ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / TRINETRA APARTMENT

Completed No litigation declared Residential / Group Housing project

TRINETRA APARTMENT

By SHREE SAI CONSTRUCTION

RG-MH-76243 · RERA P99000011142 · Last updated on MahaRERA portal: 20 Feb 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 29 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
40 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

TRINETRA APARTMENT is a Residential / Group Housing project by SHREE SAI CONSTRUCTION in Palghar, Maharashtra, registered with MahaRERA as P99000011142 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 29 months from the original filing.

At a glance

Project

  • NameTRINETRA APARTMENT
  • TypeResidential / Group Housing
  • Location
    • VASAI VIRAR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401209
  • Pincode401209
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000011142
  • ReraGenie IDRG-MH-76243

Builder

  • NameSHREE SAI CONSTRUCTION
  • Entity typePartnership
  • PartnersVISHAL SUDAM PATIL, MUKESH SHIVDAS SONAR, MANOJ KESHAVLAL LIMBAD
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJul 2023Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Jul 2023)
  • Buildings4 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WING TRINETRA RESIDENCYNA110000
B WING TRINETRA RESIDENCYNA110000
C WING TRINETRA RESIDENCYNA110000
D WING TRINETRA RESIDENCYNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

A WING TRINETRA RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING TRINETRA RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C WING TRINETRA RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D WING TRINETRA RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes85%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered7
BuildingClosed/CoveredTotal
A WING TRINETRA RESIDENCY44
B WING TRINETRA RESIDENCY11
C WING TRINETRA RESIDENCY11
D WING TRINETRA RESIDENCY11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,440 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10148.1
Proposed, not sanctioned10,148 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 13 AND 14 NIKHIL HERITAGE ACHOLE ROAD NALASOPARA EAST PALGHAR

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAPE CONSULTANTS
PartnerRole in project
SHREE SAI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000016988Jul 2023 → Dec 2025

Reason as filed by the promoterDear Sir, Due golobal Pendamic Covid-19 and revision in plan, we need more time till 31-12-2025 to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Feb 2025

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Letter - 01 08 2024.pdf20 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf20 Feb 2025
Certificates of CA (Form 3)File: FORM 3_ JUNE 24_SSC (Q1)-SIGNED - converted.pdf20 Feb 2025
Certificates of CA (Form 3)File: FORM 3_ DEC 24_SSC (Q3)-SIGNED - converted.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER LETTER 1 08 24.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf20 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRINETRA RESIDENCY OC.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5_2024_TRINETRA RESD.pdf31 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 10052024.pdf17 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate 13052024.pdf17 Jun 2024
Certificates of CA (Form 3)File: FORM 3_CA CERTIFICATE_Q4 SIGNED - converted.pdf17 Jun 2024
Disclosure of sold/ booked inventoryFile: sold unsold list 31 12 23.pdf7 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 SCANNED COPY 2023.pdf28 Jan 2024
Certificates of CA (Form 3)File: FORM 3 SIGNED_MAR 23 opt-SSC.pdf23 Jan 2024
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE Q-JUNE 2023.pdf23 Jan 2024
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE Q SEP 2023 OPT.pdf23 Jan 2024
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE Q3 DEC 2023.pdf23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTURE CERTIFICATE.pdf19 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT LETTER (Q-3).pdf19 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf19 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE (Q-3).pdf19 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Cert( OPT).pdf29 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Eng Cert (OPT).pdf29 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE Q3 2022 OPT.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE Q3 2022 OPT.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3_SSC_JUNE 21_SIGNED.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE_ opt.pdf10 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE form 3 opt.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3_CA CERT_QE JUNE 22_1.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3_CA CERT_QE JUNE 22_2.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3-CA CERT-Q E SEP 2022_1.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3-CA CERT-Q E SEP 2022_2.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3_SSC_DEC 22 SIGNED_1.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3_SSC_DEC 22 SIGNED_2.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2022 SSC SIGNED opt.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 71022CO.pdf20 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE 91022.pdf20 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT CERTIFICATE_1.pdf16 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT CERTIFICATE_2.pdf16 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ENGINEERS CERTIFICATE COMPRESSED.pdf16 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTIFICATE.pdf16 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: shree sai construction - rera audit report - 20-21.pdf16 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200226064160_For_Asset_Based_Search_17_12_2021_16_56_19_724.pdf17 Dec 2021
CERSAI detailsFile: SERSAI DECLARATION SIGNED.pdf17 Dec 2021
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf16 Dec 2021
CERSAI detailsFile: document(2).pdf8 Dec 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DETAILS.pdf2 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION TO CC.pdf14 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SSC AUDIT REPORT.pdf31 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: TRINETRA RESIDENCY FORM 5.pdf31 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: TRINETRA LATESTT CC.pdf25 Sep 2020
Proforma of Allotment letterFile: SSC AUDIT REPORT.pdf16 Oct 2019
Certificates of CA (Form 5)File: FORM 5.pdf30 Sep 2019
Certificates of CA (Form 5)File: FORM 5.pdf30 Sep 2019
Certificates of CA (Form 5)File: RERA FORM-5-SHREE SAI CONS.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: CCTRINETRA.pdf22 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf18 Dec 2017
Certificates of CA (Form 3)File: CA CERTIFICATE TRINETRA.pdf22 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf15 Aug 2017
Building plan approvalFile: BUILDING PLAN.pdf14 Aug 2017
Layout approvalFile: LAYOUT PLAN.pdf14 Aug 2017
PAN CardFile: SHREE SAI CONSTRUCTION PAN.pdf14 Aug 2017
Copy of the legal title reportFile: title search report.pdf14 Aug 2017
Details of encumbrancesFile: ENCUMBRACE LETTER.pdf14 Aug 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf14 Aug 2017
Building Plan Approval (IOD)File: BUILDING PLAN.pdf14 Aug 2017
Declaration in FORM BFile: FORM B.pdf14 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT 001.pdf14 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT 002.pdf14 Aug 2017
Certificates of CA (Form 3)File: CA FORM 3 DECLARATION.pdf14 Aug 2017
Proforma of Allotment letterFile: SALE AGREEMENT SAMPLE 01.pdf14 Aug 2017
Proforma of Allotment letterFile: SALE AGREEMENT SAMPLE 02.pdf14 Aug 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf14 Aug 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 29 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRINETRA APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI VIRAR3,200+ in Palghar

2 kmTRINETRA APARTMENTCompleted 49Lapsed / revoked 39Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: SHREE SAI CONSTRUCTION

SHREE SAI CONSTRUCTION has 6 registrations on MahaRERA, including TRINETRA APARTMENT and SAI VIHAR. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if TRINETRA APARTMENT is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRINETRA APARTMENT?

The registered promoter entity is SHREE SAI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRINETRA APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRINETRA APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRINETRA APARTMENT?

The professionals named in the filing: Architect: SHAPE CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRINETRA APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRINETRA APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRINETRA APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.