Home / Browse projects / Kolhapur, Maharashtra / VARDHAMAN CHINTAMANI

Registration lapsed No litigation declared Others project

VARDHAMAN CHINTAMANI

By MIRJE ESTATE DEVELOPERS PVT.LTD.

RG-MH-24009 · RERA P53000011547 · Last updated on MahaRERA portal: 16 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

VARDHAMAN CHINTAMANI is a Others project by MIRJE ESTATE DEVELOPERS PVT.LTD. in Kolhapur, Maharashtra, registered with MahaRERA as P53000011547 on 31 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NameVARDHAMAN CHINTAMANI
  • TypeOthers
  • Location
    • E Ward
    • Shahupuri
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416001
  • Pincode416001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000011547
  • ReraGenie IDRG-MH-24009

Builder

  • NameMIRJE ESTATE DEVELOPERS PVT.LTD.
  • Entity typeCompany
  • Managing DirectorSANMATI GANPAT MIRJE

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2022)
  • Buildings2 building records
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BULDINGNA60000
B BULDINGNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.

A BULDING81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B BULDING81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 16 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,448 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2336.13
Proposed, not sanctioned2,301 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch398 B, E Ward, Shahupuri, Kolhapur-416001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA SQUARE AMAR BHAVANENDRA UPADHYA
EngineerJW CONSULTANTS LLP
Chartered AccountantKUNTE AND CHOUGULE
PartnerRole in project
MIRJE ESTATE DEVELOPERS PVT.LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000010957Jun 2022 → Dec 2024

Reason as filed by the promoterWe have completed our Project But, we are not received Completion Certificate from Kolhapur Municipal Corporation in within time limit . So we have require for further extension for up to date 31/12/2024.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Oct 2021

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 FY 2022-23.pdf16 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate -Mirje03242023.pdf24 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A -2020 -Mirje03242023.pdf24 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A -2020 -Mirje03242023.pdf24 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A -2022 -Mirje03242023.pdf24 Mar 2023
Disclosure of sold/ booked inventoryFile: Sold unsold inventary03242023.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (1).pdf24 Mar 2023
Building plan approvalFile: Plan Basement.pdf5 Oct 2021
Building plan approvalFile: Plan Floors.pdf5 Oct 2021
Building Plan Approval (IOD)File: Plan Basement.pdf5 Oct 2021
Building Plan Approval (IOD)File: Plan Floors.pdf5 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.PDF5 Oct 2021
Declaration about Commencement CertificateFile: Commencement Certificate.PDF5 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Application for Complition.PDF5 Oct 2021
OtherFile: NOC Property Tax.pdf5 Oct 2021
OtherFile: NOC Water.PDF5 Oct 2021
OtherFile: KMC Flood Order.pdf5 Oct 2021
Layout approvalFile: Plan 1.pdf31 May 2018
Details of encumbrancesFile: Index II.pdf31 May 2018
Copy of Layout Approval (in case of layout)File: Plan 1.pdf31 May 2018
Layout approvalFile: 000000130shree1.PDF31 Jul 2017
Layout approvalFile: 000000127shree1.PDF31 Jul 2017
Building plan approvalFile: 000000129shree1.PDF31 Jul 2017
Building plan approvalFile: 000000128shree1.PDF31 Jul 2017
Copy of the legal title reportFile: Leagle and title Rrport.pdf31 Jul 2017
Details of encumbrancesFile: Declaration.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: 000000130shree1.PDF31 Jul 2017
Copy of Layout Approval (in case of layout)File: 000000127shree1.PDF31 Jul 2017
Building Plan Approval (IOD)File: 000000129shree1.PDF31 Jul 2017
Building Plan Approval (IOD)File: 000000128shree1.PDF31 Jul 2017
Declaration in FORM BFile: Page-1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Cretificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM NO 3 FOR RERA.pdf31 Jul 2017
Proforma of Allotment letterFile: New 35.pdf31 Jul 2017

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one moved by 30 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is among them

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep VARDHAMAN CHINTAMANI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shahupuri880+ in Kolhapur

2 kmVARDHAMAN CHINTAMANICompleted 59Lapsed / revoked 32Other 59Dot size: filed unitsN

Filed coordinates, straight-line distance. 150 registered projects within 2 km.

Builder: MIRJE ESTATE DEVELOPERS PVT.LTD.

MIRJE ESTATE DEVELOPERS PVT.LTD. has 1 registration on MahaRERA, including VARDHAMAN CHINTAMANI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What does it mean that VARDHAMAN CHINTAMANI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VARDHAMAN CHINTAMANI is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHAMAN CHINTAMANI?

The registered promoter entity is MIRJE ESTATE DEVELOPERS PVT.LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHAMAN CHINTAMANI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VARDHAMAN CHINTAMANI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHAMAN CHINTAMANI?

The professionals named in the filing: Architect: A SQUARE AMAR BHAVANENDRA UPADHYA; Engineer: JW CONSULTANTS LLP; Chartered Accountant: KUNTE AND CHOUGULE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHAMAN CHINTAMANI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHAMAN CHINTAMANI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHAMAN CHINTAMANI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.