Home / Browse projects / Pune, Maharashtra / Vaishnav Gaatha

Registered No litigation declared Others project

Vaishnav Gaatha

By Kalbhor Realtors And Services LLP

RG-MH-85099 · RERA P52100052318 · Last updated on MahaRERA portal: 2 Aug 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 18 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 80%
15 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

Vaishnav Gaatha is a Others project by Kalbhor Realtors And Services LLP in Pune, Maharashtra, registered with MahaRERA as P52100052318 on 9 Aug 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 18 months from the original filing. 2 of the 17 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameVaishnav Gaatha
  • TypeOthers
  • Location
    • 1587/1
    • 2P
    • Plot No. 1
    • Chikhali
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052318
  • ReraGenie IDRG-MH-85099

Builder

  • NameKalbhor Realtors And Services LLP
  • Entity typeOthers
  • Named personsYash Dhananjay Kalbhor, Dhananjay Vitthal Kalbhor, Vaishnavi Dhananjay Kalbhor
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2023First promiseJun 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed100 files

Current status

12%2 of 17 units booked

Figures as on 2 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vaishnav GaathaNA6512517

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Vaishnav Gaatha: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Open Space64

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area490 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Dec 2025

Approvals and building plan

Sanctioning authorityPimpari Chinchwad Municipal Corporation, Pimpari
Permissible FSI827.18
Proposed, not sanctioned827 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAKURDI

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPatil & Bugade Associates
EngineerRohinee Engineers
EngineerRahul Kalbhor
Chartered AccountantParag S Savale & Associates
Chartered AccountantMaheshwar Marathe
PartnerRole in project
Kalbhor Realtors And Services LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028265Jun 2025 → Dec 2026

Reason as filed by the promoterThe delay in starting construction was due to late approval from the PCMC,despite submitting all required documents on time. We adhered to legal requirements by waiting for formal clearance before beginning any construction activities. This delay impacted our schedule, affecting resource allocation and material procurement. Throughout the process, we proactively followed up with the authorities and promptly addressed any queries to expedite the approval. Now that approval has been granted, we are committed to fast-tracking construction while maintaining quality and compliance.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Vaishnav Gatha Firm 1.pdf2 Aug 2025
Form 2File: Vaishnav Gatha Form 2 Jun 2025.pdf2 Aug 2025
Form 3File: Form 3 Vaishnav Gatha Jun 2025.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Vaishnav Gatha Jun 25 Sold Unsold.pdf2 Aug 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 1File: 1.pdf27 Jun 2025
Form 2File: 2.pdf27 Jun 2025
Form 3File: 3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf27 Jun 2025
Form 2A (FY 2023-2024)File: 2A.pdf27 Jun 2025
Form 2A (FY 2024-2025)File: 2A 2024-25 Vaishnav Gatha.pdf27 Jun 2025
Form 5 (FY 2023-2024)File: form-5.pdf27 Jun 2025
Declaration in FORM BFile: 3 Declaration in FORM B.pdf29 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GetUserDocumentFileContent (39).pdf29 May 2025
Disclosure of sold/ booked inventoryFile: GetUserDocumentFileContent (43) (1).pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: GetUserDocumentFileContent (40).pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GetUserDocumentFileContent (40) (1).pdf29 May 2025
Declaration about Commencement CertificateFile: P52100052318_FileName_3.pdf21 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1) (1).pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaishnav Gatha (2).pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20250429182445.pdf29 Apr 2025
Declaration in FORM BFile: P52100052318_FileName_6.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20250423171551.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD VAISHNAV GAATHA Q-2 (2).pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold (10).pdf22 Apr 2025
Declaration in FORM BFile: Shall Not Affect Entry.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 20250412134136.pdf17 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 001_0001.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Mar-25 (1).pdf31 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form- 3 Jun-24 (1).pdf31 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vaishnav gaatha form-3 Q-4 23-24.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaishnav gaatha form-3 FY 24-25 Q-3.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: VAISHNAV GAATHA SALES Q-4 23-24.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 vaishnav gaatha fy 23-24.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vaishnav gaatha form-1 (1)_organized (1).pdf21 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: signed form 2 .pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: sold unsold .pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD VAISHNAV GAATHA Q-2.pdf21 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: signed form 2 .pdf17 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VAISHNAV GAATHA ENGINEERING CERTIFICATE Q-3.pdf17 Mar 2025
Layout approvalFile: Main Layout_11zon.pdf20 Feb 2025
Building plan approvalFile: Elevation Floor Plan.pdf20 Feb 2025
Copy of Layout Approval (in case of layout)File: Main Layout_11zon.pdf20 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Elevation Floor Plan.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VAISHNAV GAATHA ENGINEERING CERTIFICATE Q-3.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Sild Unsold.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20241106182147.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vaishav Gatha From 2.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD VAISHNAV GAATHA Q-2.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 with Sign.pdf10 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaishnav Gaatha form-1.pdf23 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vaishnav gatha form 2.pdf23 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf23 Dec 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf23 Dec 2023
Layout approvalFile: Main Layout.pdf21 Jun 2023

How this compares with Pune

12%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vaishnav Gaatha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali13,700+ in Pune

2 kmVaishnav GaathaCompleted 109Lapsed / revoked 47Other 69Dot size: filed unitsN

Filed coordinates, straight-line distance. 225 registered projects within 2 km.

Builder: Kalbhor Realtors And Services LLP

KALBHOR REALTORS AND SERVICES LLP has 2 registrations on MahaRERA, including GAATHA NAGAR PHASE 1 and Vaishnav Gaatha. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Vaishnav Gaatha is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vaishnav Gaatha?

The registered promoter entity is Kalbhor Realtors And Services LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vaishnav Gaatha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vaishnav Gaatha?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vaishnav Gaatha?

The professionals named in the filing: Architect: Patil & Bugade Associates; Engineer: Rohinee Engineers; Engineer: Rahul Kalbhor; Chartered Accountant: Parag S Savale & Associates; Chartered Accountant: Maheshwar Marathe. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vaishnav Gaatha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vaishnav Gaatha. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vaishnav Gaatha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.