Home / Browse projects / Mumbai Suburban, Maharashtra / VIKAS PALAZZO

Registered No litigation declared Others project

VIKAS PALAZZO

By DURATECH

RG-MH-01710 · RERA P51800001960 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 90 months
  • 6 extensions taken
  • Rs 10.00 crore secured on the land, in favour of KOTAK MAHINDRA INVESTMENTS LTD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2027Possession promisedmoved 90 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
11 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 153 documents Report an error

VIKAS PALAZZO is a Others project by DURATECH in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001960 on 31 Jul 2017. Possession is promised by 30 Nov 2027. The completion date has moved by 90 months from the original filing. 45 of the 56 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameVIKAS PALAZZO
  • TypeOthers
  • Location
    • Walji Ladha Road
    • Mulund West
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001960
  • ReraGenie IDRG-MH-01710

Builder

  • NameDURATECH
  • Entity typePartnership
  • PartnersROHIT VALLABHJI GADA, KETAN VALLABHJI GADA, VALLABHJI BHANJI GADA
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2017First promiseMay 2020Revised toNov 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2017
  • Promised completion30 Nov 2027
  • Revised completionRevised to 30 Nov 2027 (originally 31 May 2020)
  • Buildings1 building record
  • Documents filed153 files

Current status

80%45 of 56 units booked
86.0%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIKAS PALAZZONA434353356

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

VIKAS PALAZZO: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed152

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots152
Closed/Covered152

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,111 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofKOTAK MAHINDRA INVESTMENTS LTD
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on1 Oct 2024

Approvals and building plan

Sanctioning authorityMunicipal corporation of greater mumbai
Permissible FSI14280.0
Proposed, not sanctioned14,280 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMARATHON MAX JUNCTION OF LBS ROAD AND MULUND GOREGAON LINK ROAD MULUND WEST MUMBAI 400080
Estimated costRs 102.00 cr
Cost incurredRs 87.73 cr
Work done86.01%
BuildingWingEstimatedIncurred
VIKAS PALAZZONARs 70.00 crRs 69.11 cr
-NARs 32.00 crRs 18.62 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU KHUBI
ArchitectSHRADDHA JOSHI
EngineerJ J REALIS
EngineerKaushik Shantilal Shah
Chartered AccountantUmang Dedhia & Co. dedhia
Chartered AccountantPRAVIN SHAH AND ASSOCIATES
Chartered AccountantVUDN AND ASSOCIATES LLP
PartnerRole in project
DURATECH-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011853May 2020 → May 2023

Reason as filed by the promoterWe have received part Occupation Certificates till 38th floor and further to complete the internal unfinished work for 39th and 40th floor we request for extension for the said project for one year i.e 30/05/2023.

EXT51800005512May 2020 → May 2021

Reason as filed by the promoterDue to DCPR 2034, there is availability of additional FSI of 1685.53 sq. mtrs. and as a result of which now total proposed FSI will be increased from 12,593.48 sq. mtrs. to 14,279.01 sq. mtrs. (i.e. additional 1685.53 sq. mtrs.).

EXT51800017842May 2020 → Nov 2024

Reason as filed by the promoterWe have received OC till 38 th floor and we are in process of obtaining the full oc up to 40 floor till that time we request you grant the extension till 30.11.2024

EXT51800016483May 2020 → Nov 2023

Reason as filed by the promoterwe have completed the project as per architect certificate we have OC till 38th floor but we are in process of getting full OC , hence we require a extension for further 6 months. we have attached possession letters as annexures to the letter

EXT51800024941May 2020 → Nov 2025

Reason as filed by the promoterWe have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2025, we have attached the consent letter of all the allottees.

EA13112518322May 2020 → Nov 2027

Reason as filed by the promoterWe have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2027, we have attached the consent letter of 80%of the allottees.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Mar 2022

