Home / Browse projects / Ratnagiri, Maharashtra / TULSI RESIDENCY PHASE-II

Registration lapsed No litigation declared Residential / Group Housing project

TULSI RESIDENCY PHASE-II

By AMOL VIJAY TETAMBE HUF

RG-MH-53949 · RERA P52800017377 · Last updated on MahaRERA portal: 25 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 22 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

TULSI RESIDENCY PHASE-II is a Residential / Group Housing project by AMOL VIJAY TETAMBE HUF in Ratnagiri, Maharashtra, registered with MahaRERA as P52800017377 on 9 Aug 2018. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 22 months from the original filing.

At a glance

Project

  • NameTULSI RESIDENCY PHASE-II
  • TypeResidential / Group Housing
  • Location
    • MUMBAI-GOA HIGHWAY
    • NEAR CHIPLUN RAILWAY STATION
    • Walope
    • Chiplun
    • Ratnagiri
    • 415605
  • Pincode415605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800017377
  • ReraGenie IDRG-MH-53949

Builder

  • NameAMOL VIJAY TETAMBE HUF
  • Entity typeOthers
  • Named personAMOL VIJAY TETAMBE
  • Declared earlier projects2 →

Key dates

19 months past promisethis monthRegisteredAug 2018First promiseMay 2023Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2018
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 May 2023)
  • Buildings1 building record
  • Documents filed84 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TULSI RESIDENCY PHASE-IINA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TULSI RESIDENCY PHASE-II: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 25 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered56

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,956 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2059.8
Proposed, not sanctioned2,060 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHOGALE CHIPLUN

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAGSEN M KAMBLE
PartnerRole in project
AMOL VIJAY TETAMBE HUF-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800015310May 2023 → May 2024

Reason as filed by the promoterConstruction had stopped during the Corona period. Also it took 6 months till everything went smoothly due to the flood in Chiplun.

EXT52800019581May 2023 → Mar 2025

Reason as filed by the promoterNo more booking.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Apr 2025

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar-2025.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar-2025.pdf25 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec-2024.pdf19 Apr 2025
Certificates of CA (Form 3)File: Form 3 Dec-2024.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec-2024.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep-2024.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep-2024.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep-2024.pdf19 Dec 2024
Declaration about Commencement CertificateFile: Declaration For commencement.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31032024.pdf17 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032024.pdf17 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A 2022-23.pdf17 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2A 2023-24.pdf17 May 2024
Certificates of CA (Form 3)File: Form 3 31032024.pdf17 May 2024
Certificates of CA (Form 3)File: Form 3 31032024 Corrected.pdf17 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf17 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf17 May 2024
Declaration in FORM BFile: Rera Affidavit.pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 300623.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092023.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092023.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31122023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 300623.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30092023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30092023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122023.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory 300623.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory 31122023.pdf17 Apr 2024
Certificates of CA (Form 3)File: Form 3 300623_11zon.pdf17 Apr 2024
Certificates of CA (Form 3)File: Form 3 30092023_11zon.pdf17 Apr 2024
Certificates of CA (Form 3)File: Form 3 31122023_11zon.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf28 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Aug 2023
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory.pdf28 Aug 2023
Certificates of CA (Form 3)File: Form 3.pdf28 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Tetambe Form 5 FY 19-20 (1).pdf25 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2018-19.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2019-20.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2020-21.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 21.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar-22.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jun 22.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep-22.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 22.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2018-19.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2019-20.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2020-21.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Dec 21.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Jun 22.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Sep 22.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Dec 22.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Mar 22.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2 Mar 22.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 2018-19.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 2019-20.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 2020-21.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 Dec 21.pdf3 Feb 2023
Certificates of CA (Form 3)File: From 3 Mar 22.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 Jun 22.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 Sep 22.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 Dec 22.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Jun 21.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Inventory Dec-22.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf8 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf14 Jan 2020
Building plan approvalFile: Plan 1.pdf6 Aug 2018
Building plan approvalFile: Plan 2.pdf6 Aug 2018
Layout approvalFile: 7-12 nakasha.pdf6 Aug 2018
PAN CardFile: PAN.pdf6 Aug 2018
Copy of the legal title reportFile: Title Search.pdf6 Aug 2018
Details of encumbrancesFile: Non Encumbrance Certificate.pdf6 Aug 2018
Copy of Layout Approval (in case of layout)File: 7-12 nakasha.pdf6 Aug 2018
Building Plan Approval (IOD)File: Plan 1.pdf6 Aug 2018
Building Plan Approval (IOD)File: Plan 2.pdf6 Aug 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
TULSI RESIDENCY PHASE-1VALOPE38CompletedAug 2017Jul 2017
TULSI ANANDCHIPLUN42CompletedJan 2013Jan 2013

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one moved by 22 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep TULSI RESIDENCY PHASE-II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR CHIPLUN RAILWAY STATION1,100+ in Ratnagiri

2 kmTULSI RESIDENCY PHASE-IICompleted 28Lapsed / revoked 18Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: AMOL VIJAY TETAMBE HUF

AMOL VIJAY TETAMBE HUF has 1 registration on MahaRERA, including TULSI RESIDENCY PHASE-II. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What does it mean that TULSI RESIDENCY PHASE-II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TULSI RESIDENCY PHASE-II is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TULSI RESIDENCY PHASE-II?

The registered promoter entity is AMOL VIJAY TETAMBE HUF, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TULSI RESIDENCY PHASE-II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TULSI RESIDENCY PHASE-II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TULSI RESIDENCY PHASE-II?

The professionals named in the filing: Architect: NAGSEN M KAMBLE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TULSI RESIDENCY PHASE-II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TULSI RESIDENCY PHASE-II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULSI RESIDENCY PHASE-II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.