Home / Browse projects / Ratnagiri, Maharashtra / VASANT RESIDENCY
VASANT RESIDENCY
By IDATE BUILDERS AND DEVELOPERS
RG-MH-23654 · RERA P52800078966 · Last updated on MahaRERA portal: 21 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VASANT RESIDENCY is a Residential / Group Housing project by IDATE BUILDERS AND DEVELOPERS in Ratnagiri, Maharashtra, registered with MahaRERA as P52800078966 on 24 Jan 2025. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameVASANT RESIDENCY
- TypeResidential / Group Housing
- Location
- Anandvan Jalgaon
- Jalgaon
- Dapoli
- Ratnagiri
- 415712
- Pincode415712
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800078966
- ReraGenie IDRG-MH-23654
Builder
- NameIDATE BUILDERS AND DEVELOPERS
- Entity typePartnership
- GSTIN27AAHFI8191F1Z3
- PartnersSANTOSH VASANT IDATE, VINAYAK VASANT IDATE
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jan 2025
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VASANT RESIDENCY | NA | 4 | 4 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 72%.
VASANT RESIDENCY: 23% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 72% |
| Basement (if any) | 70% |
| Podiums (if any) | 0% |
| Plinth | 70% |
| Stilt Floor | 40% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed34
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ASHOK RAMCHANDRA RANADE | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sohan Satishrao Mali |
| Engineer | Jogesh Madhukar Sadvilkar |
| Chartered Accountant | Shreyas Shrikant Kakirde |
| Partner | Role in project |
|---|---|
| IDATE BUILDERS AND DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Nov 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Vasant Residency.pdf | 21 Jun 2026 |
| Form 2File: Form 2 - Vasant Residency.pdf | 21 Jun 2026 |
| Form 3File: Form 3 - Vasant Residency.pdf | 21 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 2026.pdf | 21 Jun 2026 |
| Form 1File: Form 1.pdf | 23 Mar 2026 |
| Form 2File: Form 2.pdf | 23 Mar 2026 |
| Form 3File: Form 3.pdf | 23 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 23 Mar 2026 |
| Form 1File: Form 1.pdf | 23 Mar 2026 |
| Form 2File: Form 2.pdf | 23 Mar 2026 |
| Form 3File: Form 3.pdf | 23 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 23 Mar 2026 |
| Form 1File: Form 1 - Vasant Residency june 2025.pdf | 20 Jul 2025 |
| Form 2File: Form 2 - Vasant Residency june 2025.pdf | 20 Jul 2025 |
| Form 3File: Form 3 - Vasant Residency june 2025.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold - Vasant Residency june 2025.pdf | 20 Jul 2025 |
| Form 1File: Form 1.pdf | 15 Jul 2025 |
| Form 2File: Form Two - Engineer Certificate.pdf | 15 Jul 2025 |
| Form 3File: Form 3.pdf | 15 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory.pdf | 15 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vasant Residency Form 1.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vasant Residency Form 2.pdf | 21 Jan 2025 |
| Proforma of Agreement for saleFile: AGREEEMENT FOR SALE_RERA (2).pdf | 13 Jan 2025 |
| Declaration about Commencement CertificateFile: CC Declaration Vasant Residency (1).pdf | 7 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: UPDATED FORM 3 -IDATE.pdf | 5 Jan 2025 |
| Other - FinanceFile: LANDOWNER DECLARATION.pdf | 5 Jan 2025 |
| Proforma of Allotment letterFile: Updated Allotment Letter Format.pdf | 25 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Vinayak Idate Other Interest.pdf | 25 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Santosh Idate Other Interest.pdf | 25 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Form B Bank Declaration of accounts.pdf | 25 Nov 2024 |
| PAN CardFile: Idate Builders Pan Card.pdf | 20 Nov 2024 |
| Other - LegalFile: IDATE PARTNERSHIP DEED.pdf | 20 Nov 2024 |
| Building plan approvalFile: Plan 2 - Vasant Residency.pdf | 19 Nov 2024 |
| Building plan approvalFile: Plan 1 - Vasant Residency.pdf | 19 Nov 2024 |
| Layout approvalFile: Plan 2 - Vasant Residency.pdf | 19 Nov 2024 |
| Layout approvalFile: Plan 1 - Vasant Residency.pdf | 19 Nov 2024 |
| Copy of the legal title reportFile: Vasant Residency Search Report.pdf | 19 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Vasant Residency - Legal and Finance.pdf | 19 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: Plan 1 - Vasant Residency.pdf | 19 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: Plan 2 - Vasant Residency.pdf | 19 Nov 2024 |
| Declaration in FORM BFile: Form B - Vasant Residency.pdf | 19 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Idate NA Order19-11-2024.pdf | 19 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1 - Vasant Residency.pdf | 19 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2 - Vasant Residency.pdf | 19 Nov 2024 |
| Other - LegalFile: Land Owner Declaration.pdf | 19 Nov 2024 |
| CERSAI detailsFile: Cersai Declaration Vasant Residency.pdf | 19 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Form A - Bank Accounts.pdf | 19 Nov 2024 |
| Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation.pdf | 19 Nov 2024 |
| Details of encumbrances concerned to LegalFile: Vasant Residency - Legal and Finance.pdf | 19 Nov 2024 |
| Other - TechnicalFile: Annexure A - One Plot Registration.pdf | 19 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: Agreement to sale - Deviation.pdf | 19 Nov 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: No motgage Declaration.pdf | 19 Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 52 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VASANT RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Anandvan Jalgaon1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 28 registered projects within 2 km.
KONKAN TRAILS LIFESPACE
KONKANTRAILSLIFESPACELLP
Cape of Bliss Phase 1A
HOABL Management LLP
VIAA VISION
VIAA VISION
COASTAL BREEZE
UNIVERSAL PROPERTIES
VRUNDAVAN
EMPIRE REALTORS AND DEVELOPERS
Cape of Bliss Phase I
Lodha Management LLP
See every Ratnagiri project, with the district possession charts
Builder: IDATE BUILDERS AND DEVELOPERS
IDATE BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including SWAPNAPURTI RESIDENCY and VASANT RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if VASANT RESIDENCY is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VASANT RESIDENCY?
The registered promoter entity is IDATE BUILDERS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAHFI8191F1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VASANT RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VASANT RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VASANT RESIDENCY?
The professionals named in the filing: Architect: Sohan Satishrao Mali; Engineer: Jogesh Madhukar Sadvilkar; Chartered Accountant: Shreyas Shrikant Kakirde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VASANT RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback