Home / Browse projects / Pune, Maharashtra / TRIDENT C, D

Registration lapsed No litigation declared Residential / Group Housing project

TRIDENT C, D

By PARANJAPE SCHEMES (CONSTRUCTION) LTD

RG-MH-92668 · RERA P52100015697 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
13 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 75%
24 of 308Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

TRIDENT C, D is a Residential / Group Housing project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Pune, Maharashtra, registered with MahaRERA as P52100015697 on 16 Mar 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 284 of the 308 units on this registration are recorded sold or booked, and 13 of 22 construction stages are filed complete.

At a glance

Project

  • NameTRIDENT C, D
  • TypeResidential / Group Housing
  • Location
    • New Wakad - Hinjawadi Link Road
    • Wakad
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015697
  • ReraGenie IDRG-MH-92668

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LTD
  • Entity typeCompany
  • ChairpersonSHRIKANT PURUSHOTTAM PARANJAPE
  • Managing DirectorSHASHANK PURUSHOTTAM PARANJAPE
  • Other registrations28 more →
  • Completed15 of 29
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

10 months past promisethis monthRegisteredMar 2018First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Mar 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings2 building records
  • Documents filed99 files

Current status

92%284 of 308 units booked
72.0%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CNA23231740174
DNA23231340134

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 75%.

C77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
D75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)75%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes25%
Street LightingYes5%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed308

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots308
Closed/Covered308
BuildingClosed/CoveredTotal
C174174
D134134

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,397 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Dnyanoba Pandurang KalateWakadPune
Subhadra Dnyanoba KalateWakadPune
Tukaram Dnyanoba KalateWakadPune
Rupali Tukaram KalateWakadPune
Rajendra Shankar KalatePimpri Chinchawad (M Corp.)Pune
Sanjay Shankar KalatePimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI15357.08
Proposed, not sanctioned11,841 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLaukik Aparatment, Plot No 3 , Ground floor, Cts Number 870, Bhandarkar Road, Pune -411004
Estimated costRs 85.93 cr
Cost incurredRs 61.86 cr
Work done71.99%
BuildingWingEstimatedIncurred
CNARs 37.40 crRs 30.60 cr
DNARs 30.94 crRs 23.30 cr
-NARs 17.59 crRs 7.95 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchland Architects Pvt Ltd
EngineerDeepak Ramchandra Gaikwad
Chartered AccountantKapure and Kapure Chartered Accountant
PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016537Dec 2023 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19

EXT52100025850Dec 2023 → Dec 2025

Reason as filed by the promoterAS per attachment

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Trident CD.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Trident CD.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Trident CD.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Trident CD.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Trident CD.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Trident CD.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 Trident CD Dec25_compressed.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 Trident CD Dec25_compressed.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 Trident CD Dec25_compressed.pdf4 May 2026
Declaration in FORM BFile: Form B Affidavit_Trident C D.pdf4 Jun 2025
Certificates of CA (Form 3)File: Form 3 - March 2025_compressed.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booked.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident C D-Mar'25-uploaded.pdf8 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident C D-FORM 2-Mar'25-uploaded.pdf8 Apr 2025
Certificates of CA (Form 3)File: Signed Form 3 as on Dec 2024_Trident CD_compressed.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: Trident Revised - Manasi Maam.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-Trident CD-FY 22-23.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2a-Trident CD-FY 23-24.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 310323.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 300623.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 300923.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 310324.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 300624.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3 Trident CD 300924.pdf2 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Bank Account.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Trident C D.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera form2 Swaniketan DEC 24 Signoff-compressed-uploaded.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Trident CD Form02 Dec2024-compressed-uploaded.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident C D-Dec'24-uploaded.pdf15 Jan 2025
Declaration in FORM BFile: Form B-Trident C D-Exten.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory-Trident C D-Sept 24-uploaded.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident C D-Sept'24-uploaded.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident Bldg CD-Sept'24-uploaded.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Trident C D 30th june update uploaded.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Trident CD-FY 23-24-uploaded.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 26 Trident C D-FORM 1-June'24-uploaded.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Form 2 Triednt C D-June'24-uploaded.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: inventory Report-TRIDENT CD- 31st March 2024-uploaded.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident CD Bldg-Mar'24-uploaded.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Trident CD-Mar'24-uploaded.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident CD-Dec'23-uploaded.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident CD-Dec'23-uploaded.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident C D bldg-Sept'23-uploaded.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Trident CD-Fy'22-23-uploaded-11oct23.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident C D-Sept'23-uploaded.pdf6 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident C D Bldg-June'23.pdf7 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident C D-June 23.pdf6 Jul 2023
Details of encumbrancesFile: Encumbrance Letter-Dues-Trident C D-Promoter.pdf16 May 2023
Declaration in FORM BFile: FORM B-Affidavit-Promoter-Trident C D.pdf16 May 2023
Disclosure of sold/ booked inventoryFile: Trident C D-Disclosure of Inventory-May 2023.pdf16 May 2023
Disclosure of sold/ booked inventoryFile: Trident C D.pdf16 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident FORM 2A-FY 19-20.pdf10 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Trident -FORM 2A-FY 20-21.pdf10 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Trident -FORM 2A-F y 21-22.pdf10 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificates of CA FY 18-19-Trident CD.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Trident C , D.pdf17 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Trident CD -Form1-FY18-19-merged-compressed.pdf4 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Trident CD -Form 1-FY 19-20-merged-compressed.pdf4 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Trident CD -Form 1-FY-20-21-merged -compressed.pdf4 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Trident CD -Form 1-June Sept Dec 21-merged -compressed.pdf4 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Trident-C D RERA-Form 1- June 2022-uploded-compressed (1).pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Trident CD Form-2 March-18 To March-19-compressed.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Trident CD Form-2 June-19 To March-20.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Trident CD Form-2 June-20 To March-21 -compressed.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Trident CD Form-2 June-21 To March-22-compressed.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Trident CD Form-2 June-22.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Trident CD Form-2 Sept-22.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Trident C D Form-2 Dec-2022.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident C D QA year Mar 2019.pdf11 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident C D QA June 20 to Mar 21.pdf11 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident C D QA June 20 to Mar 21.pdf11 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident CD QA Apr 21 to Dec 21.pdf11 Feb 2022
Layout approvalFile: Trident sanction Layout 2021_compressed.pdf2 Feb 2022
Copy of Layout Approval (in case of layout)File: Trident sanction Layout 2021_compressed.pdf2 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: A 4Commencement Certificate31Dec2021.pdf2 Feb 2022
Declaration about Commencement CertificateFile: Format D-Trident C and D-Declaration of Commencement.pdf2 Feb 2022
CERSAI detailsFile: Trident _CERSAI _Report.pdf2 Feb 2022
CERSAI detailsFile: Trident CERSAI_Report_.pdf2 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Trident CD-min_compressed.pdf25 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 17 RERA Trident CD compressed.pdf1 Apr 2021

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
127 UPPER EASTP51800000454Andheri, Mumbai Suburban-Jul 2017CompletedJun 2024Registered original: Dec 2019Jan 1970
PRATHAM RESIDENTIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103035-CompletedApr 2016Mar 2016
THE BUSINESS HUBSURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 41102986-CompletedJan 2016Nov 2015
MADHUKOSH - IIISNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune258-CompletedAug 2015Aug 2015
PRATHAM COMMERCIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103032-CompletedJun 2015Apr 2015
PUNARVASUPRABHAT ROAD ERANDWANE PUNE 41100410-CompletedDec 2014Late, Jun 2015
MADHUKOSH - IISNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune150-CompletedDec 2013Oct 2013
MADHUKOSH - ISNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune289-CompletedMar 2012Feb 2012

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIDENT C, D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wakad13,700+ in Pune

2 kmTRIDENT C, DCompleted 105Lapsed / revoked 41Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 224 registered projects within 2 km.

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD

PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that TRIDENT C, D shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TRIDENT C, D is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIDENT C, D?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIDENT C, D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRIDENT C, D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIDENT C, D?

The professionals named in the filing: Architect: Archland Architects Pvt Ltd; Engineer: Deepak Ramchandra Gaikwad; Chartered Accountant: Kapure and Kapure Chartered Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIDENT C, D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIDENT C, D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIDENT C, D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.