Home / Browse projects / Pune, Maharashtra / UTSAV RESIDENCY PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

UTSAV RESIDENCY PHASE II

By ROYAL DEVELOPERS

RG-MH-38523 · RERA P52100019080 · Last updated on MahaRERA portal: 26 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 35 months past the filed date
  • Completion date moved by 26 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2023Possession promised35 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

UTSAV RESIDENCY PHASE II is a Residential / Group Housing project by ROYAL DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100019080 on 4 Jan 2019. Possession was promised by 30 Nov 2023 and is now 35 months past that date. The completion date has moved by 26 months from the original filing.

At a glance

Project

  • NameUTSAV RESIDENCY PHASE II
  • TypeResidential / Group Housing
  • Location
    • AWHALWADI ROAD
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • RERA no.P52100019080
  • ReraGenie IDRG-MH-38523

Builder

  • NameROYAL DEVELOPERS
  • Entity typePartnership
  • PartnersZENITH LANDMARKS PVT LTD, PRAVIN BANSILAL RAISONI, KUNNANPARTH ABDUL RAMEES, SURENDRA BAPUSAHEB PATHARE, PIYUSH PRAVIN RAISONI, DEEPALI RAHUL GAVHANE, VARSHA MAHESH KARPE, JYOTI RAVINDRA BHUJABAL, SANKET SAMPAT KHARPUDE
  • Other registrations16 more →
  • Completed5 of 17
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

35 months past promisethis monthRegisteredJan 2019First promiseSep 2021Revised toNov 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jan 2019
  • Promised completion30 Nov 2023
  • Revised completionRevised to 30 Nov 2023 (originally 30 Sep 2021)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING -ANA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

WING -A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed86

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots86
Open Space86

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
SANGITA RAMDAS SATAVWAGHOLIPune
RAMESH RAMDAS SATAVWAGHOLIPune
AMOL RAMDAS SATAVWAGHOLIPune

Approvals and building plan

Permissible FSI5730.88
Proposed, not sanctioned4,932 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARADI PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParvej Jamadar and Associates
Chartered AccountantBSMART and Associates LLP
PartnerRole in project
ROYAL DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013224Sep 2021 → Nov 2023

Reason as filed by the promoterMOJNI REQUIRED FOR HAVING COMPLETION CERTIFICATE PROCESS IS GOING ON

EXT52100010775Sep 2021 → Jun 2022

Reason as filed by the promoterDUE TO PANDEMIC SITUATION LABOUR, MATERIAL PROBLEMS BECOMES HURDLE, PROJECT NOW COMES IN PMC AREA MANY PERMISSIONS PENDING BY PMRDA AND ALSO NEW BOOKINGS NOT DONE THATS WHY CASH FLOW HAMPERED THE SPEED OF WORKS.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Nov 2024

