ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / VASTU SWAPNAPURTY RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

VASTU SWAPNAPURTY RESIDENCY

By VASTU BUILDERS AND DEVELOPERS

RG-MH-56654 · RERA P51700011170 · Last updated on MahaRERA portal: 23 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 26 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

VASTU SWAPNAPURTY RESIDENCY is a Residential / Group Housing project by VASTU BUILDERS AND DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700011170 on 31 Aug 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 26 months from the original filing.

At a glance

Project

  • NameVASTU SWAPNAPURTY RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • 0
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700011170
  • ReraGenie IDRG-MH-56654

Builder

  • NameVASTU BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersDAYARAM DHANIRAM RAJPUT, VAISHALI VINAY WALAVALKAR
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

13 months past promisethis monthRegisteredAug 2017First promiseJul 2023Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Jul 2023)
  • Buildings2 building records
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VASTU SWAPNAPURTY RESIDENCY D E FNA88000
VASTU SWAPNAPURTY RESIDENCY G WINGNA55000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

VASTU SWAPNAPURTY RESIDENCY D E F91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
VASTU SWAPNAPURTY RESIDENCY G WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Open Space14
BuildingOpen SpaceTotal
VASTU SWAPNAPURTY RESIDENCY D E F88
VASTU SWAPNAPURTY RESIDENCY G WING66

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,290 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Apr 2026

Approvals and building plan

Sanctioning authorityNITIN MHATRE
Permissible FSI8586.0
Proposed, not sanctioned8,586 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANDRA EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPACE ENGINEERS
EngineerATUL KUDTARKAR & ASSOCIATES
Chartered AccountantAmrrita Jagnaani
PartnerRole in project
VASTU BUILDERS AND DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017479Jul 2023 → Mar 2024

Reason as filed by the promoterProject due to Covid 19 , there was Multiple Lockdowns throughout the Year. There was Labour Shortage Problem as well due to Migration. Also Lockdowns led to Material Shortage Problem.so i request you to extention uoto 31/03/2024.

EXT51700024115Jul 2023 → Mar 2025

Reason as filed by the promoterFINANCIAL ISSUE

EXT51700028248Jul 2023 → Sep 2025

Reason as filed by the promoterWork not completed till now

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: architect June 2025.pdf23 Dec 2025
Form 2File: Engineer June 2025.pdf23 Dec 2025
Form 3File: CA CERTIFICATE_11zon.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf23 Dec 2025
Form 1File: Architect Sep 2025.pdf23 Dec 2025
Form 2File: Engineer Sep 2025.pdf23 Dec 2025
Form 3File: 30 9 25.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf23 Dec 2025
Form 1File: ARCHITECT.pdf6 Nov 2025
Form 2File: engineer oct dec 24.pdf6 Nov 2025
Form 3File: ca certificate 31 12 24.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Nov 2025
Form 1File: architect.pdf6 Nov 2025
Form 2File: ENGINEER.pdf6 Nov 2025
Form 3File: ca certificate 30 9 24.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Nov 2025
Form 1File: ARCHITECT.pdf6 Nov 2025
Form 2File: ENGINEER.pdf6 Nov 2025
Form 3File: certificate 31 3 24.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Nov 2025
Form 1File: Architect 31 3 25.pdf5 Nov 2025
Form 2File: Engineer 31 3 25.pdf5 Nov 2025
Form 3File: Vastu B AND D form 3.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf5 Nov 2025
Form 1File: ARCHITECT.pdf5 Nov 2025
Form 2File: ENGINEER.pdf5 Nov 2025
Form 3File: FORM 3.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf5 Nov 2025
Other - TechnicalFile: VASTU (2)_11zon.pdf9 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certi310125.pdf8 May 2025
Disclosure of sold/ booked inventoryFile: vastu sold unsold.pdf8 May 2025
Declaration about Commencement CertificateFile: format d vastu.pdf8 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 vastu (1).pdf8 May 2025
Declaration in FORM BFile: form B affidavit (3).pdf25 Apr 2025
Certificates of CA (Form 3)File: Vastu B AND D form 3.pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 31 3 25.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer 31 3 25.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 30 6 24.pdf31 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 30 9 24.pdf31 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 30 12 24.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer 1 4 24.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer 1 7 24.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer 1 10 24.pdf31 Jan 2025
Certificates of CA (Form 3)File: CA CERTIFICATE_11zon (1).pdf25 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 vastu.pdf25 Jun 2024
Declaration in FORM BFile: FORM B 21 6 24.pdf22 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT 31-12-24.pdf22 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 31 3 24.pdf22 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate.pdf22 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Assurance Certificate 2024.pdf22 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Assurance Certificate 2024.pdf22 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P51700011170_FileName_1.pdf18 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate vastu.pdf14 Sep 2023
Disclosure of sold/ booked inventoryFile: VASTU UNSOLD.pdf14 Sep 2023
Certificates of CA (Form 3)File: form 3.pdf14 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5.pdf14 Sep 2023
Declaration in FORM BFile: VASTU B FORM.pdf5 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VSR-A Architecture Certificate for Complition Work.pdf5 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VSR-A Architecture Certificate for Complition Work.pdf5 Sep 2023
Building plan approvalFile: MAP.pdf31 Jul 2017
Layout approvalFile: MAP.pdf31 Jul 2017
PAN CardFile: PAN-CARD OF VASTU BUILDER.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE DEED.pdf31 Jul 2017
Details of encumbrancesFile: NO ENCUMBRACE CERTIFICATE.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: MAP.pdf31 Jul 2017
Building Plan Approval (IOD)File: MAP.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf31 Jul 2017
Declaration in FORM BFile: FORM B DECLARATION.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG.pdf31 Jul 2017
Certificates of CA (Form 3)File: FROM 3 CA CERTIFICATE.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE AS PER RERA ACT MODIFIED.pdf31 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VASTU SWPNAPURTI RESIDENCYVASTU SWAPNAPURTI RESIDENCY OPP NEW HP PETROL PUMP KARJAT BADLAPUR ROAD KATRAP BADLAPUR EAST DIST THANE90CompletedMay 2017Jan 2017
VASTU VINAY ASHISHVASTU VINAY ASHISH SNO1 H NO.17 PLOT NO.2 BEHIND USHAKIRAN RESIDANCY JOVELI BADLAPUR DIST THANE14CompletedDec 2016Late, May 2017
VASTU TERRACEVASTU TERRACE OPP NEW HP PETROL PUMP KATRAP BADLAPUR EAST THANE31CompletedMay 2012Late, Jan 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 26 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VASTU SWAPNAPURTY RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur (M Cl)7,600+ in Thane

2 kmVASTU SWAPNAPURTY RESIDECompleted 212Lapsed / revoked 80Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 426 registered projects within 2 km.

Builder: VASTU BUILDERS AND DEVELOPERS

VASTU BUILDERS AND DEVELOPERS has 3 registrations on MahaRERA, including VASTU SWAPNAPURTY RESIDENCY and PANDHARI HEIGHTS. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that VASTU SWAPNAPURTY RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VASTU SWAPNAPURTY RESIDENCY is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VASTU SWAPNAPURTY RESIDENCY?

The registered promoter entity is VASTU BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VASTU SWAPNAPURTY RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VASTU SWAPNAPURTY RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VASTU SWAPNAPURTY RESIDENCY?

The professionals named in the filing: Architect: SPACE ENGINEERS; Engineer: ATUL KUDTARKAR & ASSOCIATES; Chartered Accountant: Amrrita Jagnaani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASTU SWAPNAPURTY RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASTU SWAPNAPURTY RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASTU SWAPNAPURTY RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.