Registered No litigation declared Others project

Vardhman Oasis

By Vardhman Developers Ltd

RG-MH-18929 · RERA P51900077882 · Last updated on MahaRERA portal: 7 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
146 of 146Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

Vardhman Oasis is a Others project by Vardhman Developers Ltd in Mumbai City, Maharashtra, registered with MahaRERA as P51900077882 on 8 Nov 2024. Possession is promised by 31 Dec 2027. 0 of the 146 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete.

At a glance

Project

  • NameVardhman Oasis
  • TypeOthers
  • Location
    • V P Road
    • Girgaum
    • Mumbai
    • Mumbai City
    • 400004
  • Pincode400004
  • RERA no.P51900077882
  • ReraGenie IDRG-MH-18929

Builder

  • NameVardhman Developers Ltd
  • Entity typeCompany
  • CINU70102MH1990PLC056704
  • GSTIN27AAACV1745Q1ZU
  • DirectorsRajesh Babulal Vardhan, Ramesh Babulal Vardhan
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredNov 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Nov 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed69 files

Current status

0%0 of 146 units booked

Figures as on 7 Nov 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vardhman Oasis Wing BNA26259056146
Vardhman Oasis Wing ANA43000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

Vardhman Oasis Wing B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Vardhman Oasis Wing A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered91

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,631 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Mar 2026

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI5301.02
Proposed, not sanctioned5,301 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Jehangir Building, M G Road, Fort, Mumbai 400001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKalpesh Shah
EngineerPankaj Shah
Chartered AccountantCA Bharat Kumar Singhal
PartnerRole in project
Vardhman Developers Ltd-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - FinanceFile: Clarification Letter 2.pdf7 Nov 2024
Other - FinanceFile: Clarification Letter.pdf6 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Final 23102024.pdf23 Oct 2024
Other - FinanceFile: Sanction Plan-Sheet No 1.pdf16 Oct 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf14 Oct 2024
Layout approvalFile: Building plan.pdf12 Oct 2024
Copy of Layout Approval (in case of layout)File: Building plan.pdf12 Oct 2024
Details of encumbrances concerned to FinanceFile: EC-Legal.pdf11 Oct 2024
Details of encumbrances concerned to FinanceFile: EC-Finance.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf11 Oct 2024
Other - LegalFile: Badamwadi Conveyance.pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: EC-Finance.pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: EC-Legal.pdf11 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf11 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Loan.pdf11 Oct 2024
Building plan approvalFile: 08.pdf7 Oct 2024
Building plan approvalFile: 07.pdf7 Oct 2024
Building plan approvalFile: 06.pdf7 Oct 2024
Building plan approvalFile: 05.pdf7 Oct 2024
Building plan approvalFile: 04.pdf7 Oct 2024
Building plan approvalFile: 03.pdf7 Oct 2024
Building plan approvalFile: 02.pdf7 Oct 2024
Building plan approvalFile: 01.pdf7 Oct 2024
Layout approvalFile: 08.pdf7 Oct 2024
Layout approvalFile: 07.pdf7 Oct 2024
Layout approvalFile: 06.pdf7 Oct 2024
Layout approvalFile: 05.pdf7 Oct 2024
Layout approvalFile: 04.pdf7 Oct 2024
Layout approvalFile: 03.pdf7 Oct 2024
Layout approvalFile: 02.pdf7 Oct 2024
Layout approvalFile: 01.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 07.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 08.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 06.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 05.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 04.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 03.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 02.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: 01.pdf7 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC-Plinth.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 05.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 01.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 02.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 03.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 04.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 06.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 07.pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 08.pdf7 Oct 2024
Declaration about Commencement CertificateFile: Form D - Vardhman Oasis.pdf7 Oct 2024
Other - LegalFile: Badamwadi Conveyance.pdf28 Jun 2024
Other - LegalFile: PRC-Vardhman.pdf28 Jun 2024
Proforma of Allotment letterFile: Allotment Letter - Hightlighted.pdf29 May 2024
Other - LegalFile: One Plot and One Registration.pdf29 May 2024
Other - TechnicalFile: One Plot and One Registration.pdf29 May 2024
Proforma of Agreement for saleFile: AFS - Final.pdf29 May 2024
Copy of the legal title reportFile: Title report Vardhman Group.pdf28 May 2024
Declaration in FORM BFile: Form B.pdf28 May 2024
Other - LegalFile: Badamwadi Conveyance - converted.pdf28 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf28 May 2024
Deviation Report with respect to model copy of AgreementFile: Deviation for AFS-Format Consultant 27052024_compressed.pdf28 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Othe Real Estates.pdf28 May 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf17 May 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf17 May 2024
CERSAI detailsFile: Declaration-Nil-CERSAI Report.pdf17 May 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf17 May 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf17 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf17 May 2024
PAN CardFile: Company PAN Card.pdf14 May 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Vardhman Empire138 153 Borivali Mumbai Suburban 40006727CompletedDec 2020Oct 2020

How this compares with Mumbai City

0%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vardhman Oasis on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Girgaum, Mumbai780+ in Mumbai City

Builder: Vardhman Developers Ltd

VARDHMAN DEVELOPERS LTD has 6 registrations on MahaRERA, including VARDHMAN EMPIRE and VARDHMAN GRANDEUR. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Vardhman Oasis is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vardhman Oasis?

The registered promoter entity is Vardhman Developers Ltd, a company as per the filing. Its CIN U70102MH1990PLC056704 and GSTIN 27AAACV1745Q1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vardhman Oasis?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vardhman Oasis?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vardhman Oasis?

The professionals named in the filing: Architect: Kalpesh Shah; Engineer: Pankaj Shah; Chartered Accountant: CA Bharat Kumar Singhal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vardhman Oasis?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vardhman Oasis. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vardhman Oasis to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.