Trinity - Shashank Saptshrung
By RADHIKA CONSTRUCTION COMPANY
RG-MH-07221 · RERA P51700055300 · Last updated on MahaRERA portal: 2 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Trinity - Shashank Saptshrung is a Others project by RADHIKA CONSTRUCTION COMPANY in Thane, Maharashtra, registered with MahaRERA as P51700055300 on 14 Mar 2024. Possession is promised by 31 Aug 2028. 28 of the 85 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameTrinity - Shashank Saptshrung
- TypeOthers
- Location
- DEVI CHOWK SHASHTRI NAGAR
- dombivli west
- DOMBIVLI
- Kalyan
- Thane
- 421202
- Pincode421202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700055300
- ReraGenie IDRG-MH-07221
Builder
- NameRADHIKA CONSTRUCTION COMPANY
- Entity typePartnership
- GSTIN27ABDFR2279J1ZU
- PartnerRADHIKA SHRIKRISHNA MARATHE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Mar 2024
- Promised completion31 Aug 2028
- Revised completionNone
- Buildings1 building record
- Documents filed103 files
Current status
Figures as on 2 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TRINITY - SHASHANK SAPTASHRUNG | NA | 11 | 11 | 79 | 6 | 85 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 45%.
TRINITY - SHASHANK SAPTASHRUNG: 31% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 45% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHASHANK CO.OP. HSG SCTY LTD | DOMBIVLI | Thane |
| SAPTASHRUNG CO.OP HSG. SCTY LTD | DOMBIVLI | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SPACE ENVIRO ARCHITECTS |
| Engineer | ENTECH ENGINEERS |
| Chartered Accountant | ankur sangoi & associates |
| Chartered Accountant | NIKITA |
| Partner | Role in project |
|---|---|
| RADHIKA CONSTRUCTION COMPANY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Aug 2028
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: (Form 1)_Architect Certificate_Trinity_31 Dec 2025.pdf | 2 May 2026 |
| Form 2File: Form 2 Engimeer Certificate_Merged for Soc and Salable.pdf | 2 May 2026 |
| Form 3File: (Form 3)_Trinity_Dec 2025_Final_signed.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory as on 31 Dec 2025.pdf | 2 May 2026 |
| OthersFile: Unsold Inventory as on 31 Dec 2025.pdf | 2 May 2026 |
| Form 1File: Architect's Certificate FOR 30 JUNE 2024.pdf | 20 Nov 2025 |
| Form 2File: ENGINEERS CERTIFICATE 15-07-24.pdf | 20 Nov 2025 |
| Form 3File: Form 3 Trinity for june 2024Signed.pdf | 20 Nov 2025 |
| OthersFile: ENGINEERS CERTIFICATE F-2 15-07-24.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold_merged.pdf | 20 Nov 2025 |
| Form 1File: FORM -1 TRINITY 30 SEPT 24.pdf | 20 Nov 2025 |
| Form 2File: Form 2 merged.pdf | 20 Nov 2025 |
| Form 3File: FORM 3 TRINITY 11 NOV_Signed.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold Merged.pdf | 20 Nov 2025 |
| OthersFile: Trinity Society member new flat allotment1 (1).pdf | 20 Nov 2025 |
| Form 3File: TRINITY FORM 3.pdf | 20 Nov 2025 |
| Form 1File: Form 1 Architect's Certificate.pdf | 20 Nov 2025 |
| Form 2File: Form 2Merged.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Merged.pdf | 20 Nov 2025 |
| Form 1File: Form -1 as on 31-3-25.pdf | 20 Nov 2025 |
| Form 3File: Form 3 Signed.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory as on 31-3-25.pdf | 20 Nov 2025 |
| OthersFile: Form 2A as on 31-3-25.pdf | 20 Nov 2025 |
| Form 2File: Form 2 Merged.pdf | 20 Nov 2025 |
| Form 1File: Trinity Architect Certificate 30sept 2025.pdf | 8 Nov 2025 |
| Form 2File: trinity Engineer Certificate Saleable Area 30 sept 2025.pdf | 8 Nov 2025 |
| OthersFile: Trinity Form 2 Society Members 30 sept 2025.pdf | 8 Nov 2025 |
| Form 3File: Form 3 Trinity Sep 2025_Final Signed.pdf | 8 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Final Trinity Sold Inventory 30 sept 2025.pdf | 8 Nov 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6 Disclosure of sold booked inventory_compressed.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: TRINITY FORM 3 FOR DEC 24.pdf | 8 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 trinity Dec 24.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Saleble area Trinity dec24.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Society - trinity dec 24.pdf | 3 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: TRINITY SOLD INVENTORY AS ON DEC24.pdf | 3 Feb 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 'A' Trinity.pdf | 7 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Trinity for june 2024Signed_compressed.pdf | 5 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 TRINITY FOR MARCH 2024.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 TRINITY 11 NOV_Signed.pdf | 11 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: final Encumbrance Regarding Finance trinity.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Trinity Inventary certificate on 30sept 2024.pdf | 9 Nov 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200327050394_For_Debtor_Based_Search_09_11_2024_15_48_55_637.pdf | 9 Nov 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format -A Bank Declaration.pdf | 9 Nov 2024 |
