ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / UNIQUE PRIDE

Completed No litigation declared Residential / Group Housing project

UNIQUE PRIDE

By AKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE

RG-MH-23056 · RERA P52700032387 · Last updated on MahaRERA portal: 28 Mar 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

UNIQUE PRIDE is a Residential / Group Housing project by AKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE in Satara, Maharashtra, registered with MahaRERA as P52700032387 on 4 Jan 2022. The registration is recorded completed; possession was promised by 31 Dec 2024.

At a glance

Project

  • NameUNIQUE PRIDE
  • TypeResidential / Group Housing
  • Location
    • ITI ROAD
    • MOLACH ODHA
    • Karanje Tarf Satara (CT)
    • Satara
    • 415002
  • Pincode415002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700032387
  • ReraGenie IDRG-MH-23056

Builder

  • NameAKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE
  • Entity typeIndividual
  • GSTIN27ADXPL1225A2ZP
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2022PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Jan 2022
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Unique PrideNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Unique Pride: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area320 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MR SADASHIV DNYANOBA BACHALKoregaon (CT)Satara

Approvals and building plan

Permissible FSI714.9
Proposed, not sanctioned715 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUTHA CHOWK NEAR SANJEEVANI HOSPITAL SADARBAZAR SATARA

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Sumit Bagade
EngineerShreeram Kulkarni
Chartered AccountantMangesh Pradhan
PartnerRole in project
AKSHAD INFRASTRUCTURE AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Aug 2023

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: FULL OCCUPANCY CERTIFICATE-.pdf28 Mar 2026
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM -4 FOR ( UNIQUE PRIDE ).pdf28 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA_CERTIFICATE_R5_SUNIL_LANDAGE_31-01-2023[1].pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DocScanner Feb 2, 2023 5-26 PM.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE_R4_SUNIL LANDAGE_14-10-2022-compressed.pdf8 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg-compressed.pdf8 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE_R3_SUNIL LANDAGE_17-08-2022.pdf3 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICAT.pdf3 Sep 2022
Disclosure of sold/ booked inventoryFile: sold N unsold.pdf3 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 16062022 jan to marc.pdf3 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 27082022arp to jun.pdf3 Sep 2022
Details of encumbrances concerned to LegalFile: encumbranc.pdf20 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cerf.pdf20 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certfc.pdf20 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FINAL CA CERTIFICATE_compressed_11zon.pdf20 Aug 2022
Copy of the legal title reportFile: LEGAL Search report.pdf28 Dec 2021
Declaration in FORM BFile: Sunil.pdf28 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA cirtificate.pdf20 Dec 2021
Declaration about Commencement CertificateFile: 32 Decleretion.pdf18 Dec 2021
Proforma of Allotment letterFile: ATS BLANK FORMAT.pdf18 Dec 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf18 Dec 2021
Building plan approvalFile: NA order.pdf17 Dec 2021
Layout approvalFile: scan0580 compress layout.pdf17 Dec 2021
Building plan approvalFile: Layout plan 1 mb.pdf17 Dec 2021
PAN CardFile: SUNIL PAN.pdf17 Dec 2021
Details of encumbrancesFile: ENCOBRNC-converted.pdf17 Dec 2021
Copy of Layout Approval (in case of layout)File: scan0580 compress layout.pdf17 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: NA order.pdf17 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Layout plan 1 mb.pdf17 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Order.pdf17 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report.pdf17 Dec 2021

How this compares with Satara

16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep UNIQUE PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOLACH ODHA1,100+ in Satara

2 kmUNIQUE PRIDECompleted 12Lapsed / revoked 22Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: AKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE

AKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE has 1 registration on MahaRERA, including UNIQUE PRIDE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if UNIQUE PRIDE is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UNIQUE PRIDE?

The registered promoter entity is AKSHAD INFRASTRUCTURE AND DEVELOPERS THROUGH ITS PROPRIETOR MR SUNIL MOHAN LANDAGE, an individual as per the filing. Its GSTIN 27ADXPL1225A2ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UNIQUE PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UNIQUE PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UNIQUE PRIDE?

The professionals named in the filing: Architect: Mr Sumit Bagade; Engineer: Shreeram Kulkarni; Chartered Accountant: Mangesh Pradhan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNIQUE PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNIQUE PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNIQUE PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.