Home / Browse projects / Raigarh, Maharashtra / TULSI NISARG
TULSI NISARG
RG-MH-11520 · RERA P52000005986 · Last updated on MahaRERA portal: 6 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 72 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TULSI NISARG is a Others project by PRISTINE GROUP in Raigarh, Maharashtra, registered with MahaRERA as P52000005986 on 14 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 72 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 13 of 88 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameTULSI NISARG
- TypeOthers
- Location
- neral
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000005986
- ReraGenie IDRG-MH-11520
Builder
- NamePRISTINE GROUP
- Entity typeOthers
- PartnersBHAVIN RAMESHCHANDRA PATEL, CHIRAG KANUBHAI PATEL, KETAN PRALHADBHAI SURANI, VIJAY ASHOK JESWANI, VAIBHAV PURUSHOTTAM AGRAWAL, DEEPAK AWATRAM VALECHA, MONICA KVINJAL PATEL, JIGNESH DINESH SANGHVI
- Named personsMANGAL PYARELAL PARMAR, RAJAN SHRIRAMDAYAL KAKKAR, RADHA MOHAN MISHRA, SANJAY UTTAMCHAND SHETIYA, SHRIRAM DAJI RANE, NITESH MAHENDRAKUMAR SHAH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Aug 2017
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2021)
- Buildings8 building records
- Documents filed63 files
Current status
Figures as on 6 May 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 1 WING A | NA | 9 | 1 | 1 | 0 | 1 |
| BUILDING 1 WING B | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDIND 1 WING C | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING 2 WING D | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING NO 2 WING E | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING NO 2 WING F | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING NO 3 WING G | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 3 WING H | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 6 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Stilt Floor, at 70%.
BUILDING 1 WING A41%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 37% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 1 WING B37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDIND 1 WING C27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 2 WING D22%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 70% |
| Podiums (if any) | 0% |
| Plinth | 70% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 2 WING E18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 2 WING F9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 3 WING G0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 3 WING H0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING 1 WING A | 1 | 1 |
| BUILDING 1 WING B | 1 | 1 |
| BUILDIND 1 WING C | 1 | 1 |
| BUILDING 2 WING D | 1 | 1 |
| BUILDING NO 2 WING E | 1 | 1 |
| BUILDING NO 2 WING F | 1 | 1 |
| BUILDING NO 3 WING G | 1 | 1 |
| BUILDING NO 3 WING H | 1 | 1 |
Land and ownership6
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NITESH MAHENDRAKUMAR SHAH | Neral | Raigarh |
| MANGAL PYARELAL PARMAR | Karjat | Raigarh |
| RAJKUMAR SHRIRAMDAYAL KAKKAR | Pune (M Corp.) | Pune |
| SANJAY UTTAMCHAND SHETIYA | Pune (M Corp.) | Pune |
| RADHA MOHAN MISHRA | Pune (M Corp.) | Pune |
| SHRIRAM DAJI RANE | Neral | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAISINGH AHUJA AND ASSOCIATES |
| Engineer | S VPATEL AND ASSOCIATES |
| Chartered Accountant | CA MAYUR PADEKAR |
| Partner | Role in project |
|---|---|
| PRISTINE GROUP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid-19 , non availability of workers and business stress.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000303140 | ABBAS SHIKARI | SIDDHIVINAYAK REALTORS | 26/10/2022 |
| CC006000000303152 | ABBAS SHIKARI | SIDDHIVINAYAK REALTORS | 26/10/2022 |
| CC006000000303260 | Vilas Bhaga Dalvi | Siddhivinayak Realtors | 09/11/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed63
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - March 2022.pdf | 6 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - June 2022.pdf | 6 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sep 2022.pdf | 6 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Dec 2022.pdf | 6 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Form 2 - Mar 25.pdf | 6 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-2023.pdf | 6 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-2024.pdf | 6 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form 1 - Jun 23.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Form 1 - Sep 23.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form 1 - Dec 23.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form 1 - Mar 24.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Form 1 - Jun 24.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 0 Form 2 - Mar 23.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Form 2 - Jun 23_organized.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 - Sep 23_organized.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 - Dec 23_organized.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2 - Mar 24_organized.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2 - Jun 24.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 - Sep 24.pdf | 26 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Form 2 - Dec 24.pdf | 26 Mar 2025 |
| Certificates of CA (Form 3)File: Form for Withdrawl.pdf | 16 Feb 2024 |
| Certificates of CA (Form 3)File: Form for Withdrawl 2_11zon (1).pdf | 16 Feb 2024 |
| Certificates of CA (Form 5)File: Form 5 - FY 22-23.pdf | 4 Feb 2024 |
| Proforma of Agreement for saleFile: Customer Agreement Pristine.pdf | 27 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1)form 1-1-4-2022.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2)Form 1 -1-7-2022.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3)form 1-30-9-22.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4)form 1-1-1-23.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5)form 1-1-4-23.pdf | 26 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold inventory_compressed.pdf | 5 Jan 2023 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf | 4 Jan 2023 |
| Declaration about Commencement CertificateFile: circular 32.pdf | 30 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - SR 19-20.pdf | 23 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A - SR 20-21.pdf | 23 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - SR 21-22.pdf | 23 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Siddhivinayak Realtors Form 5.pdf | 26 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Siddhivinayak Realtors.pdf | 10 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Siddhivinayak Realtors_Tulsi Nisarg _DT100321.pdf | 10 Mar 2021 |
| Certificates of CA (Form 5)File: CA CERT.pdf | 22 Dec 2018 |
| Details of encumbrancesFile: Tulsi_Nisarg_No_Ecumbrance_Certificate.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Tulsi Nisarg Affidavit_ TN.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tulsi Nisarg Architect Cetificate.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Tulsi Nisarg Engineer's Certificate.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IMG_20170725_204730__1_.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: Tulsi Nisarg CA Certificate.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Allotment letter Tulsi Nisarg.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE NEW RERA NISARG.pdf | 28 Jul 2017 |
| Building plan approvalFile: 1Nisarg CC.pdf | 19 Jul 2017 |
| Layout approvalFile: MYSCAN_0004.PDF | 19 Jul 2017 |
| Layout approvalFile: MYSCAN_0005.pdf | 19 Jul 2017 |
| Layout approvalFile: MYSCAN_0006.PDF | 19 Jul 2017 |
| Layout approvalFile: MYSCAN_0007.pdf | 19 Jul 2017 |
| Layout approvalFile: MYSCAN_0008.pdf | 19 Jul 2017 |
| PAN CardFile: Siddhivinayak Realtors Pan Card.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: 2Title search 107.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: 3Title search 108.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_0004.PDF | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_0005.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_0006.PDF | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_0007.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_0008.pdf | 19 Jul 2017 |
| Building Plan Approval (IOD)File: 1Nisarg CC.pdf | 19 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 1Nisarg CC.pdf | 19 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 63 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep TULSI NISARG on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near neral5,900+ in Raigarh
Filed coordinates, straight-line distance. 41 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: PRISTINE GROUP
PRISTINE GROUP has 1 registration on MahaRERA, including TULSI NISARG. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if TULSI NISARG is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TULSI NISARG?
The registered promoter entity is PRISTINE GROUP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TULSI NISARG?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against TULSI NISARG?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for TULSI NISARG?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TULSI NISARG?
The professionals named in the filing: Architect: RAISINGH AHUJA AND ASSOCIATES; Engineer: S VPATEL AND ASSOCIATES; Chartered Accountant: CA MAYUR PADEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TULSI NISARG?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.