Home / Browse projects / Mumbai Suburban, Maharashtra / UK Iridium
UK Iridium
By Damodar Suruchi Developers Pvt. Ltd.
RG-MH-26231 · RERA P51800007275 · Last updated on MahaRERA portal: 6 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 24 months past the filed date
- 45 complaints at MahaRERA
- Completion date moved by 10 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
UK Iridium is a Others project by Damodar Suruchi Developers Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007275 on 17 Aug 2017. Possession was promised by 12 Oct 2024 and is now 24 months past that date. The completion date has moved by 10 months from the original filing. 45 complaints are on record with the regulator.
At a glance
Project
- NameUK Iridium
- TypeOthers
- Location
- near
- Akurli Road
- Lokhandwala Twp
- Kandivali East
- Borivali
- Mumbai Suburban
- 400101
- Pincode400101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007275
- ReraGenie IDRG-MH-26231
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion12 Oct 2024
- Revised completionRevised to 12 Oct 2024 (originally 30 Dec 2023)
- Buildings2 building records
- Documents filed141 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | NA | 32 | 0 | 0 | 0 | 0 |
| Tower 2 | NA | 32 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 6 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.
Tower 184%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Tower 287%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities19
As on 6 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 30% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Grand Entrance Gate | Yes | 0% |
| CCTV Surveillance | No | Not applicable |
| Entrance Lounge | Yes | 50% |
| Fountain Waterfall at Main entrance | No | Not applicable |
Parking filed153
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Tower 1 | 98 | 98 |
| Tower 2 | 55 | 55 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Damodar Suruchi Developers Private Limited | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shantanoo Rane and Associates |
| Engineer | Mr. Avadhoot Pai |
| Engineer | JW Consultants |
| Partner | Role in project |
|---|---|
| Damodar Suruchi Developers Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe were not able to complete the project within the timelines because of force majeure reasons and other reasons as mentioned in Form E
Complaints filed with MahaRERA45
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000480080 | Sachin Babu Gurav | DAMODAR SURUCHI DEVELOPERS PVT. LTD. | 14/04/2024 |
| CC006000000001233 | sanjiv gil | Damodar Suruchi Developers | 11/10/2017 |
| CC006000000012681 | Tushant Tukaram Malke | Damodar Suruchi Developers | 04/01/2018 |
| CC006000000054770 | Doli Panchal | Damodar Suruchi Developers | 08/07/2018 |
| CC006000000078501 | HARMEET KAUR ARORA | DAMODAR SURUCHI DEVELOPER | 19/03/2019 |
| CC006000000100204 | Harmeet Kaur Arora | Damodar Suruchi Developer | 02/08/2019 |
| CC006000000079504 | SUDARSHAN R. CHAURASIYA | DAMODAR SURUCHI DEVELOPERS | 28/05/2019 |
| CC006000000194302 | Sushma Mahendra Shetty | Damodar Suruchi Developers | 15/10/2020 |
| CC006000000428762 | DAYANAND PANDHARINATH KAMBLE | Damodar Suruchi Developers | 08/01/2024 |
| CC006000000428776 | Sunil Samatkar | Damodar Suruchi Developers | 13/01/2024 |
| CC006000000480144 | Sumet Sadanand Bagwe | Damodar Suruchi Developers Pvt Ltd | 04/06/2024 |
| CC006000000439651 | Ajay Harilal Kanojia | Damodar Suruchi Builder Private Limted | 10/04/2024 |
| CC006000000479832 | SWAPNILKUMAR PANDURANG LAKADE | DAMODAR SURUCHI DEVELOPERS PVT. LTD | 21/04/2024 |
| CC006000000479971 | GANESH ANAND ZINGADE | M/s. Damodar Suruch iDevelopers | 06/04/2024 |
| CC006000000479972 | GANGARAM ANAND ZINGADE | M/s. Damodar Suruchi Developers | 06/04/2024 |
| CC006000000479984 | Jayant Prakash | Damodar Suruchi Developers Private Limited | 10/04/2024 |
| CC006000000480011 | RAMESH DEVIDAS WANKHEDE | DAMODAR SURUCHI DEVELOPERS PVT. LTD. | 12/05/2024 |
| CC006000000480111 | Premprakash Mannulal Mourya | Damodar Suruchi Developers Pvt Ltd | 23/04/2024 |
| CC006000000480170 | Shalaka Vijay Kulkarni | Damodar Suruchi Developers Private Limited | 21/04/2024 |
| CC006000000480175 | Jitesh Madhukar Patil | Damodar Suruchi Developers Pvt. Ltd. | 23/04/2024 |
| CC006000000480183 | Nagesh Manohar Lotlikar | Damodar Suruchi Developers Pvt. Ltd. | 01/05/2024 |
| CC006000000480184 | SRNIBAS PARIDA | Damodar Suruchi Developers Pvt. Ltd. | 28/04/2024 |
| CC006000000480320 | Sachin Prakash Tanavade | Damodar Suruchi Developers | 05/05/2024 |
| CC006000000480376 | Atul Bhogilal Solanki | M/s Damodar Suruchi Developers | 06/05/2024 |
| CC006000000500592 | Shivdas Tekke Madham | Shivdas Madham | 27/05/2024 |
| CC006000000570798 | kishor Vishnu Suryavanshi | DAMODAR SURUCHI DEVELOPERS PVT. LTD | 18/06/2024 |
| CC006000000570813 | TUSHARKUMAR JAGDISHCHANDRA JOSHI | DAMODAR SURUCHI DEVELOPERS PVT. LTD | 18/06/2024 |
| CC12400416 | Prashant Parasnath Gupta | Damodar Suruchi Developers Pvt. Ltd. | 15/10/2024 |
| CC12400759 | Jatin Sunil Agrawal | Damodar Suruchi Developers Pvt. Ltd. | 13/11/2024 |
| CC12401118 | Chirag Pramod Panchal | Damodar Suruchi Developers Pvt. Ltd. | 13/12/2024 |
| CC12400812 | rahul surendra yadav | Damodar Suruchi Developers Pvt. Ltd. | 18/11/2024 |
| CC12400860 | DATTATRAY VISHWANATH MASURKAR | Damodar Suruchi Developers Pvt. Ltd. | 23/11/2024 |
| CC12401055 | SIDDHARTH VIJAY KUMAR JAIN | Damodar Suruchi Developers Pvt. Ltd. | 06/12/2024 |
| CC12401104 | Pramodkumar Laxman Dahanukar | Damodar Suruchi Developers Pvt. Ltd. | 12/12/2024 |
| CC12401209 | Kiran Balkrishna Valanger | Damodar Suruchi Developers Pvt. Ltd. | 23/12/2024 |
| CC12500299 | Sunilkumar Rana | Damodar Suruchi Developers Pvt. Ltd. | 27/01/2025 |
| CC12500477 | Vimal Desai | Damodar Suruchi Developers Pvt. Ltd. | 12/02/2025 |
| CC12500796 | Devendra Pratap Singh | Damodar Suruchi Developers Pvt. Ltd. | 08/03/2025 |
| CC12501179 | Devendra Pratap Singh | Damodar Suruchi Developers Pvt. Ltd. | 08/04/2025 |
| CC12502204 | Archana Rahul Sapkal | Damodar Suruchi Developers Pvt. Ltd. | 03/07/2025 |
| CC12504637 | RAMSINGH SURENDRAPRATAP YADAV | Damodar Suruchi Developers Pvt. Ltd. | 26/12/2025 |
| CC12601108 | Sanjay Pandurang Rane | Damodar Suruchi Developers Pvt. Ltd. | 01/03/2026 |
| CC12603908 | Damodar Suruchi Developers Pvt. Ltd. | MS PUSHTAM SUNIL RAI | 24/06/2026 |
| CC12604110 | Damodar Suruchi Developers Pvt. Ltd. | MR BHUPENDRA AWADHRAJ SINGH | 01/07/2026 |
| CC12604157 | Damodar Suruchi Developers Pvt. Ltd. | MR BHUPENDRA AWADHRAJ SINGH | 03/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 8 May 2024
Documents filed141
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: UK IRIDIUM Disclosure April to June 2024.pdf | 6 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng cert UK Iridium MAR 2024.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: Form No 3 UK Iridium BCD Wing MAR 2024.pdf | 4 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: UK Iridium Sale Building Wing BCD OC dated 6th May 2024.pdf | 8 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A UK IRIDIUM B C D Wing.pdf | 17 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: RERA Disclosure UK Iridium BCD Wing-2024_compressed.pdf | 17 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UK IRIDIUM BCD WING FORM 1 JAN 2024 - MAR 2024.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Oct 2023 to Dec 2023.pdf | 23 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng cert UK Iridium OCT to DEC 2023.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 Uk Iridium BCD Wing Oct to Dec 2023.pdf | 19 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IRIDIUM BCD Wing Oct to Dec 2023.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 UK Iridium BCD Wing 300623.pdf | 23 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 UK Iridium BCD Wing 300923.pdf | 23 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A UK IRIDIUM BCD WING 2021 TO 2022.pdf | 22 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A UK IRIDIUM BCD WING 2022 TO 2023.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing till Dec 2021 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Jan 2022 to March 2022 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing April 2022 to June 2022 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing July 2022 to Sep 2022 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Oct 2022 to Dec 2022 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Jan 2023 to March 2023 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing April 2023 to June 2023 final.pdf | 22 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing July 2023 to Sep 2023 final.pdf | 22 Nov 2023 |
| Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_310323.pdf | 22 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 2023 BCD Wing.pdf | 21 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2023 BCD Wing.pdf | 21 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 September 2023 BCD Wing.pdf | 21 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Uk iridium BCD 2022 to 2023.pdf | 21 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD March.pdf | 18 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD June.pdf | 18 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD September.pdf | 18 Nov 2023 |
| Declaration in FORM BFile: Affidavit Cum Decalaration FORM B UK IRIDIUM_compressed.pdf | 8 Nov 2023 |
| Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_300622_Compressed.pdf | 25 Mar 2023 |
| Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_300922_Compressed.pdf | 25 Mar 2023 |
| Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_311222_Compressed.pdf | 25 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 10 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 10 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 10 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 10 Feb 2023 |
| Details of encumbrancesFile: RERA - Details of Encumbrances - Iridium.pdf | 26 Apr 2022 |
| Details of encumbrancesFile: DHFL- No Due certificate.pdf | 25 Apr 2022 |
| OtherFile: Harmeet Arora - RERA.pdf | 28 Mar 2022 |
| OtherFile: Approval through Email by Mohun Rao.pdf | 22 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC For UK Iridium.pdf | 16 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Iridium.pdf | 16 Dec 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK IRIDIUM ENGINEERS CERTIFICATE.pdf | 16 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: UK Iridium Form 24.pdf | 16 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: UK Iridium Form-24 for RERA (5).pdf | 16 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventories Iridium.pdf | 16 Dec 2021 |
| Certificates of CA (Form 3)File: Form No 3 UK Iridium.pdf | 16 Dec 2021 |
| Certificates of CA (Form 3)File: Form No 3 UK Iridium.pdf | 16 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 UK Iridium 2018.pdf | 16 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form No 5 UK Iridium 2019.pdf | 16 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_UK_Irdium_2020-21.pdf | 16 Dec 2021 |
| Layout approvalFile: jpg2pdf (3).pdf | 7 Dec 2021 |
| Layout approvalFile: jpg2pdf (3).pdf | 7 Dec 2021 |
| PAN CardFile: Damodar Pvt Ltd - Pan Card-converted.pdf | 7 Dec 2021 |
| PAN CardFile: Damodar Pvt Ltd - Pan Card-converted.pdf | 7 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: jpg2pdf (3).pdf | 7 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: jpg2pdf (3).pdf | 7 Dec 2021 |
| Declaration about Commencement CertificateFile: declaration for cc-pdf.pdf | 7 Dec 2021 |
| Declaration in FORM BFile: self declaration - Iridium - DSD to DSDPL.pdf | 7 Dec 2021 |
| Declaration in FORM BFile: Affidavit Cum Declaration UK Iridium.pdf | 7 Dec 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK Iridium Form-24 for RERA (2).pdf | 7 Dec 2021 |
| OtherFile: CERTIFICATE OF INCORPORATION.PDF | 7 Dec 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK Iridium- Engineer Certificate.pdf | 18 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5-2018-2019.pdf | 14 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 2019 to 2020.pdf | 14 Sep 2021 |
| Building plan approvalFile: IOD.pdf | 6 Sep 2021 |
| Layout approvalFile: LAYOUT PLAN-1.pdf | 6 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN-1.pdf | 6 Sep 2021 |
| Building Plan Approval (IOD)File: IOD.pdf | 6 Sep 2021 |
| Certificates of CA (Form 5)File: Form 5.pdf | 6 Sep 2021 |
| PAN CardFile: Pan Card Letter.pdf | 25 Aug 2021 |
| Proforma of Allotment letterFile: AFS-25-08-2021.pdf | 25 Aug 2021 |
| Building plan approvalFile: IOA.pdf | 13 Jul 2021 |
| Building Plan Approval (IOD)File: IOA.pdf | 13 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera_Certificate_form.pdf | 31 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 141 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep UK Iridium on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kandivali East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 131 registered projects within 2 km.
Sheetal Uptown
SIDHESHWAR LIFESPACES PRIVATE LIMITED
ENSO SANZA
Sai Aastha Developers
SPRINGWOODS
PRATIK CONSTRUCTION
Godrej Nest
Shivam Megastructures Pvt Ltd
PATON TOWERS
PRAVIN VIRAM SATRA
Godrej Bliss
SHIVAM DEVELOPERS
See every Mumbai Suburban project, with the district possession charts
Builder: Damodar Suruchi Developers Pvt. Ltd.
Damodar Suruchi Developers Pvt. Ltd. has 3 registrations on MahaRERA, including UK Iridium and UK LUXECITY. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that UK Iridium shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if UK Iridium is delayed beyond 12 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of UK Iridium?
The registered promoter entity is Damodar Suruchi Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in UK Iridium?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against UK Iridium?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for UK Iridium?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at UK Iridium?
The professionals named in the filing: Architect: Shantanoo Rane and Associates; Engineer: Mr. Avadhoot Pai; Engineer: JW Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in UK Iridium?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback