Home / Browse projects / Pune, Maharashtra / Vertical Oriana Phase IV

Registration lapsed No litigation declared Residential / Group Housing project

Vertical Oriana Phase IV

By Vertical Infra

RG-MH-14513 · RERA P52100022830 · Last updated on MahaRERA portal: 10 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 37 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2023Possession promised37 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

Vertical Oriana Phase IV is a Residential / Group Housing project by Vertical Infra in Pune, Maharashtra, registered with MahaRERA as P52100022830 on 30 Oct 2019. Possession was promised by 30 Sep 2023 and is now 37 months past that date. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameVertical Oriana Phase IV
  • TypeResidential / Group Housing
  • Location
    • Keshavnagar
    • Mundwa
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • RERA no.P52100022830
  • ReraGenie IDRG-MH-14513

Builder

  • NameVertical Infra
  • Entity typePartnership
  • PartnersJayesh Kundankumar Jain, Kumarpal Mohanlal Sanghvi, Manoj Premchand Rathod, Nilesh Bansilal Lunkad, Samir Rafiq Shaikh, Vikram Achaldas Palesha, Vipul Sardarmal Bagrecha, Mukesh Kesrimal Oswal, Hasmukh Kundanmal Parmar, Nirmala Dilip Jain, Chandan Hirachand Gandhi, Lazarus Francis Adhav and 1 more
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked

Key dates

37 months past promisethis monthRegisteredOct 2019First promiseMar 2023Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Oct 2019
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vertical Oriana Phase IVNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Vertical Oriana Phase IV: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities20

As on 10 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes82%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes75%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes90%
Gas BankYes0%
Lift InstallationYes0%
Garbage ChuteYes40%
Solar Water Heater SystemYes65%
Table Games Cards Chess Carrom EtcYes65%

Parking filed79

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots79
Closed/Covered64
Open Space15

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,631 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Krishna Lala PawarPune (M Corp.)Pune
Mangal Krishna PawarPune (M Corp.)Pune
Ambika Balkrishna MantriPune (M Corp.)Pune
Sunny Krishna PawarPune (M Corp.)Pune

Approvals and building plan

Permissible FSI7069.83
Proposed, not sanctioned6,418 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCOMMERCIAL BRANCH, TILAK ROAD, PUNE

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHemant Shantaram Mahajan
ArchitectDilip G Kale & Associates
EngineerSunil Muthalik& Associates
EngineerSaurabh Mantri
Chartered AccountantSheetal M Gadiya
PartnerRole in project
Vertical Infra-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016618Mar 2023 → Sep 2023

Reason as filed by the promoterPlease Grant us Extension upto 30/09/2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Digitally Signed Phase IV.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Q2 Phase 4 Signed.pdf29 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Q2 Phase 4x.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORYx.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_Q3_compressed.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_q3_compressed.pdf25 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 digitally signed.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q1_compressed.pdf18 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_q2_compressed.pdf18 Mar 2024
Declaration in FORM BFile: Form B Compressed.pdf7 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold compressed.pdf7 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 FY 2022-23.pdf22 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3 Q4.pdf20 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Q4.pdf20 May 2023
Disclosure of sold/ booked inventoryFile: Discloure of Sold Unsold 20052023.pdf20 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4.pdf20 May 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Phase IV.pdf12 Apr 2023
Details of encumbrances concerned to LegalFile: Encumbrance Phase IV.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 FY 21-22.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 FY 22-23.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 FY 22-23.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 FY 22-23.pdf12 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 FY 21-22.pdf12 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 FY 22-23.pdf12 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 FY 22-23.pdf12 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 FY 22-23.pdf12 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 FY 21-22_compressed.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 FY 22-23_compressed.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 FY 22-23_compressed.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 FY 22-23_compressed.pdf12 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 phase IV.pdf12 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf12 Apr 2023
Details of encumbrancesFile: Non Encumbrance Certificate.pdf8 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1.pdf3 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf3 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 Feb 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration association of allottee.pdf3 Feb 2022
Status of ConveyanceFile: Declaration Conveyance Deed.pdf3 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf20 Oct 2021
Details of encumbrancesFile: Encumbarance Certificate.pdf9 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf9 Oct 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration Association of Allottee.pdf9 Oct 2021
Status of ConveyanceFile: Declaration Conyenace deed.pdf9 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architecture Certificate.pdf9 Sep 2021
Details of encumbrancesFile: Encumrance Certificate.pdf8 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3- Vertical Oriana Phase IV.pdf8 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VI Phase IV Engineer Certificate.pdf8 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Vertical Oriana Phase IV.pdf8 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: status of association of allotee -iv.pdf8 Sep 2021
Status of ConveyanceFile: Status of conveyance deed- iv.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VI PHASE 4.pdf12 Apr 2021
Layout approvalFile: 1-17.pdf5 Feb 2021
Copy of Layout Approval (in case of layout)File: 1-17.pdf5 Feb 2021
Building plan approvalFile: 8-17.pdf23 Jan 2020
Building plan approvalFile: 9-17.pdf23 Jan 2020
Building plan approvalFile: 11-17.pdf23 Jan 2020
Building plan approvalFile: 12-17.pdf23 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 8-17.pdf23 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 9-17.pdf23 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 11-17.pdf23 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 12-17.pdf23 Jan 2020
Layout approvalFile: 1_compressed.pdf12 Oct 2019
Layout approvalFile: 2_compressed.pdf12 Oct 2019
Building plan approvalFile: plan 0002_compressed.pdf12 Oct 2019
Building plan approvalFile: plan 0003_compressed.pdf12 Oct 2019
Building plan approvalFile: plan 0004_compressed.pdf12 Oct 2019
PAN CardFile: VI Pan.pdf12 Oct 2019
Copy of the legal title reportFile: TITLE REPORT - 2018_compressed.pdf12 Oct 2019
Copy of the legal title reportFile: TITLE REPORT - 2019.pdf12 Oct 2019
Details of encumbrancesFile: Encumbrance Certificate.pdf12 Oct 2019
Copy of Layout Approval (in case of layout)File: 1_compressed.pdf12 Oct 2019
Copy of Layout Approval (in case of layout)File: 2_compressed.pdf12 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: plan 0002_compressed.pdf12 Oct 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vertical Oriana Phase IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mundwa13,700+ in Pune

Builder: Vertical Infra

Vertical Infra has 5 registrations on MahaRERA, including Vertical Oriana Phase I and Vertical Oriana Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vertical Oriana Phase IV shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vertical Oriana Phase IV is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vertical Oriana Phase IV?

The registered promoter entity is Vertical Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vertical Oriana Phase IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vertical Oriana Phase IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vertical Oriana Phase IV?

The professionals named in the filing: Architect: Hemant Shantaram Mahajan; Architect: Dilip G Kale & Associates; Engineer: Sunil Muthalik& Associates; Engineer: Saurabh Mantri; Chartered Accountant: Sheetal M Gadiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vertical Oriana Phase IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vertical Oriana Phase IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vertical Oriana Phase IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.