Home / Browse projects / Aurangabad, Maharashtra / UNITY PARK

Registered No litigation declared Residential / Group Housing project

UNITY PARK

By BAHETI LANDMARK

RG-MH-64996 · RERA P51500024945 · Last updated on MahaRERA portal: 12 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 25 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedmoved 25 months from the original
37 of 55Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 90%
23 of 45Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

UNITY PARK is a Residential / Group Housing project by BAHETI LANDMARK in Aurangabad, Maharashtra, registered with MahaRERA as P51500024945 on 12 Mar 2020. Possession is promised by 31 Jan 2027. The completion date has moved by 25 months from the original filing. 22 of the 45 units on this registration are recorded sold or booked, and 37 of 55 construction stages are filed complete.

At a glance

Project

  • NameUNITY PARK
  • TypeResidential / Group Housing
  • Location
    • TISGAON
    • NEAR MAHADA
    • Aurangabad
    • 431136
  • Pincode431136
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500024945
  • ReraGenie IDRG-MH-64996

Builder

  • NameBAHETI LANDMARK
  • Entity typePartnership
  • PartnersASHOK JAYANARAYAN BAHETI, Jayanarayan Devichand Baheti
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2020First promiseDec 2024Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Mar 2020
  • Promised completion31 Jan 2027
  • Revised completionRevised to 31 Jan 2027 (originally 30 Dec 2024)
  • Buildings5 building records
  • Documents filed94 files

Current status

49%22 of 45 units booked
59.1%Work done, per cost certificate

Figures as on 12 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A TYPE BUILDINGNA4412012
B TYPE BUILDINGNA40808
C TYPE BUILDINGNA40808
D TYPE BUILDINGNA40909
E TYPE BUILDINGNA40808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 12 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

37 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

A TYPE BUILDING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B TYPE BUILDING69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
C TYPE BUILDING80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
D TYPE BUILDING61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E TYPE BUILDING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered5
BuildingClosed/CoveredTotal
A TYPE BUILDING11
B TYPE BUILDING11
C TYPE BUILDING11
D TYPE BUILDING11
E TYPE BUILDING11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,150 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jan 2026
LandownerVillageDistrict
ANIL MURLIDHAR SONI AND OTHERAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI3068.0
Proposed, not sanctioned3,068 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear Prozone Mall Chikalthana
Estimated costRs 7.26 cr
Cost incurredRs 4.29 cr
Work done59.11%
BuildingWingEstimatedIncurred
A TYPE BUILDINGNARs 1.57 crRs 1.51 cr
E TYPE BUILDINGNARs 1.19 crRs 68.60 lakh
C TYPE BUILDINGNARs 1.19 crRs 74.70 lakh
D TYPE BUILDINGNARs 1.19 crRs 99.76 lakh
B TYPE BUILDINGNARs 1.13 crRs 10.50 lakh
-NARs 1.00 crRs 25.10 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBV RAUT RB and Associates
EngineerAjay Jadhav
Chartered AccountantSHRISH SAMDANI
Chartered AccountantSA Samdani & Company
Chartered AccountantD M Samdani & Co
PartnerRole in project
BAHETI LANDMARK-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500025499Dec 2024 → Jan 2026

Reason as filed by the promoterProject is near about to complete but for completion certificate it may take 6 Months approximately. We would like to clarify that the delay in project execution was primarily due to the COVID-19 pandemic. We were planned to start the project in 2020 but due to pandemic situation we were started the project in October 2021.

