Home / Browse projects / Pune, Maharashtra / TRIMURTI PARK
TRIMURTI PARK
RG-MH-94020 · RERA P52100045528 · Last updated on MahaRERA portal: 22 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 18 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TRIMURTI PARK is a Residential / Group Housing project by SIDDHANATH DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100045528 on 24 May 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 18 months from the original filing. 14 of the 16 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameTRIMURTI PARK
- TypeResidential / Group Housing
- Location
- BAKORI ROAD
- WAGHOLI TALUKA - HAVELI
- Pune (M Corp.)
- Pune City
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100045528
- ReraGenie IDRG-MH-94020
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 May 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed65 files
Current status
Figures as on 22 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TRIMURTI PARK | NA | 5 | 5 | 16 | 0 | 16 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.
TRIMURTI PARK: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 99% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 22 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TRIMURTI PARK | NA | Rs 1.16 cr | Rs 1.15 cr |
| - | NA | Rs 25.50 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CS ARCHITECTS |
| Engineer | VIKAS TRIMBAK KHARADKAR TRIMBAK KHARADKAR |
| Chartered Accountant | OMKAR U KHUDE AND COMPANY |
| Chartered Accountant | PARESH RATANLAL |
| Partner | Role in project |
|---|---|
| SIDDHANATH DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNOC REQUIRED FROM AIR FORCE DEFENCE DEPARTMENT FOR HEIGHT LIMIT. DELAY IN GETTING NOC FROM AIR FORCE DEPARTMENT. THUS REVISED PLAN HAS NOT BEEN SANCTIONED FROM PUNE MUNCIPAL CORPORATION
Reason as filed by the promoterWe had received a sanction of the project for first 3 Floors and late we have applied for revised sanction for 4th & 5th Floors. But, Due to following legal issues we have not received a sanction for the 4th Floor & 5th Floor. 1. NOC from Air Force: Our location of the project is nearby Lohegaon Airport. Thus, we are required a special NOC from AIR Force Department from Delhi. Thus, it gets much more time for revised sanction. 2. Sanction from PMRDA: PMRDA is newly formed Government Authority and There is very much lack of manpower and Thus they are taking very much time for Sanctioning proces
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Sep 2025.pdf | 22 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Sep 2025.pdf | 22 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Sep 2025.pdf | 22 Nov 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 - TRIMURTI PARK 2023-2024.pdf | 22 Nov 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 - TRIMURTI PARK 2023-2024.pdf | 22 Nov 2025 |
| Form 5 (FY 2022-2023)File: Form 5- Trimurti Park - 2022-2023.pdf | 22 Nov 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 2 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 2 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - June 2025.pdf | 2 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - June 2023.pdf | 29 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - Sep 2023.pdf | 29 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2023.pdf | 29 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - March 2024.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - June 2023.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - Sep 2023.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park_11zon - Dec 2023.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - March 2024.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 - June 2023.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 - Sep 2023.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2023.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE - Siddhanath Developers - March 2024.pdf | 29 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A - June 2023.pdf | 29 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 3 ca certificate - Trimurti Park - Sep 2023.pdf | 29 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - TRIMURTI PARK 2023-2024.pdf | 29 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - Sep 2024.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - Dec 2024.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Discloure of Sold Flats - Sep 2024.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Discloure of Sold Flats - Dec 2024.pdf | 22 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - TRIMURTI PARK 2023-2024.pdf | 12 Nov 2024 |
| Declaration in FORM BFile: Form B - Siddhanath.pdf | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a Quality rera certificate engineers - Mar 2024.pdf | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a Quality rera certificate engineers - Dec 2023.pdf | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a Quality rera certificate engineers - June 2024.pdf | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSUE OF FLATS BOOKED.pdf | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - March 2024.pdf | 2 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect CErtificate - June 2024.pdf | 2 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE - Siddhanath Developers - March 2024.pdf | 2 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE - Siddhanath Developers - June 2024.pdf | 2 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - March 2024.pdf | 2 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park - June 2024.pdf | 2 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Discloure of Sold Flats.pdf | 16 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 13 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 13 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca certificate - Trimurti Park_11zon.pdf | 13 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Trimurti Park - 2022-2023.pdf | 28 Nov 2023 |
| Details of encumbrancesFile: Declaration on Letter Head-With Stamp.pdf | 16 May 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE- With Stamp.pdf | 16 May 2022 |
| CERSAI detailsFile: DECLARATION ABOUT NO SECURITY INTEREST- With Stamp.pdf | 16 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Certificate- With Stamp_11zon.pdf | 16 May 2022 |
| Layout approvalFile: Layout_11zon.pdf | 6 May 2022 |
| Building plan approvalFile: Sanction Plan_11zon.pdf | 6 May 2022 |
| PAN CardFile: PAN Firm.pdf | 6 May 2022 |
| Copy of the legal title reportFile: Title and Search Report_11zon.pdf | 6 May 2022 |
| Details of encumbrancesFile: Declaration- Notary.pdf | 6 May 2022 |
| Copy of Layout Approval (in case of layout)File: Layout_11zon.pdf | 6 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan_11zon.pdf | 6 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.PDF | 6 May 2022 |
| Declaration in FORM BFile: Form B_11zon.pdf | 6 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certifictae.pdf | 6 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginners Certificate.pdf | 6 May 2022 |
| Proforma of Allotment letterFile: Draft Trimurti Park.pdf | 6 May 2022 |
| Proforma of Allotment letterFile: Allotment Letter Format.pdf | 6 May 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| TRIMURTI VIHAR | CTS NO 740 PLOT NO 33 AND 34 WAGHOLI TALUKA - HAVELI PUNE - 412207 | 32 | Completed | May 2019 | Late, Jul 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TRIMURTI PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WAGHOLI TALUKA - HAVELI13,700+ in Pune
Filed coordinates, straight-line distance. 77 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: SIDDHANATH DEVELOPERS
SIDDHANATH DEVELOPERS has 2 registrations on MahaRERA, including SIddhanath apartment and TRIMURTI PARK. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that TRIMURTI PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TRIMURTI PARK is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TRIMURTI PARK?
The registered promoter entity is SIDDHANATH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TRIMURTI PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TRIMURTI PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TRIMURTI PARK?
The professionals named in the filing: Architect: CS ARCHITECTS; Engineer: VIKAS TRIMBAK KHARADKAR TRIMBAK KHARADKAR; Chartered Accountant: OMKAR U KHUDE AND COMPANY; Chartered Accountant: PARESH RATANLAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TRIMURTI PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback