 Architect Cert Q3 FY 25-26.pdf17 Mar 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q3 FY 25-26.pdf17 Mar 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Q3 FY 25-26_Compress..pdf17 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Cert Q- I.pdf15 Dec 2025
Withdrawal Update Form 1File: Form 1 Architect Cert Q- II.pdf15 Dec 2025
Withdrawal Update Form 2File: Form 2 Excel Bdlg 19 Eng Cert Q-1 25-26.pdf15 Dec 2025
Withdrawal Update Form 2File: Form 2 Excel Bdlg 19. Eng Cert Q-2 25-26..pdf15 Dec 2025
Withdrawal Update Form 3File: Form-3 Final _CA Certificate Q-I_Signed.pdf15 Dec 2025
Withdrawal Update Form 3File: Form 3 Final_CA Certificate Q-II_Signed.pdf15 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Excel Ent FY 24 25_Final.pdf1 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate - Excel Enterprises_Q4_Updated Certificate as per Estimated Cost_Signed.pdf4 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Cert - QIV.pdf21 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - Q-IV.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Q3.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Cert Q-III.pdf9 May 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format-A_Signed.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q-II Excel Enterprises.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Bldg Q-3_Signed.pdf24 Apr 2025
Layout approvalFile: Amend IOA drawing - 1-3.pdf29 Mar 2025
Building plan approvalFile: Amend IOA.pdf29 Mar 2025
Building plan approvalFile: Amend IOA drawing - 1-3.pdf29 Mar 2025
Building plan approvalFile: Amend IOA drawing 4-6.pdf29 Mar 2025
Building plan approvalFile: Amend IOA drawing 4-6.pdf29 Mar 2025
Copy of Layout Approval (in case of layout)File: Amend IOA drawing - 1-3.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amend IOA.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amend IOA drawing - 1-3.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amend IOA drawing 4-6.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amend IOA drawing 4-6.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Excel Enterprises Q-II_signed - converted.pdf11 Jan 2025
Declaration about Commencement CertificateFile: DocScanner 19 Jul 2024 8-09 pm.pdf19 Jul 2024
Declaration in FORM BFile: Dev form b.pdf3 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca final 1_merged.pdf3 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DocScanner 2 Jul 2024 6-30 pm.pdf2 Jul 2024
Other - TechnicalFile: DocScanner Jun 25, 2024 14-30.pdf25 Jun 2024
Other - LegalFile: 1.pdf24 Jun 2024
Other - LegalFile: 2.pdf24 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Rera Account (1).pdf12 Jun 2024
Copy of the legal title reportFile: DocScanner 6 Jun 2024 1-09 pm.pdf6 Jun 2024
Details of encumbrances concerned to FinanceFile: Annexure - A (2).pdf6 Jun 2024
Details of encumbrances concerned to FinanceFile: DocScanner 6 Jun 2024 1-19 pm.pdf6 Jun 2024
Details of encumbrances concerned to LegalFile: Annexure - A (2).pdf6 Jun 2024
Details of encumbrances concerned to LegalFile: DocScanner 6 Jun 2024 1-19 pm.pdf6 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: downloaded_file_240508_191316 (1).pdf6 Jun 2024
CERSAI detailsFile: Declaration about CERSAI Report (3).pdf6 Jun 2024
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf6 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Sheet - Agreement for Sale.pdf6 Jun 2024
CERSAI detailsFile: CERSAI_Search_Report_200305729469_For_Asset_Based_Search_04_05_2024_00_14_12_419.pdf3 May 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER DRAFT (3).pdf3 May 2024
Proforma of Agreement for saleFile: Model_AFS_in_English (8).pdf3 May 2024
Layout approvalFile: BLDG NO 19 LAYOUT PLAN.pdf23 Mar 2024
Copy of Layout Approval (in case of layout)File: BLDG NO 19 LAYOUT PLAN.pdf23 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-1-8.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-9.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-10.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-11_compressed.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-12_compressed.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-13_compressed.pdf19 Mar 2024
Building plan approvalFile: Login_A4_merged_compressed-14.pdf19 Mar 2024
PAN CardFile: PAN CARD Excel LLP.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-1-8.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-9.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-10.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-11_compressed.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-12_compressed.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-13_compressed.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Login_A4_merged_compressed-14.pdf19 Mar 2024

How this compares with Mumbai Suburban

11%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sahakar excel Acropolis - I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANDRA EAST6,700+ in Mumbai Suburban

2 kmSahakar excel Acropolis Completed 90Lapsed / revoked 45Other 97Dot size: filed unitsN

Filed coordinates, straight-line distance. 232 registered projects within 2 km.

Builder: EXCEL ENTERPRISES REALTY LLP

EXCEL ENTERPRISES REALTY LLP has 2 registrations on MahaRERA, including Sahakar excel Acropolis - I and Sahakar Excel Acropolis - II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sahakar excel Acropolis - I is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sahakar excel Acropolis - I?

The registered promoter entity is EXCEL ENTERPRISES REALTY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sahakar excel Acropolis - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sahakar excel Acropolis - I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sahakar excel Acropolis - I?

The professionals named in the filing: Architect: ELLORA PROJECT CONSULTANT PVT LTD; Engineer: VINAYAK CHOPDEKAR; Engineer: Aditya Dinesh Mehta; Chartered Accountant: INANI & ASSOCIATES; Chartered Accountant: Rahul Sukwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sahakar excel Acropolis - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sahakar excel Acropolis - I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sahakar excel Acropolis - I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.