EA22012619547Dec 2024 → Jan 2027

Reason as filed by the promoterProject is near about to complete but for completion certificate it may take 6 Months approximately. We would like to clarify that the delay in project execution was primarily due to the COVID-19 pandemic. We were planned to start the project in 2020 but due to pandemic situation we were started the project in October 2021.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2027

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate June-26.pdf12 Aug 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June-26.pdf12 Aug 2026
Withdrawal Update Form 3File: Form 3 Unity Park June-26.pdf12 Aug 2026
Withdrawal Update Form 1File: Q15.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate march-26.pdf27 Apr 2026
Withdrawal Update Form 3File: From 3 CA Certificate march-26.pdf27 Apr 2026
Form 2A (FY 2020-2021)File: 20-21.pdf19 Jan 2026
Form 2A (FY 2021-2022)File: 21-22.pdf19 Jan 2026
Form 2A (FY 2022-2023)File: 22-23.pdf19 Jan 2026
Form 2A (FY 2023-2024)File: 23-24.pdf19 Jan 2026
Form 2A (FY 2024-2025)File: 24-25.pdf19 Jan 2026
Form 2A (FY 2019-2020)File: Form 2A.pdf17 Jan 2026
Form 1File: Architect certifiate Dec-25.pdf16 Jan 2026
Form 2File: Engineer Certificate Dec-25.pdf16 Jan 2026
Form 3File: Form 3 Unity Park Dec-25.pdf16 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Dec-2025.pdf16 Jan 2026
Form 1File: Architect Certificate Sep-25.pdf15 Nov 2025
Form 2File: Engineer Certificate Sep-25.pdf15 Nov 2025
Form 3File: Form 3 Unity Park Sep-25.pdf15 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold & Booked Unit Sep-25.pdf15 Nov 2025
Form 1File: Form 1 Unity Park June-25.pdf24 Jul 2025
Form 2File: Form 2 Engineer Certificate June-25.pdf24 Jul 2025
Form 3File: Form 3 Unity Park June 25.pdf24 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-unsold inventory June-25.pdf24 Jul 2025
Form 5 (FY 2024-2025)File: Unity Park Form 5 24-25.pdf24 Jul 2025
Form 1File: Architech Certificate Nov-24.pdf18 Jul 2025
Form 2File: Engineer Certificate Form 2.pdf18 Jul 2025
Form 3File: Annxure D Form 3.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unslod Inventory till Nov-24.pdf18 Jul 2025
Form 1File: Architect Certificate March-25.pdf18 Jul 2025
Form 2File: Engineer Certificate March-25.pdf18 Jul 2025
Form 3File: Unity Park form 31 March-25.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Data March-25.pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Unity Park form 3 March-25.pdf10 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Unity Park Form 5 24-25.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate March-25.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate March-25.pdf6 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Certificate 24-25.pdf6 May 2025
OtherFile: Clarification about delay.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate Nov-24.pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annxure D Form 3.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unslod Inventory till Nov-24.pdf16 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate Form 2.pdf16 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate.pdf16 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Audit Report Form 5.pdf16 Dec 2024
Declaration in FORM BFile: Form B Affidavit.pdf14 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: from 2 may 2020.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q5.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q6.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q7.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q8.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q9.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q10.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q11.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q12.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q13.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q14.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q15.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 may 2020.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 aug 2020.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2nov 2020.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 feb 2021.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 may 2021.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 aug 2021.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 nov 2021.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 feb 2022.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 may 2022.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 aug 2022.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 nov 2022.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 feb 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: from 2 may 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 aug 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 nov 2023.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Unslod Inventory till March 2022.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5 20-21.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 21-22.pdf11 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SKY CITYSATARA28CompletedMar 2021Oct 2019

How this compares with Aurangabad

49%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 25 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep UNITY PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR MAHADA1,400+ in Aurangabad

2 kmUNITY PARKCompleted 24Lapsed / revoked 9Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: BAHETI LANDMARK

BAHETI LANDMARK has 1 registration on MahaRERA, including UNITY PARK. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if UNITY PARK is delayed beyond 31 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UNITY PARK?

The registered promoter entity is BAHETI LANDMARK, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UNITY PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UNITY PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UNITY PARK?

The professionals named in the filing: Architect: BV RAUT RB and Associates; Engineer: Ajay Jadhav; Chartered Accountant: SHRISH SAMDANI; Chartered Accountant: SA Samdani & Company; Chartered Accountant: D M Samdani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNITY PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNITY PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNITY PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.