Documents filed153

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Vikas Palazzo Architect Certificate.pdf22 Jul 2026
Withdrawal Update Form 1File: Vikas Palazzo Architect Certificate.pdf22 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate Q3 Vikas palazzo.pdf22 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3 - Q3.pdf22 Jul 2026
Withdrawal Update Form 3File: Vikas Palazzo_Form 3_FY 25-26_Q4.pdf22 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25 .pdf13 Nov 2025
Form 5 (FY 2024-2025)File: Form 5.pdf13 Nov 2025
Form 2File: Engineer Certificate MArch 2025.pdf12 Nov 2025
Form 3File: Form 3 RERA March 2025.pdf12 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory MArch 2025.pdf12 Nov 2025
Form 1File: Vikas Palazzo Architect Certificate.pdf12 Nov 2025
Form 1File: Vikas Palazzo Architect Certificate.pdf12 Nov 2025
Form 2File: Engineer Certificate June 2025.pdf12 Nov 2025
Form 3File: Form 3 RERA June 2025.pdf12 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory june 2025.pdf12 Nov 2025
Form 2File: Engineer Certificate Sept 2025.pdf12 Nov 2025
Form 3File: Form 3 RERA Sep 2025.pdf12 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory sept 2025.pdf12 Nov 2025
Form 1File: Vikas Palazzo Architect Certificate.pdf12 Nov 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Mar24.pdf5 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_June24.pdf5 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Sept24.pdf5 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclouser of Inventory 1.pdf5 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf5 Nov 2024
Declaration in FORM BFile: Form B.pdf31 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GetUserDocumentFileContent (1).pdf31 Oct 2024
Certificates of CA (Form 3)File: Form 3 - Q4 - Final - Signed.pdf31 Oct 2024
Certificates of CA (Form 3)File: Form 3 - Q1 Signed.pdf31 Oct 2024
Certificates of CA (Form 3)File: Form 3 - Q2 Signed.pdf31 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Mar24.pdf31 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_June24.pdf31 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Sept24.pdf31 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclouser of Inventory.pdf31 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A -Duratech.pdf31 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf1 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf1 Feb 2024
Certificates of CA (Form 3)File: FORM - 3 CA CERTIFICATE OF DURA TECH - DEC'23 (2)_compressed.pdf1 Feb 2024
Details of encumbrancesFile: MORTGAGE DEED.pdf25 Oct 2023
Details of encumbrancesFile: Mortgage Deed vp.pdf25 Oct 2023
Declaration in FORM BFile: FORM B.pdf25 Oct 2023
Declaration in FORM BFile: Form_B.pdf25 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vikas Palazzo Architect Certificate.pdf25 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vikas Palazzo Engineer Certificate- September 2023.pdf25 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf25 Oct 2023
Certificates of CA (Form 3)File: CA_CERTIFICATE.pdf25 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Dura Tech Form 5.pdf25 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Dura Tech Form 5.pdf18 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vikas Palazzo Architect Certificate.pdf13 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vikas Palazzo- Engineer Certificate- June 2023.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GetUserDocumentFileContent.pdf13 Oct 2023
Certificates of CA (Form 3)File: CA Certificate_compressed.pdf13 Oct 2023
Certificates of CA (Form 3)File: fORM 3 Q4.pdf26 Jun 2023
Layout approvalFile: lATEST APPROVED PLANS.pdf9 May 2023
Copy of Layout Approval (in case of layout)File: lATEST APPROVED PLANS.pdf9 May 2023
Declaration in FORM BFile: FORM B.pdf9 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf9 May 2023
Disclosure of sold/ booked inventoryFile: DISCLOUSER OF INVENTORY.pdf9 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate Q1.pdf28 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate Q2.pdf28 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate Q3.pdf28 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vikas Palazzo Architect Certificate- 31st Mar 2023.pdf28 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Q1.pdf28 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Q2.pdf28 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Q3.pdf28 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vikas Palazzo Engineer Certificate- 31st Mar 2023.pdf28 Apr 2023
Certificates of CA (Form 3)File: Form 3 Q1.pdf28 Apr 2023
Certificates of CA (Form 3)File: Form 3 Q2.pdf28 Apr 2023
Certificates of CA (Form 3)File: Form 3 Q3.pdf28 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Dura Form 5 NEW FORMATE.pdf27 Oct 2022
Details of encumbrancesFile: doc00184320220609143253 (1)_compressed.pdf10 Jun 2022
Certificates of CA (Form 3)File: CA SCAN_compressed.pdf31 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate- Mar 2022.pdf20 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate.pdf20 May 2022
Disclosure of sold/ booked inventoryFile: 02_Disclosure of sold and unsold details and part oc.pdf13 May 2022
Disclosure of sold/ booked inventoryFile: 02_Disclosure of sold and unsold details and part oc.pdf13 May 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Partial OC.pdf8 Mar 2022
Certificates of CA (Form 3)File: CA Certificate Dec 21.pdf28 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: REVISED_Duratech- Vikas Pallazo- Engineer Certificate- March 2021.pdf25 Feb 2022

How this compares with Mumbai Suburban

80%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 90 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIKAS PALAZZO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West6,700+ in Mumbai Suburban

2 kmVIKAS PALAZZOCompleted 123Lapsed / revoked 99Other 149Dot size: filed unitsN

Filed coordinates, straight-line distance. 371 registered projects within 2 km.

Builder: DURATECH

DURATECH has 2 registrations on MahaRERA, including VIKAS PALAZZO and VIKAS RISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VIKAS PALAZZO is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIKAS PALAZZO?

The registered promoter entity is DURATECH, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIKAS PALAZZO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIKAS PALAZZO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIKAS PALAZZO?

The professionals named in the filing: Architect: VASTU KHUBI; Architect: SHRADDHA JOSHI; Engineer: J J REALIS; Engineer: Kaushik Shantilal Shah; Chartered Accountant: Umang Dedhia & Co. dedhia; Chartered Accountant: PRAVIN SHAH AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIKAS PALAZZO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIKAS PALAZZO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIKAS PALAZZO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.