ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / SHREE VIHAR

Registered No litigation declared Residential / Group Housing project

SHREE VIHAR

By M/s SHREE SAIDARSHAN DEVELOPERS

RG-MH-17515 · RERA P52700029745 · Last updated on MahaRERA portal: 2 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 16 months from the original
9 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 88%
45 of 78Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

SHREE VIHAR is a Residential / Group Housing project by M/s SHREE SAIDARSHAN DEVELOPERS in Satara, Maharashtra, registered with MahaRERA as P52700029745 on 29 Jun 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 16 months from the original filing. 33 of the 78 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREE VIHAR
  • TypeResidential / Group Housing
  • Location
    • -
    • KARANGE
    • Karanje Tarf Satara (CT)
    • Satara
    • 415002
  • Pincode415002
  • RERA no.P52700029745
  • ReraGenie IDRG-MH-17515

Builder

  • NameM/s SHREE SAIDARSHAN DEVELOPERS
  • Entity typePartnership
  • PartnersJANARDHAN KASHIRAM MANE, SANTOSH ASHOK SATARKAR, GANESH BALIRAM GUJAR, MUKESH BALASAHEB MAHAMULKAR, SAGAR CHANDRAKANT GOLE, DARSHANA VISHAL BHOSALE

Key dates

this monthRegisteredJun 2021First promiseNov 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jun 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Nov 2025)
  • Buildings2 building records
  • Documents filed61 files

Current status

42%33 of 78 units booked
65.1%Work done, per cost certificate

Figures as on 2 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A AND BNA7648048
WING C AND DNA5430030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 88%.

WING A AND B71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C AND D54%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises72%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Aug 2025
LandownerVillageDistrict
SHREE VIHARSataraSatara

Approvals and building plan

Sanctioning authoritySATARA NAGAR PARISHAD, SATARA
Permissible FSI5224.28
Proposed, not sanctioned5,224 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOTI CHOWK SATAR
Estimated costRs 18.82 cr
Cost incurredRs 12.25 cr
Work done65.08%
BuildingWingEstimatedIncurred
WING A AND BNARs 9.18 crRs 6.00 cr
WING C AND DNARs 9.18 crRs 6.00 cr
-NARs 47.00 lakhRs 25.00 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUMIT SHIVAJI BAGADE
EngineerSHWETA S PATIL
EngineerSHAMBHURAJ PATIL
Chartered AccountantS M RAJHANS AND CO
Chartered AccountantTRIPTI PIMPALKAR
Chartered Accountantshripad durgawade
PartnerRole in project
M/s SHREE SAIDARSHAN DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27022620041Nov 2025 → Mar 2027

Reason as filed by the promoterDue to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/03/2027 to complete the project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SHREE VIHAR (1).pdf2 May 2026
Withdrawal Update Form 2File: SHREE VIHAR (2).pdf2 May 2026
Withdrawal Update Form 3File: SHREE VIHAR.pdf2 May 2026
Withdrawal Update Form 1File: ART.pdf30 Apr 2026
Withdrawal Update Form 230 Apr 2026
Withdrawal Update Form 3File: Registration Application Form3-7.pdf30 Apr 2026
Form 1File: FORM 1.pdf29 Jan 2026
Form 2File: FORM2.pdf29 Jan 2026
Form 3File: FORM3.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: SHREE VIHAR SOLD UNSOLD.pdf29 Jan 2026
Form 1File: FORM 1_page-0001.pdf29 Jan 2026
Form 2File: FORM 2.pdf29 Jan 2026
Form 3File: FORM3_page-0001.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: SHREE VIHAR SOLD UNSOLD_page-0001.pdf29 Jan 2026
Form 1File: 30032023.pdf22 Aug 2025
Form 2File: 30032023.pdf22 Aug 2025
Form 3File: FROM NO 3(22-23).pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UN SOLD 1-4-2023 to 31-3-2024.pdf22 Aug 2025
Form 1File: 30032024.pdf22 Aug 2025
Form 2File: 30032024.pdf22 Aug 2025
Form 3File: FROM NO (23-24).pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UN SOLD 1-4-2023 to 31-3-2024.pdf22 Aug 2025
Form 1File: 30032025.pdf22 Aug 2025
Form 2File: 30032025.pdf22 Aug 2025
Form 3File: FROM NO 3 (24-25).pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UN SOLD 1-4-2024 to 31-3-2025.pdf22 Aug 2025
Form 1File: 30062025.pdf22 Aug 2025
Form 2File: 30062025.pdf22 Aug 2025
Form 3File: FROM NO 3(apr25-jun25).pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UN SOLD 1-4-2025 to 30-6-2025.pdf22 Aug 2025
Form 2A (FY 2024-2025)File: 0 (24).pdf22 Aug 2025
Form 2A (FY 2023-2024)File: 0 (24).pdf22 Aug 2025
Form 5 (FY 2024-2025)File: 0 (22).pdf22 Aug 2025
Form 5 (FY 2023-2024)File: 0 (23).pdf22 Aug 2025
Layout approvalFile: 1-3.pdf25 Jun 2021
Layout approvalFile: 2-3.pdf25 Jun 2021
Layout approvalFile: 3-3.pdf25 Jun 2021
Copy of Layout Approval (in case of layout)File: 1-3.pdf25 Jun 2021
Copy of Layout Approval (in case of layout)File: 2-3.pdf25 Jun 2021
Copy of Layout Approval (in case of layout)File: 3-3.pdf25 Jun 2021
Declaration in FORM BFile: hanumant kirdat.pdf25 Jun 2021
Declaration in FORM BFile: siya kirdat.pdf25 Jun 2021
Declaration in FORM BFile: maruti kirdat b form.pdf25 Jun 2021
Declaration in FORM BFile: vaishali kirdat.pdf25 Jun 2021
Declaration in FORM BFile: shrirang.pdf25 Jun 2021
Declaration in FORM BFile: PROMOTAR B.pdf25 Jun 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf25 Jun 2021
Building plan approvalFile: 2-3.pdf24 Jun 2021
Building plan approvalFile: 2-3.pdf24 Jun 2021
Building plan approvalFile: 3-3.pdf24 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: 2-3.pdf24 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: 2-3.pdf24 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: 3-3.pdf24 Jun 2021
Declaration in FORM BFile: dilip kirdat.pdf24 Jun 2021
Proforma of Allotment letterFile: Draft Agreement for Sale.pdf24 Jun 2021
Copy of the legal title reportFile: full adv.pdf23 Jun 2021
Declaration about Commencement CertificateFile: final comm certif.pdf23 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ART.pdf16 Jun 2021
Details of encumbrancesFile: encumbrance.pdf15 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf15 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: PERMTION.pdf14 Jun 2021

How this compares with Satara

42%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 16 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep SHREE VIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARANGE1,100+ in Satara

Builder: M/s SHREE SAIDARSHAN DEVELOPERS

M/s SHREE SAIDARSHAN DEVELOPERS has 1 registration on MahaRERA, including SHREE VIHAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if SHREE VIHAR is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE VIHAR?

The registered promoter entity is M/s SHREE SAIDARSHAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE VIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE VIHAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE VIHAR?

The professionals named in the filing: Architect: SUMIT SHIVAJI BAGADE; Engineer: SHWETA S PATIL; Engineer: SHAMBHURAJ PATIL; Chartered Accountant: S M RAJHANS AND CO; Chartered Accountant: TRIPTI PIMPALKAR; Chartered Accountant: shripad durgawade. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE VIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE VIHAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE VIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.