Home / Browse projects / Mumbai Suburban, Maharashtra / UK Iridium

Registration lapsed No litigation declared Others project

UK Iridium

By Damodar Suruchi Developers Pvt. Ltd.

RG-MH-26231 · RERA P51800007275 · Last updated on MahaRERA portal: 6 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 24 months past the filed date
  • 45 complaints at MahaRERA
  • Completion date moved by 10 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2024Possession promised24 months past this date
15 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 80%
45Complaints at MahaRERAon this registration
Jump to the 141 documents Report an error

UK Iridium is a Others project by Damodar Suruchi Developers Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007275 on 17 Aug 2017. Possession was promised by 12 Oct 2024 and is now 24 months past that date. The completion date has moved by 10 months from the original filing. 45 complaints are on record with the regulator.

At a glance

Project

  • NameUK Iridium
  • TypeOthers
  • Location
    • near
    • Akurli Road
    • Lokhandwala Twp
    • Kandivali East
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007275
  • ReraGenie IDRG-MH-26231

Builder

  • NameDamodar Suruchi Developers Pvt. Ltd.
  • Entity typeCompany
  • DirectorDevanshu Dinesh Bansal
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

24 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toOct 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion12 Oct 2024
  • Revised completionRevised to 12 Oct 2024 (originally 30 Dec 2023)
  • Buildings2 building records
  • Documents filed141 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA320000
Tower 2NA320000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

Tower 184%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Tower 287%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities19

As on 6 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Grand Entrance GateYes0%
CCTV SurveillanceNoNot applicable
Entrance LoungeYes50%
Fountain Waterfall at Main entranceNoNot applicable

Parking filed153

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots153
Closed/Covered153
BuildingClosed/CoveredTotal
Tower 19898
Tower 25555

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,508 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Damodar Suruchi Developers Private LimitedAndheriMumbai Suburban

Approvals and building plan

Permissible FSI21826.0
Proposed, not sanctioned21,826 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA-Wing, Ground Floor, Indralok Building, Swami Samarth Nagar, Andheri West, Mumbai, Maharashtra 4000

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShantanoo Rane and Associates
EngineerMr. Avadhoot Pai
EngineerJW Consultants
PartnerRole in project
Damodar Suruchi Developers Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017932Dec 2023 → Oct 2024

Reason as filed by the promoterWe were not able to complete the project within the timelines because of force majeure reasons and other reasons as mentioned in Form E

Complaints filed with MahaRERA45

Case no.ComplainantRespondentFiled
CC006000000480080Sachin Babu GuravDAMODAR SURUCHI DEVELOPERS PVT. LTD.14/04/2024
CC006000000001233sanjiv gilDamodar Suruchi Developers11/10/2017
CC006000000012681Tushant Tukaram MalkeDamodar Suruchi Developers04/01/2018
CC006000000054770Doli PanchalDamodar Suruchi Developers08/07/2018
CC006000000078501HARMEET KAUR ARORADAMODAR SURUCHI DEVELOPER19/03/2019
CC006000000100204Harmeet Kaur AroraDamodar Suruchi Developer02/08/2019
CC006000000079504SUDARSHAN R. CHAURASIYADAMODAR SURUCHI DEVELOPERS28/05/2019
CC006000000194302Sushma Mahendra ShettyDamodar Suruchi Developers15/10/2020
CC006000000428762DAYANAND PANDHARINATH KAMBLEDamodar Suruchi Developers08/01/2024
CC006000000428776Sunil SamatkarDamodar Suruchi Developers13/01/2024
CC006000000480144Sumet Sadanand BagweDamodar Suruchi Developers Pvt Ltd04/06/2024
CC006000000439651Ajay Harilal KanojiaDamodar Suruchi Builder Private Limted10/04/2024
CC006000000479832SWAPNILKUMAR PANDURANG LAKADEDAMODAR SURUCHI DEVELOPERS PVT. LTD21/04/2024
CC006000000479971GANESH ANAND ZINGADEM/s. Damodar Suruch iDevelopers06/04/2024
CC006000000479972GANGARAM ANAND ZINGADEM/s. Damodar Suruchi Developers06/04/2024
CC006000000479984Jayant PrakashDamodar Suruchi Developers Private Limited10/04/2024
CC006000000480011RAMESH DEVIDAS WANKHEDEDAMODAR SURUCHI DEVELOPERS PVT. LTD.12/05/2024
CC006000000480111Premprakash Mannulal MouryaDamodar Suruchi Developers Pvt Ltd23/04/2024
CC006000000480170Shalaka Vijay KulkarniDamodar Suruchi Developers Private Limited21/04/2024
CC006000000480175Jitesh Madhukar PatilDamodar Suruchi Developers Pvt. Ltd.23/04/2024
CC006000000480183Nagesh Manohar LotlikarDamodar Suruchi Developers Pvt. Ltd.01/05/2024
CC006000000480184SRNIBAS PARIDADamodar Suruchi Developers Pvt. Ltd.28/04/2024
CC006000000480320Sachin Prakash TanavadeDamodar Suruchi Developers05/05/2024
CC006000000480376Atul Bhogilal SolankiM/s Damodar Suruchi Developers06/05/2024
CC006000000500592Shivdas Tekke MadhamShivdas Madham27/05/2024
CC006000000570798kishor Vishnu SuryavanshiDAMODAR SURUCHI DEVELOPERS PVT. LTD18/06/2024
CC006000000570813TUSHARKUMAR JAGDISHCHANDRA JOSHIDAMODAR SURUCHI DEVELOPERS PVT. LTD18/06/2024
CC12400416Prashant Parasnath GuptaDamodar Suruchi Developers Pvt. Ltd.15/10/2024
CC12400759Jatin Sunil AgrawalDamodar Suruchi Developers Pvt. Ltd.13/11/2024
CC12401118Chirag Pramod PanchalDamodar Suruchi Developers Pvt. Ltd.13/12/2024
CC12400812rahul surendra yadavDamodar Suruchi Developers Pvt. Ltd.18/11/2024
CC12400860DATTATRAY VISHWANATH MASURKARDamodar Suruchi Developers Pvt. Ltd.23/11/2024
CC12401055SIDDHARTH VIJAY KUMAR JAINDamodar Suruchi Developers Pvt. Ltd.06/12/2024
CC12401104Pramodkumar Laxman DahanukarDamodar Suruchi Developers Pvt. Ltd.12/12/2024
CC12401209Kiran Balkrishna ValangerDamodar Suruchi Developers Pvt. Ltd.23/12/2024
CC12500299Sunilkumar RanaDamodar Suruchi Developers Pvt. Ltd.27/01/2025
CC12500477Vimal DesaiDamodar Suruchi Developers Pvt. Ltd.12/02/2025
CC12500796Devendra Pratap SinghDamodar Suruchi Developers Pvt. Ltd.08/03/2025
CC12501179Devendra Pratap SinghDamodar Suruchi Developers Pvt. Ltd.08/04/2025
CC12502204Archana Rahul SapkalDamodar Suruchi Developers Pvt. Ltd.03/07/2025
CC12504637RAMSINGH SURENDRAPRATAP YADAVDamodar Suruchi Developers Pvt. Ltd.26/12/2025
CC12601108Sanjay Pandurang RaneDamodar Suruchi Developers Pvt. Ltd.01/03/2026
CC12603908Damodar Suruchi Developers Pvt. Ltd.MS PUSHTAM SUNIL RAI24/06/2026
CC12604110Damodar Suruchi Developers Pvt. Ltd.MR BHUPENDRA AWADHRAJ SINGH01/07/2026
CC12604157Damodar Suruchi Developers Pvt. Ltd.MR BHUPENDRA AWADHRAJ SINGH03/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 May 2024

Documents filed141

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: UK IRIDIUM Disclosure April to June 2024.pdf6 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng cert UK Iridium MAR 2024.pdf4 Jun 2024
Certificates of CA (Form 3)File: Form No 3 UK Iridium BCD Wing MAR 2024.pdf4 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: UK Iridium Sale Building Wing BCD OC dated 6th May 2024.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A UK IRIDIUM B C D Wing.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: RERA Disclosure UK Iridium BCD Wing-2024_compressed.pdf17 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UK IRIDIUM BCD WING FORM 1 JAN 2024 - MAR 2024.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Oct 2023 to Dec 2023.pdf23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng cert UK Iridium OCT to DEC 2023.pdf19 Jan 2024
Certificates of CA (Form 3)File: Form 3 Uk Iridium BCD Wing Oct to Dec 2023.pdf19 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IRIDIUM BCD Wing Oct to Dec 2023.pdf12 Jan 2024
Certificates of CA (Form 3)File: Form 3 UK Iridium BCD Wing 300623.pdf23 Nov 2023
Certificates of CA (Form 3)File: Form 3 UK Iridium BCD Wing 300923.pdf23 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A UK IRIDIUM BCD WING 2021 TO 2022.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A UK IRIDIUM BCD WING 2022 TO 2023.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing till Dec 2021 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Jan 2022 to March 2022 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing April 2022 to June 2022 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing July 2022 to Sep 2022 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Oct 2022 to Dec 2022 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing Jan 2023 to March 2023 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing April 2023 to June 2023 final.pdf22 Nov 2023
Disclosure of sold/ booked inventoryFile: UK Iridium B, CD Wing July 2023 to Sep 2023 final.pdf22 Nov 2023
Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_310323.pdf22 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 2023 BCD Wing.pdf21 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2023 BCD Wing.pdf21 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 September 2023 BCD Wing.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Uk iridium BCD 2022 to 2023.pdf21 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD March.pdf18 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD June.pdf18 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate Wing BCD September.pdf18 Nov 2023
Declaration in FORM BFile: Affidavit Cum Decalaration FORM B UK IRIDIUM_compressed.pdf8 Nov 2023
Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_300622_Compressed.pdf25 Mar 2023
Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_300922_Compressed.pdf25 Mar 2023
Certificates of CA (Form 3)File: Form3_UKIridium_ BCD_311222_Compressed.pdf25 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf10 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf10 Feb 2023
Details of encumbrancesFile: RERA - Details of Encumbrances - Iridium.pdf26 Apr 2022
Details of encumbrancesFile: DHFL- No Due certificate.pdf25 Apr 2022
OtherFile: Harmeet Arora - RERA.pdf28 Mar 2022
OtherFile: Approval through Email by Mohun Rao.pdf22 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: CC For UK Iridium.pdf16 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Iridium.pdf16 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK IRIDIUM ENGINEERS CERTIFICATE.pdf16 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: UK Iridium Form 24.pdf16 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: UK Iridium Form-24 for RERA (5).pdf16 Dec 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventories Iridium.pdf16 Dec 2021
Certificates of CA (Form 3)File: Form No 3 UK Iridium.pdf16 Dec 2021
Certificates of CA (Form 3)File: Form No 3 UK Iridium.pdf16 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 UK Iridium 2018.pdf16 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form No 5 UK Iridium 2019.pdf16 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_UK_Irdium_2020-21.pdf16 Dec 2021
Layout approvalFile: jpg2pdf (3).pdf7 Dec 2021
Layout approvalFile: jpg2pdf (3).pdf7 Dec 2021
PAN CardFile: Damodar Pvt Ltd - Pan Card-converted.pdf7 Dec 2021
PAN CardFile: Damodar Pvt Ltd - Pan Card-converted.pdf7 Dec 2021
Copy of Layout Approval (in case of layout)File: jpg2pdf (3).pdf7 Dec 2021
Copy of Layout Approval (in case of layout)File: jpg2pdf (3).pdf7 Dec 2021
Declaration about Commencement CertificateFile: declaration for cc-pdf.pdf7 Dec 2021
Declaration in FORM BFile: self declaration - Iridium - DSD to DSDPL.pdf7 Dec 2021
Declaration in FORM BFile: Affidavit Cum Declaration UK Iridium.pdf7 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK Iridium Form-24 for RERA (2).pdf7 Dec 2021
OtherFile: CERTIFICATE OF INCORPORATION.PDF7 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UK Iridium- Engineer Certificate.pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5-2018-2019.pdf14 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 2019 to 2020.pdf14 Sep 2021
Building plan approvalFile: IOD.pdf6 Sep 2021
Layout approvalFile: LAYOUT PLAN-1.pdf6 Sep 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN-1.pdf6 Sep 2021
Building Plan Approval (IOD)File: IOD.pdf6 Sep 2021
Certificates of CA (Form 5)File: Form 5.pdf6 Sep 2021
PAN CardFile: Pan Card Letter.pdf25 Aug 2021
Proforma of Allotment letterFile: AFS-25-08-2021.pdf25 Aug 2021
Building plan approvalFile: IOA.pdf13 Jul 2021
Building Plan Approval (IOD)File: IOA.pdf13 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera_Certificate_form.pdf31 Dec 2020

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 10 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UK Iridium on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali East6,700+ in Mumbai Suburban

2 kmUK IridiumCompleted 38Lapsed / revoked 26Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 131 registered projects within 2 km.

Builder: Damodar Suruchi Developers Pvt. Ltd.

Damodar Suruchi Developers Pvt. Ltd. has 3 registrations on MahaRERA, including UK Iridium and UK LUXECITY. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that UK Iridium shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if UK Iridium is delayed beyond 12 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UK Iridium?

The registered promoter entity is Damodar Suruchi Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UK Iridium?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against UK Iridium?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for UK Iridium?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UK Iridium?

The professionals named in the filing: Architect: Shantanoo Rane and Associates; Engineer: Mr. Avadhoot Pai; Engineer: JW Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UK Iridium?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UK Iridium. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UK Iridium to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.