| Details of encumbrances concerned to LegalFile: final Encumbrance Regarding Finance trinity.pdf | 9 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: RERA DRAFT OF TRINITY PROJECT.pdf | 9 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: trinity RERA AGREEMENT daviation.pdf | 9 Nov 2024 |
| Proforma of Agreement for saleFile: RERA DRAFT OF TRINITY PROJECT.pdf | 9 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: ICICI Format B.pdf | 9 Nov 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: final Disclosure for Secured finance aviled for Trinity.pdf | 9 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 TRINITY 30 SEPT 24.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 TRINITY Society Member 30SEPT 2024.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 TRINITY Saleable Area 30 SEPT 24.pdf | 6 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: tRINITYFORM 1 FOR MARCH 2024.pdf | 11 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: tRINITY Architect's Certificate FOR 30 JUNE 2024.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2 FOR SALEABLE AREA AVAILABLE FOR TRINITY.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2 FOR OLD SCTY MEMBERS TRINITY.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2 TRINITY FOR FLAT ALLOTED TO OLDMEMBERS FOR MARCH 2024.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: tRINITY fORM 2 fOR SALEABLE AREA TO TRINITY FOR mARCH 2024.pdf | 11 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF UNSOLD INVENTORY TRINITY.pdf | 11 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY AS ON 30 JUNE 2024.pdf | 11 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A TRINITY 31 MARCH 2024.pdf | 11 Oct 2024 |
| Copy of the legal title reportFile: Title ReporT SHASHANK NEW.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: Declaration Regarding Encumbrances_Finance.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: Declaration Regarding Encumbrances_Legal.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Declaration Regarding Encumbrances_Finance.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Declaration Regarding Encumbrances_Legal.pdf | 22 Feb 2024 |
| Declaration in FORM BFile: FORM B OF TRINITY.pdf | 22 Feb 2024 |
| CERSAI detailsFile: CERSAI UNDERTAKING.pdf | 22 Feb 2024 |
| CERSAI detailsFile: Asset Based Search trinity 22 feb 2024.pdf | 22 Feb 2024 |
| CERSAI detailsFile: cersai mail extract.pdf | 22 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3 signed and scanned (1).pdf | 22 Feb 2024 |
| Proforma of Agreement for saleFile: TRNITY SALE AGREEMENT.pdf | 22 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: DAVIATION AFFIDAVIT FINAL.pdf | 22 Feb 2024 |
| Other - LegalFile: Radhika Construction Co Partnership Deed.pdf | 22 Feb 2024 |
| Other - TechnicalFile: trinity Declaration Cum Undertaking as per order 50-2024.pdf | 22 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ( COST FOR SALEABLE AREA).pdf | 3 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Trinity - Shashank Saptshrung on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near dombivli west7,600+ in Thane
Filed coordinates, straight-line distance. 286 registered projects within 2 km.
Swaminarayan City Phase 1C
Swaminarayan Life Space LLP
Swaminarayan City Phase I
Swaminarayan Life Space LLP
BHOIR JEWELS
SHANKAR NAMAJI BHOIR
Swaminarayan City Phase 1D
Swaminarayan Life Space LLP
Amar Galaxy Bldg No. 2 Wing B and C
AMAR REALTY
Swaminarayan City Phase 1B
Swaminarayan Life Space LLP
See every Thane project, with the district possession charts
Builder: RADHIKA CONSTRUCTION COMPANY
RADHIKA CONSTRUCTION COMPANY has 1 registration on MahaRERA, including Trinity - Shashank Saptshrung. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Trinity - Shashank Saptshrung is delayed beyond 31 Aug 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Trinity - Shashank Saptshrung?
The registered promoter entity is RADHIKA CONSTRUCTION COMPANY, a partnership as per the filing. Its GSTIN 27ABDFR2279J1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Trinity - Shashank Saptshrung?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Trinity - Shashank Saptshrung?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Trinity - Shashank Saptshrung?
The professionals named in the filing: Architect: SPACE ENVIRO ARCHITECTS; Engineer: ENTECH ENGINEERS; Chartered Accountant: ankur sangoi & associates; Chartered Accountant: NIKITA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Trinity - Shashank Saptshrung?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback