Home / Browse projects / Raigarh, Maharashtra / VIJAY ESTATE VAKAS PHASE - 1

Registration lapsed No litigation declared Others project

VIJAY ESTATE VAKAS PHASE - 1

By VIJAYGROUP HOUSING PRIVATE LIMITED

RG-MH-09717 · RERA P52000000959 · Last updated on MahaRERA portal: 10 Nov 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 55 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
90 of 561Construction stages doneacross 51 buildings; furthest along: External plumbing and external plaster, 96%
55Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

VIJAY ESTATE VAKAS PHASE - 1 is a Others project by VIJAYGROUP HOUSING PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000000959 on 25 Jul 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. 55 complaints are on record with the regulator.

At a glance

Project

  • NameVIJAY ESTATE VAKAS PHASE - 1
  • TypeOthers
  • Location
    • Neral - Kashele Road
    • Village Vakas
    • Near Neral
    • Vakas
    • Karjat
    • Raigarh
    • 410101
  • Pincode410101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000000959
  • ReraGenie IDRG-MH-09717

Builder

  • NameVIJAYGROUP HOUSING PRIVATE LIMITED
  • Entity typeCompany

Key dates

28 months past promisethis monthRegisteredJul 2017PromisedJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Jul 2017
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings51 building records
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NE 24 BUILDING NO 1NA50000
NE 24 BUILDING NO 2NA50000
NE 24 BUILDING NO 3NA50000
NE 24 BUILDING NO 4NA50000
NE 24 BUILDING NO 5NA50000
NE 24 BUILDING NO 6NA50000
NE 24 BUILDING NO 7NA50000
NE 24 BUILDING NO 8NA50000
NE 24 BUILDING NO 9NA50000
NE 24 BUILDING NO 10NA50000
SE 05 BUILDING NO 1NA50000
SE 05 BUILDING NO 2NA50000
SE 05 BUILDING NO 3NA50000
SE 05 BUILDING NO 4NA50000
SE 05 BUILDING NO 5NA50000
SE 05 BUILDING NO 6NA50000
SE 05 BUILDING NO 7NA50000
SE 05 BUILDING NO 8NA50000
SE 25 BUILDING NO 1NA50000
SE 25 BUILDING NO 2NA50000
SE 25 BUILDING NO 3NA50000
SE 25 BUILDING NO 4NA50000
SE 25 BUILDING NO 5NA50000
SE 25 BUILDING NO 6NA50000
SE 26 BUILDING NO 1NA50000
SE 26 BUILDING NO 2NA50000
SE 26 BUILDING NO 3NA50000
SE 26 BUILDING NO 4NA50000
SE 26 BUILDING NO 5NA50000
SE 26 BUILDING NO 6NA50000
SE 26 BUILDING NO 7NA50000
SE 26 BUILDING NO 8NA50000
SE 27 BUILDING NO 1NA50000
SE 27 BUILDING NO 2NA50000
SE 27 BUILDING NO 3NA50000
SE 27 BUILDING NO 4NA50000
SE 27 BUILDING NO 5NA50000
SE 27 BUILDING NO 6NA50000
SE 27 BUILDING NO 7NA50000
SE 27 BUILDING NO 8NA50000
SE 27 BUILDING NO 9NA50000
SE 27 BUILDING NO 10NA50000
SE 27 BUILDING NO 11NA50000
SE 04 BUILDING NO 1NA50000
SE 04 BUILDING NO 2NA50000
SE 04 BUILDING NO 3NA50000
SE 04 BUILDING NO 4NA50000
SE 04 BUILDING NO 5NA50000
SE 04 BUILDING NO 6NA50000
SE 04 BUILDING NO 7NA50000
SE 04 BUILDING NO 8NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 10 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 51 buildings; the table lists the first 20.

90 of 561 construction stages are filed complete across 51 buildings. The stage furthest along is External plumbing and external plaster, at 96%.