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: UTSAV PHASE II FORM 4.pdf26 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Phase-II UTSAV Residency Completion Certificate.pdf12 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 29022024 Phase II.pdf18 Jun 2024
Certificates of CA (Form 3)File: Form 3 Phase II 29022024.pdf18 Jun 2024
Declaration in FORM BFile: PHASE II FROM 3.pdf11 Apr 2024
Declaration in FORM BFile: PHASE II FROM 3.pdf11 Apr 2024
Declaration in FORM BFile: PHASE II FROM 3.pdf11 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Phase II Royal Developers FY 22-23.pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera form 1.pdf15 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Utsav Residency Phase II 30092022.pdf20 Feb 2023
Certificates of CA (Form 3)File: CA Certificate PHASE II 30092022.pdf20 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Utsav Residency Phase II Form 5 21-22.pdf29 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Phase 2 SOCIETY CERTIFICATE.pdf17 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase II 31032022.pdf29 Jul 2022
Disclosure of sold/ booked inventoryFile: Circular 29 Phase II 31032022.pdf29 Jul 2022
Certificates of CA (Form 3)File: Form 3 Phase II 31032022.pdf29 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase-2_form-1_Architect_sign.pdf31 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032021 Phase II.pdf21 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Phase II FY 2021.pdf21 Feb 2022
Declaration about Commencement CertificateFile: Declaration about commencement Certificate-Phase II.pdf2 Sep 2021
Declaration about Commencement CertificateFile: COMMINCEMENT_CERTIFICATE_PHASE-2_certified_by_Architect.pdf25 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory Utsav Residency Phase II.pdf14 Aug 2021
Certificates of CA (Form 3)File: UTSAV RESIDENCY PHASE II ( FORM -3) 20032021-compressed.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Utsav Residency Phase II Engineer Certificate 31032020.pdf17 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Residncy Phase II 19-20.pdf17 May 2021
Certificates of CA (Form 3)File: UTSAV RESIDENCY Phase II 20032020.pdf10 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PHASE-2_ENGINEER_CERTIFICATE_10th_March.pdf15 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PHASE-2_ENGINEER_CERTIFICATE.pdf11 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2.pdf7 Jul 2020
Certificates of CA (Form 3)File: Form 3 Royal -Utsav Phase II 311219.pdf4 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Phase II FY 18-19.pdf4 Jul 2020
Details of Restarting of Construction work post lockdownFile: Maha RERA.pdf2 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng_II_Phase.pdf3 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: quality_ph_ii.pdf3 Feb 2020
Certificates of CA (Form 3)File: FORM 3 PHASE II Signed.pdf11 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engeer_certicicate_aminity.pdf7 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engner_certificate_phase_II.pdf7 Jun 2019
Certificates of CA (Form 3)File: CA Form 3 Phase 2 Final.pdf18 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_Phase-2.pdf17 Dec 2018
Proforma of Allotment letterFile: 2ND PHASE DRAFT.pdf11 Dec 2018
Layout approvalFile: Layout Plan.pdf8 Dec 2018
Building plan approvalFile: Sanction.pdf8 Dec 2018
Building plan approvalFile: Parking Floor Plan.pdf8 Dec 2018
Building plan approvalFile: Floor Plan G 1.pdf8 Dec 2018
Building plan approvalFile: Floor Plan 2 4 6 8.pdf8 Dec 2018
Building plan approvalFile: Floor Plan 9.pdf8 Dec 2018
Building plan approvalFile: Elevation Plan.pdf8 Dec 2018
Details of encumbrancesFile: NO ENCUMBRANCE 53R.pdf8 Dec 2018
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf8 Dec 2018
Building Plan Approval (IOD)File: Sanction.pdf8 Dec 2018
Building Plan Approval (IOD)File: Parking Floor Plan.pdf8 Dec 2018
Building Plan Approval (IOD)File: Floor Plan G 1.pdf8 Dec 2018
Building Plan Approval (IOD)File: Floor Plan 2 4 6 8.pdf8 Dec 2018
Building Plan Approval (IOD)File: Floor Plan 9.pdf8 Dec 2018
Building Plan Approval (IOD)File: Elevation Plan.pdf8 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMINCEMENT CERTIFICATE.pdf8 Dec 2018
Copy of the legal title reportFile: Tital Report 53R.pdf7 Dec 2018
Copy of the legal title reportFile: Search Report 53R.pdf7 Dec 2018
Declaration in FORM BFile: Rahul_Gavhane_B-Form_5877__1_.pdf6 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Arch Certificate 53 R.pdf30 Oct 2018
PAN CardFile: Royal Pan Card.pdf29 Aug 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
UTSAV RESIDENCYGAT NO 1127 AVHALVADI ROAD WAGHOLI PUNE174CompletedJun 2019Apr 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 26 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UTSAV RESIDENCY PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGHOLI13,700+ in Pune

Builder: ROYAL DEVELOPERS

ROYAL DEVELOPERS has 17 registrations on MahaRERA, including UTSAV RESIDENCY and Gurukripa Appartment. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that UTSAV RESIDENCY PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if UTSAV RESIDENCY PHASE II is delayed beyond 30 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UTSAV RESIDENCY PHASE II?

The registered promoter entity is ROYAL DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UTSAV RESIDENCY PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UTSAV RESIDENCY PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UTSAV RESIDENCY PHASE II?

The professionals named in the filing: Architect: Parvej Jamadar and Associates; Chartered Accountant: BSMART and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UTSAV RESIDENCY PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UTSAV RESIDENCY PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UTSAV RESIDENCY PHASE II to a free account