Home / Browse projects / Mumbai City, Maharashtra / TRANQUIL BAY

Completed No litigation declared Residential / Group Housing project

TRANQUIL BAY

By SURAJ ESTATE DEVELOPERS LTD

RG-MH-20978 · RERA P51900003689 · Last updated on MahaRERA portal: 26 Jul 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
1Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

TRANQUIL BAY is a Residential / Group Housing project by SURAJ ESTATE DEVELOPERS LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900003689 on 6 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTRANQUIL BAY
  • TypeResidential / Group Housing
  • Location
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900003689
  • ReraGenie IDRG-MH-20978

Builder

  • NameSURAJ ESTATE DEVELOPERS LTD
  • Entity typeCompany
  • CINU99999MH1986PTC040873
  • GSTIN27AAACS8375H1Z0
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorTHOMAS RAJAN
  • Other registrations14 more →
  • Completed4 of 15
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRANQUIL BAYNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

TRANQUIL BAY: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 26 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered1
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area796 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2625.32
Proposed, not sanctioned2,425 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWORLI MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUNIL AMBRE AND ASSOCIATES
EngineerDR KELKAR DESIGNS PVT LTD
PartnerRole in project
SURAJ ESTATE DEVELOPERS LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900000994Dec 2018 → Dec 2019

Reason as filed by the promoterWe have constructed the building “Tranquil Bay” consists of Stilt, 1st floor podium parking and 2nd to 18th floor and part 19th floor as habitable floors. The building is complete in all aspects and Part Occupancy Certificate bearing No.EB/3281/GN/A dated 18th December 2017 from MCGM is obtained upto 11th floor. We are now in the process of obtaining CFO NOC and permissions from other authorities with a view to obtain Full Occupation Certificate. The delay in giving possession of the remaining flats to clients from 10th to 19th floor is due to compliance of IOD conditions of MCGM for issuance

Litigation declared1

CaseCourtStatus
968 OF 2011/2011CITY CIVIL COURT MUMBAIPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000057349MR. MEGHNATH SHAMRO GAWADMR. THOMAS RAJAN07/01/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Dec 2022

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf26 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1181 82 Form1.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineer Certificate.pdf26 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Inventory.pdf26 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Drawing (1)_compressed.pdf15 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Letter.pdf15 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AR CER.pdf5 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5 - FP 1181-min.pdf10 Mar 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Letter 2017.pdf7 Jul 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Letter 2019.pdf7 Jul 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf7 Jul 2020
Certificates of CA (Form 5)File: Form 5 - Tranquil bay.pdf26 Dec 2018
OtherFile: 1181 - OC Letter.pdf24 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate 1181 82.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FP 1181 1182.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA cert Tranqil Bay.pdf28 Jul 2017
Details of encumbrancesFile: 1181 82.pdf27 Jul 2017
Declaration in FORM BFile: Form-B.pdf27 Jul 2017
Proforma of Allotment letterFile: Receipt-cum-Allotment Letter_1181-1182.pdf27 Jul 2017
Proforma of Allotment letterFile: Final RERA Agreement 1181 and 1182.pdf27 Jul 2017
PAN CardFile: Pan card.pdf26 Jul 2017
Copy of the legal title reportFile: Title certicate page 1.pdf26 Jul 2017
Copy of the legal title reportFile: Title certicate page 2.pdf26 Jul 2017
Copy of the legal title reportFile: Title certicate page 4.pdf26 Jul 2017
Copy of the legal title reportFile: Title certicate page 3.pdf26 Jul 2017
Copy of the legal title reportFile: Title certicate page 5.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-2008 (1).pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-2008(2).pdf26 Jul 2017
Building plan approvalFile: Binder2.pdf25 Jul 2017
Building plan approvalFile: Binder1.pdf25 Jul 2017
Building plan approvalFile: 5.pdf25 Jul 2017
Layout approvalFile: 1 A.pdf25 Jul 2017
Building plan approvalFile: 2 A.pdf25 Jul 2017
Building plan approvalFile: 3.pdf25 Jul 2017
Building plan approvalFile: 1.pdf25 Jul 2017
Building plan approvalFile: 4.pdf25 Jul 2017
Building plan approvalFile: 2.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: 1 A.pdf25 Jul 2017
Building Plan Approval (IOD)File: 1.pdf25 Jul 2017
Building Plan Approval (IOD)File: 2.pdf25 Jul 2017
Building Plan Approval (IOD)File: 2 A.pdf25 Jul 2017
Building Plan Approval (IOD)File: 3.pdf25 Jul 2017
Building Plan Approval (IOD)File: 4.pdf25 Jul 2017
Building Plan Approval (IOD)File: 5.pdf25 Jul 2017
Building Plan Approval (IOD)File: Binder1.pdf25 Jul 2017
Building Plan Approval (IOD)File: Binder2.pdf25 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PALETTEP51900008207DADAR-WEST, Mumbai City152Aug 2017OngoingDec 2025Registered original: Jun 2023Not delivered
HALLMARKCS 104 BHIMWADI WADALA EAST MUMBAI7-CompletedJul 2016Late, Nov 2016
ETERNITY APARTMENTFP 469 MMC CROSS ROAD MAHIM WEST MUMBAI 40001616-CompletedAug 2011Aug 2011
PARK SIDEFP 888 DATTA RAUL ROAD DADAR WEST MUMBAI 40002828-CompletedJul 2010Late, Feb 2011

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 12 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRANQUIL BAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GNorth-400028780+ in Mumbai City

2 kmTRANQUIL BAYCompleted 48Lapsed / revoked 51Other 73Dot size: filed unitsN

Filed coordinates, straight-line distance. 172 registered projects within 2 km.

Builder: SURAJ ESTATE DEVELOPERS LTD

SURAJ ESTATE DEVELOPERS LTD has 15 registrations on MahaRERA, including ST ANTHONY APARTMENT and TRANQUIL BAY. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if TRANQUIL BAY is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRANQUIL BAY?

The registered promoter entity is SURAJ ESTATE DEVELOPERS LTD, a company as per the filing. Its CIN U99999MH1986PTC040873 and GSTIN 27AAACS8375H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRANQUIL BAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TRANQUIL BAY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TRANQUIL BAY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRANQUIL BAY?

The professionals named in the filing: Architect: SUNIL AMBRE AND ASSOCIATES; Engineer: DR KELKAR DESIGNS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRANQUIL BAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRANQUIL BAY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRANQUIL BAY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.