Home / Browse projects / Jalna, Maharashtra / VANSH BLUEBELLS
VANSH BLUEBELLS
RG-MH-02531 · RERA P51400014727 · Last updated on MahaRERA portal: 1 Apr 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VANSH BLUEBELLS is a Residential / Group Housing project by NEHA INFRASTRUCTURES in Jalna, Maharashtra, registered with MahaRERA as P51400014727 on 26 Dec 2017. Possession was promised by 5 Dec 2023 and is now 34 months past that date.
At a glance
Project
- NameVANSH BLUEBELLS
- TypeResidential / Group Housing
- Location
- NAYA BAZAR JALNA
- JALNA
- Jalna (M Cl)
- 431203
- Pincode431203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51400014727
- ReraGenie IDRG-MH-02531
Builder
- NameNEHA INFRASTRUCTURES
- Entity typePartnership
- GSTIN27AAOFN2100N1Z5
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Dec 2017
- Promised completion5 Dec 2023
- Revised completionNone
- Buildings7 building records
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A 4 SHOPS AND 24 FLATS | NA | 6 | 0 | 0 | 0 | 0 |
| B TYPE ROW HOUSES B1 TO B6 | NA | 2 | 0 | 0 | 0 | 0 |
| C TYPE ROW HOUSES C1 TO C4 | NA | 3 | 0 | 0 | 0 | 0 |
| D TYPE ROW HOUSES D1 TO D10 | NA | 3 | 0 | 0 | 0 | 0 |
| E TYPE ROW HOUSES E1 TO E9 | NA | 3 | 0 | 0 | 0 | 0 |
| F TYPE ROW HOUSES F1 TO F4 | NA | 3 | 0 | 0 | 0 | 0 |
| G TYPE ROW HOUSES | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 1 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
43 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Slabs of Super Structure, at 50%.
BUILDING A 4 SHOPS AND 24 FLATS45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B TYPE ROW HOUSES B1 TO B632%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C TYPE ROW HOUSES C1 TO C432%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D TYPE ROW HOUSES D1 TO D1073%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E TYPE ROW HOUSES E1 TO E973%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F TYPE ROW HOUSES F1 TO F473%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G TYPE ROW HOUSES73%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 1 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | Yes | 0% |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAURABH MIRKUTE |
| Engineer | PRADEEP VITTHALRAO MOTE |
| Chartered Accountant | EKTA KUTHIALA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| NEHA INFRASTRUCTURES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Dec 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Dec 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Dec 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Apr 2022
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 1 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200231185873_For_Asset_Based_Search_26_02_2022_11_41_33_429.pdf | 1 Apr 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion Certificate.pdf | 1 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: buil per.pdf | 18 Dec 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: NA PERMISTION.pdf | 18 Dec 2017 |
| Certificates of CA (Form 3)File: ca cer.pdf | 18 Dec 2017 |
| Layout approvalFile: LAYOUT SANCTION PLAN 1.pdf | 15 Dec 2017 |
| Building plan approvalFile: A TYPE APT.pdf | 15 Dec 2017 |
| Building plan approvalFile: FINAL ROW HOUSE TYPE B AND C.pdf | 15 Dec 2017 |
| Building plan approvalFile: 1FINAL ROW HOUSE TYPE D AND E.pdf | 15 Dec 2017 |
| Building plan approvalFile: FINAL ROW HOUSE TYPE F AND G-min.pdf | 15 Dec 2017 |
| Building plan approvalFile: LAYOUT SANCTION PLAN.pdf | 15 Dec 2017 |
| PAN CardFile: PAN CARD COPY.pdf | 15 Dec 2017 |
| Copy of the legal title reportFile: FINAL LEGAL TITLE REPORT.pdf | 15 Dec 2017 |
| Details of encumbrancesFile: DETAILS OF ENCUMMARANCE CER.pdf | 15 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT SANCTION PLAN 1.pdf | 15 Dec 2017 |
| Building Plan Approval (IOD)File: A TYPE APT.pdf | 15 Dec 2017 |
| Building Plan Approval (IOD)File: FINAL ROW HOUSE TYPE B AND C.pdf | 15 Dec 2017 |
| Building Plan Approval (IOD)File: 1FINAL ROW HOUSE TYPE D AND E.pdf | 15 Dec 2017 |
| Building Plan Approval (IOD)File: FINAL ROW HOUSE TYPE F AND G-min.pdf | 15 Dec 2017 |
| Building Plan Approval (IOD)File: LAYOUT SANCTION PLAN.pdf | 15 Dec 2017 |
| Declaration in FORM BFile: DECLERATION OF FORM B.pdf | 15 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER.pdf | 15 Dec 2017 |
| Proforma of Allotment letterFile: AGREEMENT OT SALE.pdf | 15 Dec 2017 |
| OtherFile: OTHER PAPER.pdf | 15 Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jalna
Computed across the 100+ Jalna projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 25 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VANSH BLUEBELLS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JALNA100+ in Jalna
VITTHALA TOWERS
TIRUPATI BUILDCON
SHREE SAI CITY PHASE-I
SHREE SAI CITY BUILDERS AND DEVELOPERS
JINDAL GOYAL SQUARE
JINDAL GOYAL REALITY LLP
Krishna Capital
Krishna Capital
Lalbag, Plotting
GO Developers LLP
RUKHMINI HEIGHTS
TIRUPATI INFRA JALNA
See every Jalna project, with the district possession charts
Builder: NEHA INFRASTRUCTURES
NEHA INFRASTRUCTURES has 2 registrations on MahaRERA, including VANSH BLUEBELLS and VANSH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.
Frequently asked questions
What does it mean that VANSH BLUEBELLS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VANSH BLUEBELLS is delayed beyond 5 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VANSH BLUEBELLS?
The registered promoter entity is NEHA INFRASTRUCTURES, a partnership as per the filing. Its GSTIN 27AAOFN2100N1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VANSH BLUEBELLS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VANSH BLUEBELLS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VANSH BLUEBELLS?
The professionals named in the filing: Architect: SAURABH MIRKUTE; Engineer: PRADEEP VITTHALRAO MOTE; Chartered Accountant: EKTA KUTHIALA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VANSH BLUEBELLS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback