TRIDENT BUSINESS PARK
By PARANJAPE SCHEMES (CONSTRUCTION) LTD
RG-MH-16407 · RERA P52100025946 · Last updated on MahaRERA portal: 26 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TRIDENT BUSINESS PARK is a Others project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Pune, Maharashtra, registered with MahaRERA as P52100025946 on 2 Aug 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 9 months from the original filing. 153 of the 208 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameTRIDENT BUSINESS PARK
- TypeOthers
- Location
- New Wakad -Hinjawadi Link Road
- Wakad
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100025946
- ReraGenie IDRG-MH-16407
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Aug 2020
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Sep 2025)
- Buildings1 building record
- Documents filed69 files
Current status
Figures as on 26 Sep 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Trident Commercial and MAHADA | NA | 19 | 19 | 146 | 62 | 208 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.
Trident Commercial and MAHADA: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 26 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed135
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership6
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Dnyanoba Pandurang kalate | Wakad | Pune |
| Subhadra Dnyyanoba Kalate | Wakad | Pune |
| Tukaram Dnyanoba kalate | Wakad | Pune |
| Rupali tukaram kalate | Wakad | Pune |
| Rajendra Shankar kalate | Wakad | Pune |
| Sanjay Shankar kalate | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Trident Commercial and MAHADA | NA | Rs 44.74 cr | Rs 33.05 cr |
| - | NA | Rs 9.24 cr | Rs 7.71 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Archland Architects Pvt Ltd |
| Engineer | Vijaykumar Salunkhe |
| Engineer | Chnadrashekhar |
| Engineer | Namita More |
| Chartered Accountant | Gosavi Yardi and Company |
| Chartered Accountant | Kapure and Kapure Chartered Accoutant |
| Partner | Role in project |
|---|---|
| PARANJAPE SCHEMES (CONSTRUCTION) LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We hereby state that an application for additional FSI was submitted by us, and the same was under consideration for a period of approximately one and a half years. However, due to our internal decision, we have chosen not to proceed further with the said application
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jul 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Trident Business Parku003dJuneu002725.pdf | 26 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 Trident Business Park-Juneu002725.pdf | 26 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3-TBP-Juneu002725 (1).pdf | 26 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business Park--mar'25-uploaded.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident Business Park-Mar'25-uploaded.pdf | 8 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Trident Business Park-uploaded.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Trident Busi Park-June '24-uploaded.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business Park-Dec'24-uploaded.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident Business Park-Dec'24-uploaded.pdf | 15 Jan 2025 |
| Layout approvalFile: Layout -Oct'24-Wakad.pdf | 8 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: Layout -Oct'24-Wakad.pdf | 8 Jan 2025 |
| Declaration about Commencement CertificateFile: Commencement 03-10-2024 Trident Wakad-uploaded.PDF | 8 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure- Trident Business Park-Sept'24-uploaded.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business Park-Sept'24-uploaded.pdf | 17 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident BP-Sept'24-uploaded.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Trident business park - 30th june update-uploaded.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Trident Business Park-FY23'24-uploaded.pdf | 8 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30 Form 2-Trident Business Park-uploaded.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 25 Trident Business park-FORM 1-June'24-uploaded.pdf | 4 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Report-Trident Business Park- 31st March 2024-uploaded.pdf | 19 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- Trident Business Park-Mar'24-uploaded.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Trident Business PArk-Mar'24-uploaded.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident Business Park-Dec'23-uploaded.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business Park-Dec'23-uploaded.pdf | 3 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Trident Business Park-Fy 22-23-uploaded.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Trident Business Park-Sept'23-uploaded.pdf | 11 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business Park-Sept'23-uploaded.pdf | 6 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2-Trident Business Park-June'23.pdf | 7 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Trident Business park -June 23.pdf | 6 Jul 2023 |
| Proforma of Agreement for saleFile: 1 6 Trident Business Park-Agreement to Sale-31 May 2023.pdf | 31 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Form 2 - Trident BP-Mar 2023-uplaoded.pdf | 8 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Trident Business Park.pdf | 20 Feb 2023 |
| Declaration about Commencement CertificateFile: 3Trident Business Park -Form 2 March-2022.pdf | 4 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Trident Businee Park-FPRM 1-Sept 20 to Mar 21-merged -compressed.pdf | 4 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Trident Business Park-Form 1-June 21 to Mar 22-merged -compressed.pdf | 4 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Trident Business Park-RERA-Form 1- June 2022-uploaded.pdf | 4 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Trident Business Park- RERA-Form 1- Sept 22-uploaded.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Trident Business Park -Form 2 Sep-2020 to Dec-2020.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Trident Business Park-Form 2 March-2021 to Dec-2021.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3Trident Business Park -Form 2 March-2022.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4Trident Business Park- Form 2 June -2022.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Trident Business Park- Form 2 Sep -2022.pdf | 4 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Trident Business Park-Form 2 Dec-2022.pdf | 4 Feb 2023 |
| Copy of the legal title reportFile: Title certificate- Trident Buisness park-Change of name-Feb 2022.pdf | 7 Apr 2022 |
| Layout approvalFile: Trident sanction Layout 2021_compressed.pdf | 2 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: Trident sanction Layout 2021_compressed.pdf | 2 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: A 4Commencement Certificate31Dec2021.pdf | 2 Feb 2022 |
| Declaration about Commencement CertificateFile: Format D- Declaration of Commencement- Trident Comm MHADA.pdf | 2 Feb 2022 |
| CERSAI detailsFile: Trident _CERSAI _Report.pdf | 31 Jan 2022 |
| CERSAI detailsFile: Trident Enhancement_CERSAI_Report.pdf | 31 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf | 3 Nov 2021 |
| Declaration about Commencement CertificateFile: Trident Comm MHADA -Format D of Circular 32.pdf | 25 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A Sept2021 Trident Comm MHADA.pdf | 25 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Trident Commercial and Mhada compressed.pdf | 25 Oct 2021 |
| Proforma of Allotment letterFile: TRIDENT COMM MHADA_AGR FOR SALE -FINAL_15-03-2021 uploaded 22Mar2021.pdf | 22 Mar 2021 |
| Layout approvalFile: Trident Comm rev layout R2.pdf | 9 Oct 2020 |
| Copy of Layout Approval (in case of layout)File: Trident Comm rev layout R2.pdf | 9 Oct 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Trident Comm Revised Commencement 26Aug2020 compressed.pdf | 9 Oct 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Trident Comm Quality Assurance Certificate.pdf | 9 Oct 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trident Form 3 FINAL RERA compressed.pdf | 25 Jul 2020 |
| Layout approvalFile: Trident Sanction MHADA Commercial RERA Regn new.pdf | 17 Jul 2020 |
| Building plan approvalFile: Trident Sanction MHADA Commercial RERA Regn new.pdf | 17 Jul 2020 |
| Copy of Layout Approval (in case of layout)File: Trident Sanction MHADA Commercial RERA Regn new.pdf | 17 Jul 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Trident Sanction MHADA Commercial RERA Regn new.pdf | 17 Jul 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Comm Certi Trident Comm MHADA New RERA Regn.pdf | 17 Jul 2020 |
| Copy of the legal title reportFile: Trident Comm MHADA Title Certificate.pdf | 13 Jul 2020 |
| Details of encumbrancesFile: Trident Comm MHADA Encumbrance.pdf | 13 Jul 2020 |
| Declaration in FORM BFile: Trident Comm MHADA Form B Promoter.pdf | 13 Jul 2020 |
| Proforma of Allotment letterFile: Trident Comm MHADA Allotment Ltr ATS compressed.pdf | 13 Jul 2020 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| 127 UPPER EASTP51800000454 | Andheri, Mumbai Suburban | - | Jul 2017 | Completed | Jun 2024Registered original: Dec 2019 | Jan 1970 |
| PRATHAM RESIDENTIAL | 727 SADASHIV PETH KUMTHEKAR ROAD PUNE 411030 | 35 | - | Completed | Apr 2016 | Mar 2016 |
| THE BUSINESS HUB | SURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 411029 | 86 | - | Completed | Jan 2016 | Nov 2015 |
| MADHUKOSH - III | SNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune | 258 | - | Completed | Aug 2015 | Aug 2015 |
| PRATHAM COMMERCIAL | 727 SADASHIV PETH KUMTHEKAR ROAD PUNE 411030 | 32 | - | Completed | Jun 2015 | Apr 2015 |
| PUNARVASU | PRABHAT ROAD ERANDWANE PUNE 411004 | 10 | - | Completed | Dec 2014 | Late, Jun 2015 |
| MADHUKOSH - II | SNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune | 150 | - | Completed | Dec 2013 | Oct 2013 |
| MADHUKOSH - I | SNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune | 289 | - | Completed | Mar 2012 | Feb 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 28 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep TRIDENT BUSINESS PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Wakad13,700+ in Pune
Filed coordinates, straight-line distance. 433 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD
PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that TRIDENT BUSINESS PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TRIDENT BUSINESS PARK is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TRIDENT BUSINESS PARK?
The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TRIDENT BUSINESS PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TRIDENT BUSINESS PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TRIDENT BUSINESS PARK?
The professionals named in the filing: Architect: Archland Architects Pvt Ltd; Engineer: Vijaykumar Salunkhe; Engineer: Chnadrashekhar; Engineer: Namita More; Chartered Accountant: Gosavi Yardi and Company; Chartered Accountant: Kapure and Kapure Chartered Accoutant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TRIDENT BUSINESS PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback