Home / Browse projects / Pune, Maharashtra / VANAHA SPRINGS T1 WILLOW

Registered Litigation declared Residential / Group Housing project

VANAHA SPRINGS T1 WILLOW

By IMAGE REALTY PRIVATE LIMITED

RG-MH-22044 · RERA P52100030065 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 350.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 86%
0 of 307Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

VANAHA SPRINGS T1 WILLOW is a Residential / Group Housing project by IMAGE REALTY PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100030065 on 29 Jul 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 307 of the 307 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVANAHA SPRINGS T1 WILLOW
  • TypeResidential / Group Housing
  • Location
    • SPINE ROAD
    • OXFORD GOLF RESORT
    • Lavale
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • RERA no.P52100030065
  • ReraGenie IDRG-MH-22044

Builder

  • NameIMAGE REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU68200MH2026PTC465298
  • GSTIN27AAICI6208F1ZM
  • PartnersNirav Bhupendra Dalal, Haresh Jayantilal Shah, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal
  • Other registrations9 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2021First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed125 files

Current status

100%307 of 307 units booked
98.7%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VANAHA SPRINGS T1 WILLOWNA36303070307

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 86%.

VANAHA SPRINGS T1 WILLOW: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks82%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.56%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.56%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes48%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes52%
Landscaping & Tree PlantingYes39%
Street LightingYes0%
Community BuildingsYes40%
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes85%
Energy managemcntYes10%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes27%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed322

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots322
Closed/Covered322

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,789 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofIDBI TRUSTEE SHIP SERVICES LTD
Secured amountRs 350.00 crore
CERSAI search filedYes
Declared on20 Nov 2025
LandownerVillageDistrict
IMAGE REALTY LLPPune (M Corp.)Pune
KNOWLEDGE CITY EDUCATION PVT LTDPune (M Corp.)Pune
OXFORD GOLF & RESORTS PVT LTDPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI27351.62
Proposed, not sanctioned27,352 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJ B NAGAR ANDHERI WEST MUMBAI
Estimated costRs 153.40 cr
Cost incurredRs 151.36 cr
Work done98.67%
BuildingWingEstimatedIncurred
VANAHA SPRINGS T1 WILLOWNARs 125.73 crRs 125.25 cr
-NARs 27.67 crRs 26.11 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAPADIA ASSOCIATES DESIGN LLP
ArchitectCRYSTAL ARCH
ArchitectSALEEL DESHPANDE
EngineerAJIT KULKARNI
Chartered AccountantBhavesh Nagda
Chartered AccountantHarshad Doshi & Co.
PartnerRole in project
IMAGE REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23122518942Mar 2026 → Mar 2027

Reason as filed by the promoterThe project “VANAHA SPRINGS T1 WILLOW” was registered with MahaRERA on 29/07/2021, with validity granted up to 31/03/2026 under Section 5 of the Act. The project forms part of the larger township “Vanaha”, situated at Village Lavale, Taluka Mulshi, District Pune, spread across a larger land parcel of approximately 953 acres. The specific land parcel for VANAHA SPRINGS T1 WILLOW measures 1,788.58 sq. mtrs., forming part of Sector OCR-12 of the township. The delay in completion has arisen due to factors beyond the control of the Promoter. At the initial stage, development of the access road and

Litigation declared3

CaseCourtStatus
940/2022Civil Court Senior Division PunePending for Issues
291/2022District and Sessions Court PunePending for Orders
940/2022Civil CourtOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602802Subhash Sharad TillooIMAGE REALTY PRIVATE LIMITED14/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: WILLOW 2026.pdf9 Jun 2026
Building plan approvalFile: Revised Building Plan.pdf20 Apr 2026
Withdrawal Update Form 1File: Architect Certificate WILLOW 31 03 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate WILLOW 31 03 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: 20260331 RERA Certificate OCR 12 T1 Willow - RERA.pdf20 Apr 2026
Withdrawal Update Form 1File: ARCHITECT WILLOW 31 12 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: WILLOW_Eng Cert 31 12 2025.pdf5 Feb 2026
Withdrawal Update Form 3File: 20240307 RERA Certificate OCR 12 T1 Willow.pdf5 Feb 2026
Form 1File: ARCHITECT WILLOW 09 10 2025.pdf20 Oct 2025
Form 2File: WILLOW.pdf20 Oct 2025
Form 3File: 20250930 RERA Certificate OCR 12 T1 Willow - RERA.pdf20 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory_T1.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 OCR 12 T1 Willow_1.pdf30 Sep 2025
Form 1File: Architect cert -WILLOW_01 07 2025.pdf15 Jul 2025
Form 2File: WILLOW_Eng Cert 01 07 2025.pdf15 Jul 2025
Form 3File: 20250630 RERA Certificate OCR 12 T1 Willow - RERA.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory_T1.pdf15 Jul 2025
Disclosure of sold/ booked inventoryFile: Format_Progress Report_Dec 2024_WILLOW.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ASPEN 21 01 2025.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW-28 03 2025.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20241231 RERA Certificate OCR 12 T1 Willow - RERA.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20250331 RERA Certificate OCR 12 T1 Willow - RERA.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW 2024.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW_Eng Cert 31 12 2024.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW_Eng Cert 31 12 2023_1.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW 19 06 2024-SS.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW 19 10 24.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW 21 01 2025.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Format_Progress Report_Mar 2025_WILLOW.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Format_Progress Report_Dec 2024_WILLOW.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 OCR 12 T1 Willow.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Format_Progress Report_Sept 2024_WILLOW.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20240930 RERA Certificate OCR 12 T1 Willow - RERA.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Willow.pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW.pdf18 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_S T1.pdf18 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20240307 RERA Certificate OCR 12 T1 Willow.pdf18 Apr 2024
Copy of the legal title reportFile: PDF-1329-RERA Report 1187.pdf18 Feb 2024
Copy of the legal title reportFile: PDF-1330-RERA Report 1188.pdf18 Feb 2024
Copy of the legal title reportFile: PDF-1331-RERA Report 1189.pdf18 Feb 2024
Copy of the legal title reportFile: PDF-1328-RERA Report 1198 by 2.pdf18 Feb 2024
Proforma of Agreement for saleFile: RERA AFS OCR 12 - TOWER 1 WILLOW.pdf18 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW 18 12 2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20230930 RERA Certificate OCR 12 T1 Willow - RERA_compressed.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Format_Progress Report_Dec 2023_WILLOW.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Progress Report_Sept 2023_WILLOW.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_WILLOW.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW.pdf30 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20230911 RERA Certificate OCR 12 T1 Willow - RERA_compressed.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_WILLOW.pdf28 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_T1.pdf13 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: WILLOW.pdf13 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Progress Report_June 2023_WILLOW.pdf4 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf4 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW.pdf30 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: WILLOW.pdf30 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20230531 RERA Certificate OCR 12 T1 Willow - RERA.pdf30 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Progress Report_March 2023_WILLOW.pdf1 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf1 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW_20 02 2023.pdf2 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH2 T1 WILLOW.pdf2 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20230221 RERA Certificate OCR 12 T1 Willow - RERA.pdf2 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VANAHA SPRINGS T1 WILLOW_17 01 2023.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG_CERT_WILLOW_17 01 2023.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20221231 RERA Certificate OCR 12 T1 Willow - RERA.pdf22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WILLOW_Progress Report_Dec 2022.pdf30 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory_T1.pdf30 Dec 2022
Proforma of Agreement for saleFile: 20 12 2022 OCR-12 AFS RESIDENTIAL.pdf21 Dec 2022
Copy of the legal title reportFile: RERA Title Report _Gat No 1198-2.pdf16 Dec 2022

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
YAHAVI-TOWER-3-TEAKP52100028033OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI-TOWER-2-PINEP52100028082OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI-TOWER-1-OAKP52100028031OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI RETAILP52100031784OXFORD GOLF COURSE, Pune19Nov 2021CompletedJun 2024Jun 2024

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VANAHA SPRINGS T1 WILLOW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OXFORD GOLF RESORT13,700+ in Pune

Builder: IMAGE REALTY PRIVATE LIMITED

IMAGE REALTY PRIVATE LIMITED has 10 registrations on MahaRERA, including VANAHA SPRINGS T1 WILLOW and VANAHA SPRINGS T2 CEDAR. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VANAHA SPRINGS T1 WILLOW is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VANAHA SPRINGS T1 WILLOW?

The registered promoter entity is IMAGE REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U68200MH2026PTC465298 and GSTIN 27AAICI6208F1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VANAHA SPRINGS T1 WILLOW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VANAHA SPRINGS T1 WILLOW?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VANAHA SPRINGS T1 WILLOW?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VANAHA SPRINGS T1 WILLOW?

The professionals named in the filing: Architect: KAPADIA ASSOCIATES DESIGN LLP; Architect: CRYSTAL ARCH; Architect: SALEEL DESHPANDE; Engineer: AJIT KULKARNI; Chartered Accountant: Bhavesh Nagda; Chartered Accountant: Harshad Doshi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VANAHA SPRINGS T1 WILLOW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VANAHA SPRINGS T1 WILLOW. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VANAHA SPRINGS T1 WILLOW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.