NE 24 BUILDING NO 162%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises59%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks84%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
NE 24 BUILDING NO 262%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises59%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.92%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%
NE 24 BUILDING NO 363%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 464%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises67%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.8%
NE 24 BUILDING NO 564%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 663%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.93%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 759%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises51%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.78%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 863%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 963%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NE 24 BUILDING NO 1062%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 156%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.58%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 258%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises43%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 359%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.79%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 454%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises36%
Sanitary Fittings within the flats / premises46%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 550%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises32%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.28%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 663%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 759%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises46%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.78%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 05 BUILDING NO 854%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 25 BUILDING NO 138%
ActivityProgress
Excavation100%
Basement (if any)92%
Podiums (if any)0%
Plinth92%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks17%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.17%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SE 25 BUILDING NO 233%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 10 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes2%
Water SupplyYes1%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes23%
Storm Water DrainsYes3%
Landscaping & Tree PlantingYes6%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes8%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Landscape Garden with Jogging track, Gazebo for Senior citizen corner & basic kids play equipment seYes0%
SOCIETY OFFICEYes25%

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered2
Open Space63
BuildingClosed/CoveredOpen SpaceTotal
NE 24 BUILDING NO 1011
NE 24 BUILDING NO 2022
NE 24 BUILDING NO 3022
NE 24 BUILDING NO 401010
NE 24 BUILDING NO 5123
NE 24 BUILDING NO 6022
NE 24 BUILDING NO 7022
NE 24 BUILDING NO 8022
SE 05 BUILDING NO 1044
SE 05 BUILDING NO 8044
SE 25 BUILDING NO 1055
SE 25 BUILDING NO 5022
SE 25 BUILDING NO 6134
SE 26 BUILDING NO 1066
SE 26 BUILDING NO 5022
SE 26 BUILDING NO 6022
SE 26 BUILDING NO 7022
SE 26 BUILDING NO 8011
SE 04 BUILDING NO 1044
SE 04 BUILDING NO 5022
SE 04 BUILDING NO 6011
SE 04 BUILDING NO 7011
SE 04 BUILDING NO 8011

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,167 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI73537.0
Proposed, not sanctioned72,492 sq m
Buildings approved51
Buildings sanctioned51

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURAJ HOUSE SHOP NO 1 AND 2 GR FLOOR PATLIPADA GHODBUNDER ROAD THANE MAHARASHTRA 400607

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s. Ajay Wade & Associates
ArchitectM/s. Dimensions Architects Pvt Ltd
EngineerM/s. Epicons Consultant Pvt. Ltd.
PartnerRole in project
VIJAYGROUP HOUSING PRIVATE LIMITED-

Litigation declared5

CaseCourtStatus
114/2016Sub Divisional Officer KarjatPENDING
OA/460/2020/2020DEBTS RECOVERY TRIBUNAL DELHIPENDING
CP IB NO 274 OF 2022/2022NCLT MUMBAIPENDING
CP IB NO 384 OF 2022/2022NCLT MUMBAIPENDING
CP IB NO 759 MB OF 2022/2022NCLT MUMBAIPENDING

Complaints filed with MahaRERA55

Case no.ComplainantRespondentFiled
CC006000000196094Mrs.Manasi Mahesh Anjarlekar and Mr.Darshan Mahesh Anjarlekar1.M/s.Vijaygroup Housing Pvt Ltd. 2.Mr.Ateev Vrajlal Gala 3.Mr.Vipul Jain02/03/2021
CC006000000195303Ananth RangarajanVijaygroup Housing Pvt Ltd22/12/2020
CC006000000110703sumit Kumar ThakurVijay Group Housing pvt ltd26/08/2019
CC006000000110780Bhavana SharmaVijay Group Housing Private Limited02/09/2019
CC006000000110855Pratiksha DeorukhkarVijay Group Housing Pvt. Ltd.14/09/2019
CC006000000141102Newman CreadoVijay Group01/10/2019
CC006000000192894YOGIRAJ MOHAN GAIKWADVijay Group Housing Pvt. Ltd21/09/2020
CC006000000210260Deepak Laxmichand FuriaVijayGroup Housing Pvt Ltd04/03/2022
CC006000000195428Bejoya Bijon TalukderVijaygroup Housing Private Limited29/12/2020
CC006000000195453Sundeep Mohan Naik and Samruddhi Sundeep NaikVijaygroup Housing Private Limited30/12/2020
CC006000000195459Ramakrishnan Narayanan Iyer and Uma N. IyerVijaygroup Housing Private Limited31/12/2020
CC006000000195495Charlotte PereiraVijaygroup Housing Private Limited02/01/2021
CC006000000195758Anant Madhav JoshiVijaygroup Housing Private Limited27/01/2021
CC006000000195997Rajal H ThakkarVijaygroup Housing Private Limited12/02/2021
CC006000000196092Niraj Kishore SawlaniVijaygroup Housing Private Limited19/02/2021
CC006000000196245Girish Ashokrao NaikVijaygroup Housing Private Limited04/03/2021
CC006000000196247Pranit Anil DereVijaygroup Housing Private Limited04/03/2021
CC006000000196978Parameshwar K. V.Vijaygroup Housing Private Limited24/05/2021
CC006000000197067Appikatla Veera Venkata Durga SyamVijaygroup Housing Private Limited24/05/2021
CC006000000197391Rekha JadhavVijaygroup Housing Private Limited25/06/2021
CC006000000192713susanta ranaateev gala21/02/2020
CC006000000193035Chandrakant Vinayak DandekarVijay Group Housing Pvt. Ltd.17/03/2020
CC006000000194202Shailesh Suryakant PowaleVijay Group Housing Pvt Ltd02/10/2020
CC006000000194733DILIP GAJANAN PARDESHIVijay Group Housing Private Ltd.30/10/2020
CC006000000195631apurva pednekarVIJAY GROUP HOUSING PVT LTD29/01/2021
CC006000000197290apurva pednekarVIJAY GROUP HOUSING PVT LTD18/06/2021
CC006000000195861Mrs. Kanchan Kishore Bal & Mr. Kishor Maruti BalVIJAYGROUP HOUSING PRIVATE LIMITED02/02/2021
CC006000000196030Delay possesionAteev gala18/04/2021
CC006000000196281Tejas Sunil SalianVijay Group Housing Pvt. Ltd.23/03/2021
CC006000000197772TEJAS SALIAN & NEETA SUNIL SALAINVIJAY ESTATE (VAKAS)04/08/2021
CC006000000196576Sujata Suryanarayan Sastri VedulaVijay Group Housing Pvt Ltd05/04/2021
CC006000000196653Dilip Ambadas LonkarVijay Group Housing Pvt Ltd09/04/2021
CC006000000196693Amit Mahadev ModakVijay Group Housing Pvt Ltd12/04/2021
CC006000000196713Anuradha SalviVijayGroup Housing Pvt Ltd15/04/2021
CC006000000196715Umesh KambleVijay Group HousingPvt Ltd15/04/2021
CC006000000196716Rahul SuryawanshiVijay GroupPvt LtdHousing15/04/2021
CC006000000196724Mr Kush Kumar Karoda Mrs Swati GuptaVijay Group Housing Pvt Ltd16/04/2021
CC006000000196765Madhura Milind Gaikwad and Milind Shivaji GaikwadVijay Group Housing Pvt Ltd20/04/2021
CC006000000196803Sundip CharmodeVijay Group Housing Pvt Ltd27/04/2021
CC006000000196804Mrs. Jagruti Shailesh Upadhyaya and Mr. Shailesh Prataprai UpadhyayaVijay Group Housing Pvt Ltd06/05/2021
CC006000000197783MRUTYUNJAY NAGRALDEEPAK LAXMICHAND FURIA 2) ANIL ATMARAM PANCHAL27/07/2021
CC006000000198316GIRISH VENGURLEKARVIJAY GROUP HOUSING PVT LTD16/09/2021
CC006000000198888Bheem SinghVIJAY GROUP HOUSING PVT LTD30/10/2021
CC006000000210261Kalpana Deepak FuriaVijayGroup Housing Pvt Ltd04/03/2022
CC006000000210263Forum Meet PoladiaVijayGroup Housing Pvt Ltd04/03/2022
CC006000000210262Disha Deepak FuriaVijayGroup Housing Pvt Ltd04/03/2022
CC006000000220588Vijay DalviAteev Gala(Vijay Group)29/03/2022
CC006000000220948SAKSHI AKHIL AGARWALVIJAY GROUP HOUSING PVT LTD24/04/2022
CC006000000220963Pradnya Sandeep NikamVijaygroup Housing Private Limited26/04/2022
CC006000000282181Prakash Ramchandra ManeM/s Vijay Group Housing Private Limited05/08/2022
CC006000000282199Pravin Jugalkishore AgarwalVijay Group Housing Pvt Ltd20/09/2022
CC006000000303047Pranab YadavVijay Group Housing Private Limited14/10/2022
CC006000000303141Adarsh Kumar SrivastavaVijaygroup Housing Private Limited23/10/2022
CC006000000333841Nikita ShahVijaygroup Housing Private Limited03/01/2023
CC006000000375050MAHIPAL BHOORMAL MEHTAVIJAY GROUP HOUSING PVT LTD04/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: DIR 12.pdf10 Nov 2021
OtherFile: DLF Resignation.pdf10 Nov 2021
OtherFile: BR DLF Resignation.pdf10 Nov 2021
Certificates of CA (Form 5)File: Form 5_VEV.pdf28 Nov 2018
Proforma of Allotment letterFile: Vakas Agreement for Commercial Units.pdf20 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1_VEV (2).pdf16 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2_VEV.pdf16 Oct 2017
Certificates of CA (Form 3)File: Vakas Form 3.pdf16 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 - Engineer Certificate Vakas.pdf22 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf22 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf22 Jul 2017
Proforma of Allotment letterFile: Flat Sale Agreement.pdf22 Jul 2017
Building plan approvalFile: NA ORDER- Revised_Dt- 10-04-2017.pdf21 Jul 2017
Layout approvalFile: NA ORDER- Revised_Dt- 10-04-2017.pdf21 Jul 2017
PAN CardFile: Pan card_VGHPL.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part I.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part II.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part III.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part IV.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part V.pdf21 Jul 2017
Copy of the legal title reportFile: Phoenix Title-Part VI.pdf21 Jul 2017
Details of encumbrancesFile: Self Declaration-VGHPL.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: NA ORDER- Revised_Dt- 10-04-2017.pdf21 Jul 2017
Building Plan Approval (IOD)File: NA ORDER- Revised_Dt- 10-04-2017.pdf21 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER- Revised_Dt- 10-04-2017.pdf21 Jul 2017
Declaration in FORM BFile: Vakas_Form B_Declaration.pdf21 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vakas_Form_1_Architect Certificate.pdf21 Jul 2017
OtherFile: Disclosure Statement.pdf21 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIJAY ESTATE VAKAS PHASE - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Vakas, Near Neral5,900+ in Raigarh

2 kmVIJAY ESTATE VAKAS PHASECompleted 2Lapsed / revoked 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: VIJAYGROUP HOUSING PRIVATE LIMITED

VIJAYGROUP HOUSING PRIVATE LIMITED has 1 registration on MahaRERA, including VIJAY ESTATE VAKAS PHASE - 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that VIJAY ESTATE VAKAS PHASE - 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VIJAY ESTATE VAKAS PHASE - 1 is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIJAY ESTATE VAKAS PHASE - 1?

The registered promoter entity is VIJAYGROUP HOUSING PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIJAY ESTATE VAKAS PHASE - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VIJAY ESTATE VAKAS PHASE - 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VIJAY ESTATE VAKAS PHASE - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIJAY ESTATE VAKAS PHASE - 1?

The professionals named in the filing: Architect: M/s. Ajay Wade & Associates; Architect: M/s. Dimensions Architects Pvt Ltd; Engineer: M/s. Epicons Consultant Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIJAY ESTATE VAKAS PHASE - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIJAY ESTATE VAKAS PHASE - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIJAY ESTATE VAKAS PHASE - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.