Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

VALENCIA PARADISE is a Others project by PARADISE ASSOCIATES in Mumbai City, Maharashtra, registered with MahaRERA as P51900010342 on 24 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVALENCIA PARADISE
  • TypeOthers
  • Location
    • Mumbai City
    • 400004
  • Pincode400004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900010342
  • ReraGenie IDRG-MH-24792

Builder

  • NamePARADISE ASSOCIATES
  • Entity typePartnership
  • PartnersIBRAHIM ABUBAKER MOMIN, JITENDRA KANTILAL SHAH
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

82 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VALENCIA PARADISENA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

VALENCIA PARADISE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area733 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4792.4
Proposed, not sanctioned4,792 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHARAM PALACE N S PATKAR MARG GAMDEVI MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKARNIK CHAUHAN
EngineerSTRESCON SONSULTANTS
PartnerRole in project
PARADISE ASSOCIATES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900002458Dec 2018 → Dec 2019

Reason as filed by the promoterSTOP WORK NOTICE ISSUED BY MCGM

EXT51900000115Dec 2018 → Dec 2019

Reason as filed by the promoterAPPLIED FOR FULL OCCUPATION CERTIFICATE, BUT PART OCCUPATION CERTIFICATE RECEIVED ON 25 SEPTEMBER 2017 DUE TO MHADA NOC FOR OCCUPATION RECEIVED FOR 54 TENANTS ONLY. REST TENANTS WERE NOT PRESENT AT THE TIME OF VERIFICATION. ONCE ALL THE TENANTS ARE VERIFIED FULL NOC WILL BE ISSUED BY MHADA AND THEN FULL OCCUPATION CERTIFICATE WILL BE ISSUED BY MCGM.

Litigation declared6

CaseCourtStatus
82/2016HIGH COURTPENDING FOR HEARINGG
2120/2016HIGH COURTPENDING FOR HEARING
2606/2018HIGH COURTPENDING FOR HEARING
571/2018HIGH COURTPENDING FOR HEARING
582/2018HIGH COURTPENDING FOR HEARING
697/2018HIGH COURTPENDING FOR HEARING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000012230Narhari BhatkarParadise Associates30/11/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jan 2023

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PARADISE.pdf16 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Valencia Paradiae.pdf16 Jan 2023
Certificates of CA (Form 5)File: form 5.pdf1 Oct 2018
OtherFile: Part OC.pdf18 Nov 2017
Layout approvalFile: Paradise Layout.pdf14 Aug 2017
Details of encumbrancesFile: Pending cases.pdf14 Aug 2017
Copy of Layout Approval (in case of layout)File: Paradise Layout.pdf14 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng Certificate.pdf14 Aug 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf14 Aug 2017
Building plan approvalFile: Paradise IOD.pdf11 Aug 2017
PAN CardFile: Pan card Paradise associates Pdf.pdf11 Aug 2017
Copy of the legal title reportFile: Paradise Title Certificate.pdf11 Aug 2017
Building Plan Approval (IOD)File: Paradise IOD.pdf11 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Paradise CC.pdf11 Aug 2017
Declaration in FORM BFile: Form B Paradise Associates.pdf11 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Paradise Associates.pdf11 Aug 2017
Proforma of Allotment letterFile: Agreement Declaration.pdf11 Aug 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 12 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VALENCIA PARADISE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai City780+ in Mumbai City

2 kmVALENCIA PARADISECompleted 35Lapsed / revoked 39Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 167 registered projects within 2 km.

Builder: PARADISE ASSOCIATES

PARADISE ASSOCIATES has 3 registrations on MahaRERA, including PARADISE HILLS NEW and VALENCIA PARADISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that VALENCIA PARADISE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VALENCIA PARADISE is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VALENCIA PARADISE?

The registered promoter entity is PARADISE ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VALENCIA PARADISE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VALENCIA PARADISE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VALENCIA PARADISE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VALENCIA PARADISE?

The professionals named in the filing: Architect: KARNIK CHAUHAN; Engineer: STRESCON SONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VALENCIA PARADISE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VALENCIA PARADISE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VALENCIA PARADISE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.