VANDE MATARAM DIVINE
RG-MH-04569 · RERA P52000022082 · Last updated on MahaRERA portal: 16 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VANDE MATARAM DIVINE is a Residential / Group Housing project by SADGURU SHELTER in Raigarh, Maharashtra, registered with MahaRERA as P52000022082 on 25 Aug 2019. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 80 of the 106 units on this registration are recorded sold or booked, and 30 of 33 construction stages are filed complete.
At a glance
Project
- NameVANDE MATARAM DIVINE
- TypeResidential / Group Housing
- Location
- SR NO 141 5B 5C
- NEAR DHRUV RESIDENCY
- Pashane
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000022082
- ReraGenie IDRG-MH-04569
Builder
- NameSADGURU SHELTER
- Entity typePartnership
- PartnersARVIND DEVASIBHAI LIMBANI, MANIBHAI PATEL, SURESH LALJIBHAI CHOPDA, JAYASHRI NIKUNJ PATEL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on25 Aug 2019
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
- Buildings3 building records
- Documents filed98 files
Current status
Figures as on 16 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C | NA | 5 | 4 | 36 | 0 | 36 |
| D | NA | 4 | 4 | 35 | 0 | 35 |
| E | NA | 4 | 4 | 35 | 0 | 35 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 16 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| C | 10 | 10 |
| D | 9 | 9 |
| E | 9 | 9 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| RAVINDRA BALU PALANDE | Pashane | Raigarh |
| SANDEEP BALU PALANDE | Pashane | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C | NA | Rs 1.96 cr | Rs 1.96 cr |
| D | NA | Rs 1.95 cr | Rs 1.95 cr |
| E | NA | Rs 1.95 cr | Rs 1.95 cr |
| - | NA | Rs 28.50 lakh | Rs 28.50 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESTINATION ARCHITECHTS |
| Engineer | KR PATEL AND ASSOCIATES |
| Chartered Accountant | PRITESH GADA & CO |
| Chartered Accountant | DHARA PRITESH GADA |
| Partner | Role in project |
|---|---|
| SADGURU SHELTER | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the pandemic situation prevailing for almost last 2 years construction activity also affected adversely.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: FORM 2A 24-25.pdf | 16 Feb 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A 24-25.pdf | 16 Feb 2026 |
| Form 2A (FY 2019-2020)File: FORM 2A 19-20.pdf | 16 Feb 2026 |
| Form 2A (FY 2020-2021)File: FORM 2A 20-21.pdf | 16 Feb 2026 |
| Form 2A (FY 2021-2022)File: FORM 2A 21-22.pdf | 16 Feb 2026 |
| Form 2A (FY 2022-2023)File: FORM 2A 22-23.pdf | 16 Feb 2026 |
| Form 2A (FY 2023-2024)File: FORM 2A 23-24.pdf | 16 Feb 2026 |
| Form 5 (FY 2020-2021)File: Form 5- New 2021.pdf | 16 Feb 2026 |
| Form 5 (FY 2021-2022)File: 21-22_page-0001_merged.pdf | 16 Feb 2026 |
| Form 5 (FY 2022-2023)File: Form 5 22-23.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 10 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 10 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 10 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 10 Feb 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 10 Feb 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 10 Feb 2026 |
| Form 5 (FY 2019-2020)File: 19-20_page-0001_merged.pdf | 10 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Rera.pdf | 10 Feb 2026 |
| Form 1File: Form 1.pdf | 29 Jan 2026 |
| Form 2File: Form 2.pdf | 29 Jan 2026 |
| Form 3File: Form 3.pdf | 29 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Final.pdf | 29 Jan 2026 |
| Form 1File: Form 1.pdf | 29 Jan 2026 |
| Form 2File: FORM 2.pdf | 29 Jan 2026 |
| Form 3File: FORM 3.pdf | 29 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY.pdf | 29 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5.pdf | 29 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Mar25.pdf | 27 Oct 2025 |
| Form 1File: Form 1.pdf | 18 Oct 2025 |
| Form 2File: Form 2.pdF | 18 Oct 2025 |
| Form 3File: FORM 3.pdf | 18 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold & Unsold.pdf | 18 Oct 2025 |
| Form 1File: Form 1.pdf | 18 Oct 2025 |
| Form 2File: Form 2.pdF | 18 Oct 2025 |
| Form 3File: Form 3.pdf | 18 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold & Unsold.pdf | 18 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Final.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT'S CERTIFICATE FINAL.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY.pdf | 22 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 22 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2024.pdf | 5 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 16 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD UNITS.pdf | 16 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 13 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE CERTIFICATE LEGAL.pdf | 7 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE CERTIFICATE CONCERNED FINANCE.pdf | 7 Feb 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE CERTIFICATE LEGAL.pdf | 7 Feb 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE CERTIFICATE CONCERNED FINANCE.pdf | 7 Feb 2024 |
| CERSAI detailsFile: No CERSAI Report.pdf | 7 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report in Respect of Allotment.pdf | 7 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report in Respect of Agreement.pdf | 7 Feb 2024 |
| Details of encumbrancesFile: NON ENCUMBRANCE.pdf | 13 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest of Other Real Estate Org.pdf | 13 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A SEPERATE BANK ACCOUNT DETAIL.pdf | 13 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 19 20.pdf | 8 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 20 21.pdf | 8 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21 22.pdf | 8 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22 23.pdf | 8 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD AREA D n E WING AS ON 30SEPT23.pdf | 8 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 22-23_page-0001_merged.pdf | 8 Jan 2024 |
| Declaration in FORM BFile: FORM B NOTARY.pdf | 25 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A stamped.pdf | 25 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20_page-0001_merged.pdf | 25 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 21-22_page-0001_merged.pdf | 25 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 22-23_page-0001_merged.pdf | 25 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 22-23_page-0001_merged.pdf | 25 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (ARCHITECT).pdf | 4 Dec 2023 |
| Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf | 24 Jan 2023 |
| Declaration about Commencement CertificateFile: CC DECLRATION.pdf | 16 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 16 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA 9 08 19_compressed.pdf | 20 Aug 2019 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 20 Aug 2019 |
| Building plan approvalFile: 111.pdf | 16 Aug 2019 |
| Building plan approvalFile: 222.pdf | 16 Aug 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VANDE MATARAM DIVINE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR DHRUV RESIDENCY5,900+ in Raigarh
Filed coordinates, straight-line distance. 35 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: SADGURU SHELTER
SADGURU SHELTER has 1 registration on MahaRERA, including VANDE MATARAM DIVINE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that VANDE MATARAM DIVINE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VANDE MATARAM DIVINE is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VANDE MATARAM DIVINE?
The registered promoter entity is SADGURU SHELTER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VANDE MATARAM DIVINE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VANDE MATARAM DIVINE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VANDE MATARAM DIVINE?
The professionals named in the filing: Architect: DESTINATION ARCHITECHTS; Engineer: KR PATEL AND ASSOCIATES; Chartered Accountant: PRITESH GADA & CO; Chartered Accountant: DHARA PRITESH GADA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VANDE MATARAM DIVINE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback