Home / Browse projects / Satara, Maharashtra / KRISHNAKUNJ VIHAR PHASE-3
KRISHNAKUNJ VIHAR PHASE-3
RG-MH-52447 · RERA P52700050176 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 17 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KRISHNAKUNJ VIHAR PHASE-3 is a Residential / Group Housing project by Pooja Shridhar Kangralkar in Satara, Maharashtra, registered with MahaRERA as P52700050176 on 21 Mar 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 17 months from the original filing. 54 of the 80 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete.
At a glance
Project
- NameKRISHNAKUNJ VIHAR PHASE-3
- TypeResidential / Group Housing
- Location
- KARANJE TARF
- Karanje Tarf Satara (CT)
- Satara
- 415002
- Pincode415002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700050176
- ReraGenie IDRG-MH-52447
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on21 Mar 2023
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 1 Jan 2025)
- Buildings4 building records
- Documents filed71 files
Current status
Figures as on 6 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KRISHNA-8 | NA | 7 | 5 | 20 | 0 | 20 |
| KRISHNA-9 | NA | 7 | 5 | 20 | 0 | 20 |
| KRISHNA-10 | NA | 7 | 5 | 20 | 0 | 20 |
| KRISHNA-11 | NA | 7 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.
KRISHNA-872%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
KRISHNA-972%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
KRISHNA-1044%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
KRISHNA-1144%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 20% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed152
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| KRISHNA-8 | 38 | 38 |
| KRISHNA-9 | 38 | 38 |
| KRISHNA-10 | 38 | 38 |
| KRISHNA-11 | 38 | 38 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | BHALACHANDRAA A BIRJE |
| Engineer | HANMANT B JADHAV |
| Chartered Accountant | CA NIKHIL TANKSALE |
| Partner | Role in project |
|---|---|
| Pooja Shridhar Kangralkar | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe had got phase 3 registration for our four buildings. Out of these four building we have nearly complete our building K8 and K9 for the balance work of these building we required time till March 2025 . But for reaming two buildings i.e. K10 and K11as slab in superstructure are going on till date for the completion of these building we will required time till December 2025 in same duration we will complete all other Common areas And Facilities, Amenities work. After that we will apply for OC and try to get it till March 2026, as this is our last Phase of project Planning Authority Might requi
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form no 1.pdf | 6 May 2026 |
| Form 2File: form no 2.pdf | 6 May 2026 |
| Form 3File: form no 3.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: sold.pdf | 6 May 2026 |
| Form 1File: arch.pdf | 20 Jan 2026 |
| Form 2File: engineer.pdf | 20 Jan 2026 |
| Form 3File: ca.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold.pdf | 20 Jan 2026 |
| Form 1File: FORM 1.pdf | 20 Oct 2025 |
| Form 2File: FORM 2.pdf | 20 Oct 2025 |
| Form 3File: FORM 3.pdf | 20 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD.pdf | 20 Oct 2025 |
| Form 1File: ARCH.pdf | 20 Oct 2025 |
| Form 2File: ENGG.pdf | 20 Oct 2025 |
| Form 3File: CA.pdf | 20 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD.pdf | 20 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_Phase.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_Certificate_Phase_.pdf | 20 Apr 2025 |
| Declaration in FORM BFile: form b.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY 18-10-2024.PDF | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY 21-12-2024.PDF | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY 31-12-2024 - Copy.PDF | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH PHASE 3.pdf | 23 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA PHASE 3.pdf | 23 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG PHAESE 3.pdf | 23 Jan 2025 |
| Declaration in FORM BFile: FORM B.PDF | 23 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PHASE 3 ARCHITECH CERTIFICATE.pdf | 21 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase -3 Form 3.pdf | 21 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase 3 Engineers Certificate.pdf | 21 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Phase -3 Form 5.pdf | 21 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 21 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS_CERTIFICATE.pdf | 21 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 21 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE PHASE-3.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engieer DEC 23.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.PDF | 20 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual report on statement of account phase -3.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 20 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality_Phase-3.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 1.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE PHASE-3.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE PHASE -3.pdf | 20 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE CERTIFICATE PHASE-3.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE PHASE 3 20.pdf | 20 Apr 2023 |
| Declaration about Commencement CertificateFile: DEC COMMENCEMENT DEC.pdf | 14 Mar 2023 |
| Proforma of Agreement for saleFile: model form of agreement ind.pdf | 14 Mar 2023 |
| Layout approvalFile: layout.pdf | 13 Mar 2023 |
| Layout approvalFile: phase wise layout.pdf | 13 Mar 2023 |
| Building plan approvalFile: 10-11.pdf | 13 Mar 2023 |
| Building plan approvalFile: 8-9.pdf | 13 Mar 2023 |
| PAN CardFile: 1 PAN Card Pooja k.pdf | 13 Mar 2023 |
| Copy of the legal title reportFile: search.pdf | 13 Mar 2023 |
| Copy of the legal title reportFile: search 1.pdf | 13 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: encum.pdf | 13 Mar 2023 |
| Details of encumbrances concerned to LegalFile: encum.pdf | 13 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 13 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: phase wise layout.pdf | 13 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 10-11.pdf | 13 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 8-9.pdf | 13 Mar 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf | 13 Mar 2023 |
| Declaration in FORM BFile: FORM-B.pdf | 13 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE PHASE3.pdf | 13 Mar 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200261481462_For_Asset_Based_Search_27_02_2023_16_27_05_863.pdf | 13 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca.pdf | 13 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INT.PDF | 13 Mar 2023 |
| Proforma of Allotment letterFile: allotment.pdf | 13 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACC.PDF | 13 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: DEC DEVI ALLOTMENT.PDF | 13 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEC DEVI - AGREEMENT.PDF | 13 Mar 2023 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Ayodhya Nagari | s no 298 Hissa no 3 Plot No. 1 & 2 | 128 | Completed | Jul 2013 | Jun 2013 |
| Ayodhya Nagari | S no 298 Hissa no 3 Plot No 1 & 2 Satara | 128 | Completed | Jul 2013 | Jun 2013 |
| Ayodhya Nagari | S no 298 Hissa no 3 Plot No. 1 & 2 | 128 | Completed | Jul 2013 | Jun 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KRISHNAKUNJ VIHAR PHASE-3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KARANJE TARF1,100+ in Satara
Filed coordinates, straight-line distance. 100 registered projects within 2 km.
Sukhodayam Villas
M/s Ultra Urban Greene Realty LLP
YASHWANT ELITE
RAHULDEV PROMOTERS SATARA
SHATAKSHI TOWER
VISHAL DILIP PAWAR
SHREE VIHAR
M/s SHREE SAIDARSHAN DEVELOPERS
SHIVSAMARTH RESIDENCY
MS BHOSALE AND NALAWADE
SKYVIEW TOWERS
Rajan Namdeo Pore
See every Satara project, with the district possession charts
Builder: Pooja Shridhar Kangralkar
Pooja Shridhar Kangralkar has 3 registrations on MahaRERA, including Krishnakunj Vihar Phase-1 and Krishnakunj Vihar Phase-2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What does it mean that KRISHNAKUNJ VIHAR PHASE-3 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KRISHNAKUNJ VIHAR PHASE-3 is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KRISHNAKUNJ VIHAR PHASE-3?
The registered promoter entity is Pooja Shridhar Kangralkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KRISHNAKUNJ VIHAR PHASE-3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KRISHNAKUNJ VIHAR PHASE-3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KRISHNAKUNJ VIHAR PHASE-3?
The professionals named in the filing: Architect: BHALACHANDRAA A BIRJE; Engineer: HANMANT B JADHAV; Chartered Accountant: CA NIKHIL TANKSALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRISHNAKUNJ VIHAR PHASE-3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback