Home / Browse projects / Mumbai Suburban, Maharashtra / TRIDEV ANUBHAV

Registered No litigation declared Residential / Group Housing project

TRIDEV ANUBHAV

By TRIDEV REALTY AND CONSTRUCTION PVT LTD

RG-MH-35700 · RERA P51800011760 · Last updated on MahaRERA portal: 17 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
6 of 11Construction stages donefurthest along: Staircases, 98%
40 of 87Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 295 documents Report an error

TRIDEV ANUBHAV is a Residential / Group Housing project by TRIDEV REALTY AND CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011760 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 47 of the 87 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameTRIDEV ANUBHAV
  • TypeResidential / Group Housing
  • Location
    • Near Moksh Mahal
    • Mulund West
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011760
  • ReraGenie IDRG-MH-35700

Builder

  • NameTRIDEV REALTY AND CONSTRUCTION PVT LTD
  • Entity typeCompany
  • Managing DirectorsDEEPAK MULCHAND GOSAR, MEHUL HARISH GOSAR, CHANDRAKANT RAVJI HARIA
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed295 files

Current status

54%47 of 87 units booked
56.2%Work done, per cost certificate

Figures as on 17 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANUBHAV CO-OP HSG SOC LTDNA262384387

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 98%.

ANUBHAV CO-OP HSG SOC LTD: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.81%

Progress on shared amenities15

As on 17 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered32
Open Space46

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,897 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority (SRA)
Permissible FSI10245.96
Proposed, not sanctioned4,029 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOLE BANGLOW N S ROAD MULUND WEST MUMBAI - 400080
Estimated costRs 30.59 cr
Cost incurredRs 17.20 cr
Work done56.23%
BuildingWingEstimatedIncurred
ANUBHAV CO-OP HSG SOC LTDNARs 26.39 crRs 16.00 cr
-NARs 4.20 crRs 1.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV S Vaidya And Associates
EngineerRajendra Paranjpe Advance Creative Design Consultancy
Chartered AccountantHimmat Shethia
Chartered AccountantMalay Furia
PartnerRole in project
TRIDEV REALTY AND CONSTRUCTION PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018453Dec 2023 → Dec 2024

Reason as filed by the promoterRCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th November-2023. In Light of the same we, M/s. Tridev Realty & Construction Private Limited Developer of the aforesaid project seek extension of one year for due date of completion of the project that is 29-Dec-2024. Self Declaration dated 25.12.2023 for extension of due date for the project “Tridev Anubhav" registered with MahaRERA vide registration Number P518000

EXT51800028009Dec 2023 → Dec 2025

Reason as filed by the promoterMore than 90% Construction work of the said project is completed as evidences by the latest Architect Certificate dated 05-04-2025. Other pending work viz. Tower Parking, C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2025. We have duly complied and updated and corrected the consent table other than existing members with stamp and signature of promoter on each page as annexed herein below. We request you to kindly approve the project completion date

EA27022620037Dec 2023 → Dec 2026

Reason as filed by the promoterMore than 95% Construction work of the said project is completed as evidenced by the latest Architect Certificate dated 07-04-2026. Other pending work viz. Tower Parking, Part of C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2026. Consent table in Format B other than existing members with stamp and signature of promoter on each page as annexed herein below. In light of the same we request you to kindly approve the project completion date up-to 31-De

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed295

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 295 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Scan_Tridev Anubhav Form 1_31-03-2025.pdf17 Feb 2026
Form 2File: Scan_Form 2_Anubhav_31-03-2025.pdf17 Feb 2026
Form 3File: Scan_Anubhav_Form 3 - CA Certificate_31-03-2025_compressed.pdf17 Feb 2026
Disclosure of Sold and Booked InventoryFile: Tridev Anubhav Disclosure Of Sold Inventories_31-03-2025.pdf17 Feb 2026
Withdrawal Update Form 1File: Scan_Form 1_30-06-2025 Anubhav.pdf17 Feb 2026
Withdrawal Update Form 1File: Scan_Form 1_Anubhav_30-09-2025.pdf17 Feb 2026
Withdrawal Update Form 1File: Scan_Anubhav_Form 1_31-12-2025.pdf17 Feb 2026
Withdrawal Update Form 2File: Scan_Form 2_Anubhav_30-06-2025.pdf17 Feb 2026
Withdrawal Update Form 2File: Scan_Form 2_Anubhav_30-09-2025.pdf17 Feb 2026
Withdrawal Update Form 2File: Scan_Form 2_Anubhav_31-12-2025.pdf17 Feb 2026
Withdrawal Update Form 3File: Scan_Anubhav_Form 3 - CA Certificate_30-06-2025_compressed.pdf17 Feb 2026
Withdrawal Update Form 3File: Scan_Anubhav_Form 3 - CA Certificate_30-09-2025_compressed.pdf17 Feb 2026
Withdrawal Update Form 3File: Scan_AnubhavForm 3 - CA Certificate_31-12-2025_compressed.pdf17 Feb 2026
Form 5 (FY 2024-2025)File: Scan_Form 5 - Anubhav FY 2024-2025.pdf14 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 - Anubhav FY 2023-2024.pdf14 Feb 2026
Form 5 (FY 2022-2023)File: Form 5 - Anubhav FY 2022-2023.PDF14 Feb 2026
Form 5 (FY 2021-2022)File: Scan_Form 5 - Anubhav FY 2021-2022.PDF14 Feb 2026
Form 1File: Form 1_31-12-2024.pdf13 Feb 2026
Form 2File: Scan_Form 2_31-12-24_Anubhav.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_31-12-2024_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Tridev Anubhav Disclosure 31-12-2024_compressed.pdf13 Feb 2026
Form 1File: Form 1 Anubhav_30-09-2024.pdf13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_30-09-2024.pdf13 Feb 2026
Form 3File: Form 3 Anubhav 30-09-2024_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Tridev Anubhav Disclosure of Sold Inventories.pdf13 Feb 2026
Form 1File: Form 1 Anubhav_30-06-2024.pdf13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_30-06-2024.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_30-06-2024_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Tridev Anubhav Disclosure of Sold Inventories.pdf13 Feb 2026
Form 1File: Form 1 Anubhav_31-03-24.pdf13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_31-03-2024.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_31-03-2024_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Tridev Anubhav Disclosure of Sold Inventories.pdf13 Feb 2026
Form 1File: Form 1 Anubhav_31-12-23.pdf13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_31-12-2023.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_31-12-2023_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Booked Inventory.PDF13 Feb 2026
Form 1File: Form 1_Anubhav_30-09-2023.PDF13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_30-09-2023.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_30-09-2023_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Booked Inventory.PDF13 Feb 2026
Form 1File: Form 1_Anubhav_30-06-2023.PDF13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_30-06-2023.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_30-06-2023_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Booked Inventory.PDF13 Feb 2026
Form 1File: Form 1_Anubhav_31-03-2023.PDF13 Feb 2026
Form 2File: Tridev Anubhav_Form 2_31-03-2023.pdf13 Feb 2026
Form 3File: Form 3 Anubhav_31-03-2023_compressed.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Booked Inventory.PDF13 Feb 2026
Form 1File: Form 1 Anubhav 31-12-2022.PDF13 Feb 2026
Form 2File: Form 2_31-12-2022 Anubhav.PDF13 Feb 2026
Form 3File: Form 3_31-12-2022.PDF13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Form 1 Anubhav 30-09-2022.PDF13 Feb 2026
Form 2File: Form 2_30-09-2022 Anubhav.PDF13 Feb 2026
Form 3File: Form 3_30-09-2022.PDF13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Form 1 Anubhav 30-06-2022.PDF13 Feb 2026
Form 2File: Form 2_30-06-2022 Anubhav.PDF13 Feb 2026
Form 3File: Form 3_30-06-2022.PDF13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Form 1 Anubhav 31-03-2022.PDF13 Feb 2026
Form 2File: Form 2_31-03-2022 Anubhav.PDF13 Feb 2026
Form 3File: Form 3_31-03-2022.PDF13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Form 1 Anubhav 31-12-2021.PDF13 Feb 2026
Form 2File: Form 2_31-12-2021 Anubhav.PDF13 Feb 2026
Form 3File: Form 3_31-12-2021.PDF13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Scan_Anubhav 30-09-2021_compressed.pdf13 Feb 2026
Form 2File: Form 2 30-09-2021 Anubhav CHS Ltd_compressed.pdf13 Feb 2026
Form 3File: Scan_Anubhav 30-09-2021 Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Scan_Anubhav 30-06-2021_compressed.pdf13 Feb 2026
Form 2File: Form 2 30-06-2021 Anubhav CHS Ltd_compressed.pdf13 Feb 2026
Form 3File: Scan_Anubhav 30-06-2021 Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Scan_Anubhav Disclosure of Sold Inventories.PDF13 Feb 2026
Form 1File: Scan_Anubhav 31-03-2021_compressed.pdf13 Feb 2026
Form 2File: Scan_Form - 2_Anubhav_31-03-2021.pdf13 Feb 2026
Form 3File: Scan_Anubhav 31-03-2021 Form 3.pdf13 Feb 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NANDJA CHS LTDNandja CHS ltd BPS Rd no 2 Mulund west Mumbai 40008015CompletedNov 2015Nov 2015

How this compares with Mumbai Suburban

54%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIDEV ANUBHAV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West6,700+ in Mumbai Suburban

2 kmTRIDEV ANUBHAVCompleted 106Lapsed / revoked 76Other 146Dot size: filed unitsN

Filed coordinates, straight-line distance. 328 registered projects within 2 km.

Builder: TRIDEV REALTY AND CONSTRUCTION PVT LTD

TRIDEV REALTY AND CONSTRUCTION PVT LTD has 3 registrations on MahaRERA, including BALAJI APARTMENT and TRIDEV ANUBHAV. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if TRIDEV ANUBHAV is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIDEV ANUBHAV?

The registered promoter entity is TRIDEV REALTY AND CONSTRUCTION PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIDEV ANUBHAV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRIDEV ANUBHAV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIDEV ANUBHAV?

The professionals named in the filing: Architect: V S Vaidya And Associates; Engineer: Rajendra Paranjpe Advance Creative Design Consultancy; Chartered Accountant: Himmat Shethia; Chartered Accountant: Malay Furia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIDEV ANUBHAV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIDEV ANUBHAV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIDEV ANUBHAV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.