VASTU BUILDERS AND DEVELOPERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

VASTU BUILDERS AND DEVELOPERS has 3 registrations in this build, including VASTU SWAPNAPURTY RESIDENCY and PANDHARI HEIGHTS. Its filings disclose 3 earlier MahaRERA projects: 1 of 3 past projects completed on time.

3Registrations in this build
3Past projects disclosed
+5 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VASTU SWAPNAPURTY RESIDENCYThane, Maharashtra--Registration lapsed
PANDHARI HEIGHTSAhmednagar, Maharashtra2821%Registered
Vastu ImperiaThane, Maharashtra7315%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VASTU TERRACE
15 May 20124 Jan 2017+56 months
VASTU VINAY ASHISH
15 Dec 20163 May 2017+5 months
VASTU SWPNAPURTI RESIDENCY
15 May 20174 Jan 2017On time

Frequently asked questions

How do I verify VASTU BUILDERS AND DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with VASTU BUILDERS AND DEVELOPERS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.